To resolve the problem, Quang Ngai is determined to bring the VND204,400 billion expressway to the finish line on time

VIÊN NGUYỄN |

Quang Ngai - Quang Ngai - Hoai Nhon Expressway is at the completion stage, the Provincial Chairman has directed to resolutely remove obstacles, committing to opening the route on August 30, 2025.

On August 6, Mr. Nguyen Hoang Giang - Chairman of the People's Committee of Quang Ngai province - chaired a working session with units and localities to direct the removal of some obstacles related to the Quang Ngai - Hoai Nhon component project of the North - South Expressway Construction Project in the East, phase 2021 - 2025.

The component project of the Quang Ngai - Hoai Nhon section is 88km long, of which the section through Quang Ngai province is 60.3km long.

Up to now, the main items have been basically completed such as roadbed construction, tunnel 1 and tunnel 2.

Of the total 77 bridges on the route, 70 bridges have been installed with girders and are under construction. The project is entering the finishing stage.

Cong nhan thi cong vao ban dem tren du an cao toc Quang Ngai - Hoai Nhon. Anh: Vien Nguyen
Workers work at night on the Quang Ngai - Hoai Nhon expressway project. Photo: Vien Nguyen

To ensure progress, contractors have mobilized 3,450 engineers, workers and more than 1,400 machines and equipment. However, the general progress is still affected by some problems in compensation and site clearance at 7 locations under the overpass and intersection packages...

At the meeting, the authorities of the relevant communes said that they have actively coordinated with contractors and construction units to mobilize and explain to the people.

Many households have agreed and pledged not to hinder the construction work. In Nguyen Nghiem commune alone, the government has established 2 working groups to completely resolve the remaining problems. Up to now, 4/5 households with problems have received compensation and committed not to hinder the construction.

Speaking at the meeting, Mr. Nguyen Hoang Giang acknowledged and highly appreciated the sense of responsibility, the active coordination between departments, branches, localities and contractors in the past time.

At the same time, he emphasized that the remaining workload is currently very small, but he requested that the forces, commune authorities, investors, and contractors continue to promote a high spirit of solidarity and unity, join in speeding up the construction progress, and commit to opening the route no later than August 30.

Mr. Nguyen Hoang Giang requested the Chairmen of the People's Committees of relevant communes and wards to clearly identify the common goal, consider this an important political task, focus resources, uphold the sense of responsibility, and be determined in directing and operating.

In addition, we must be close to the people, close to the people, strengthen propaganda and mobilization work so that people understand and share. At the same time, it is necessary to transparently publicize the plan, level of damage, compensation and have a specific commitment to the people to create consensus.

Mr. Nguyen Hoang Giang requested that units report daily implementation progress to the Provincial People's Committee to promptly direct the removal of difficulties and obstacles when exceeding their authority.

VIÊN NGUYỄN
RELATED NEWS

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

|

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Quang Ngai to completely handle the existence of the Quang Ngai - Hoai Nhon expressway before June 30

|

Quang Ngai - Resolutely remove obstacles and completely handle existing problems related to the Quang Ngai - Hoai Nhon Expressway before June 30

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

|

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Container truck catches fire on My Phuoc - Tan Van road in Ho Chi Minh City

|

HCMC - A container truck caught fire on My Phuoc - Tan Van road. The authorities quickly put out the fire and regulated traffic.

20h News: People complain about the sudden increase in electricity bills in July despite being absent

|

People complain about the sudden increase in electricity bills in July despite being absent; The Ministry of Home Affairs responds to recommendations on the arrangement of concurrent commune accountants...

Early resignation is no longer a strategic move for Ms. Paetongtarn

|

August is considered a turning point in the political fortunes of Ms. Paetongtarn Shinawatra and Mr. Thaksin Shinawatra.

In the next 4 days, many streets in Hanoi will ban vehicles from circulating during certain time frames

|

Hanoi - Some routes will completely ban vehicles from circulating during certain time frames (from August 7 to August 10, 2025).

There are projects of thousands of hectares abandoned for 20 years but the State has not collected anything

|

According to Mr. Le Dinh Thang - Chief Auditor of the State Audit Office, Sector 2, there are projects of thousands of hectares that have been abandoned for 20 years but the State has not collected anything.

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

VIÊN NGUYỄN |

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Quang Ngai to completely handle the existence of the Quang Ngai - Hoai Nhon expressway before June 30

VIÊN NGUYỄN |

Quang Ngai - Resolutely remove obstacles and completely handle existing problems related to the Quang Ngai - Hoai Nhon Expressway before June 30

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

VIÊN NGUYỄN |

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.