Exceeding the progress of Van Phong - Nha Trang Expressway

Hữu Long |

Khanh Hoa - Van Phong - Nha Trang Expressway is basically completed, meeting the schedule, the construction value according to the contract reached about 90%.

In March 2025, Project Management Board 7 (Ministry of Construction) reported on the expressway section Van Phong - Nha Trang with a total length of more than 83km, starting at the southern gate of Co Ma tunnel, ending at the starting point of the expressway section Nha Trang - Cam Lam; passing through 4 districts and towns including: Van Ninh, Ninh Hoa, Khanh Vinh and Dien Khanh.

Cao toc doan Van Phong - Nha Trang co tong chieu dai hon 83 km, tong muc dau tu du an hon 11.800 ti dong. Anh: Huu Long
The Van Phong - Nha Trang expressway section has a total length of more than 83km, with a total investment of more than 11,800 billion VND. Photo: Huu Long

Currently, the investor has completed 70/83km and is completing procedures to put it into operation on April 30, 2025.

The total construction output of the project reached 91% of the contract value, about 11:00 ahead of schedule.

Chu dau tu va cac nha thau quyet tam phan dau hoan thanh cong trinh vao dip 30.4 theo chi dao cua Thu tuong Chinh phu. Anh: Huu Long
The investor and contractors are determined to strive to complete the project by April 30 according to the direction of the Prime Minister. Photo: Huu Long

For the remaining section (13km), the progress is currently slower than the completion plan on April 30, 2025. The reason for the delay is due to unfavorable weather conditions. From this reality, construction units are making efforts to complete the main route on April 30 and complete the entire route in June 2025.

The Van Phong - Nha Trang Expressway will have 1 rest stop at Km334+900.

For this, the Vietnam Expressway Administration (now the Vietnam Road Administration) has approved the investor selection results.

Ban Quan ly du an 7 cho biet tien do thi cong toan du an dang vuot khoang 8 thang so voi tien do theo hop dong. Anh: Huu Long
Project Management Board 7 said that the construction progress of the entire project is about 8 months ahead of the contracted schedule. Photo: Huu Long

Regarding the ITS system (smart communication), ETC and mobile vehicle weight weighting system, the Ministry of Transport (now the Ministry of Construction) has approved the basic design of the ITS, ETC systems and vehicle weight control stations of the Project.

Currently, the investor is implementing the selection of design consultants and consultants for reviewing the design steps to be implemented after the basic design. It is expected that the design work will be completed in May 2025 to select a contractor, implement the construction, and be completed in December 2025.

Gia tri xay lap doi voi cao toc Van Phong - Nha Trang theo hop dong dat khoang 90%, vuot tien do so voi yeu cau. Anh: Huu Long
The construction value of the Van Phong - Nha Trang expressway under the contract reached about 90%, exceeding the required progress. Photo: Huu Long
Hữu Long
RELATED NEWS

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

|

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.

3 provinces are allocated additional central capital for expressway construction

|

According to the direction of the Prime Minister, the three provinces of Ha Giang, Tuyen Quang and Dong Thap will be allocated additional central capital for expressway construction.

The billion-dollar expressway in the West is urgently reaching the finish line in 2026

|

The Western region - Chau Doc - Can Tho - Soc Trang Expressway, a key project is being urgently constructed to complete in 2026.

Olympic gold medalist receives a bonus of 3.5 billion VND

|

For the first time in history, athletes who win Olympic gold medals will receive special treatment, reflecting the true value of high-performance sports.

Mr. Maduro escorted by the US by helicopter to court

|

On the morning of January 5, Venezuelan President Nicolas Maduro was preparing to enter a hearing in New York, on drug charges.

Electricity consumption deviates from GDP growth: Statistics Department explains the reason

|

GDP in 2025 grew at a high level of 8.02%, but the total commercial electricity output of the entire system only increased by 4.9%, much lower than the previous year.

Suoi Sap is encroached upon, people worry about landslides

|

Son La - People in Long Sap commune are worried about the situation of soil and rock encroachment on the Sap stream, causing the flow to narrow, risk of landslides, and unsafety during the rainy and flood season.

Houses in Hanoi emit many explosions and then catch fire, 3 people injured and killed

|

Hanoi - The 2nd floor of a house in a residential area suddenly caught fire after many loud explosions. Initial determination shows 3 casualties.

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.

3 provinces are allocated additional central capital for expressway construction

Xuyên Đông |

According to the direction of the Prime Minister, the three provinces of Ha Giang, Tuyen Quang and Dong Thap will be allocated additional central capital for expressway construction.

The billion-dollar expressway in the West is urgently reaching the finish line in 2026

PHƯƠNG ANH |

The Western region - Chau Doc - Can Tho - Soc Trang Expressway, a key project is being urgently constructed to complete in 2026.