Cutting hills and mountains to build a 300 billion VND road in Yen Bai

Trần Bùi |

Dozens of workers and machines are working hard to bring the route connecting Nguyen Tat Thanh Street to Au Co Street (Yen Bai City) to the finish line on schedule.

Dynamic urban development project - Yen Bai City sub-project - Construction of the road connecting Nguyen Tat Thanh street to Au Co street invested by Yen Bai Provincial Construction Investment Project Management Board.

The route is about 4.2km long, constructed by a consortium of Nam Phong Investment, Construction and Trading Joint Stock Company, Yen Bai Traffic Construction Joint Stock Company and Thanh Trung Construction and Trading Company Limited, with a total investment of nearly 300 billion VND. Construction started in December 2022 and is expected to be completed in April 2025.

Anh: Tran Bui
The route has a total investment capital of nearly 300 billion VND. Photo: Tran Bui

According to Lao Dong's report on October 5, under the scorching sun, at the construction site of the road connecting Nguyen Tat Thanh Street to Au Co Street, dozens of workers and many heavy machines are still working hard to bring the project on schedule.

Ms. Tran Hong Hanh (32 years old, Tan Thinh, Yen Bai city) said that people have high expectations for this road to be completed soon.

"First, the route will make my family and I's travel much more convenient. At the same time, this new road will significantly shorten travel time from home to the city center," said Ms. Hanh.

He thong ha tang tren tuyen duong dang duoc hoan thien. Anh: Tran Bui
The infrastructure system on the route is being completed. Photo: Tran Bui

Speaking with Lao Dong, Mr. Doan Van Hai - project manager said that according to the contract, the route is expected to be completed in April 2025.

"The unit is striving to take advantage of favorable weather to pave the entire road surface by December 2024. Currently, the total completed work volume has reached more than 60%," said Mr. Hai.

He thong cong thoat nuoc da duoc hoan thien. Anh: Tran Bui
The drainage system has been completed. Photo: Tran Bui

According to Director of Nam Phong Construction Investment and Trading Joint Stock Company Tuong Duc Cuong, the construction site of the road mostly passes through mountainous terrain.

"The route is 4.2km long, but more than 3km of it had to be cut through mountains and hills for construction. Despite the difficult terrain, with the spirit of completing the project on schedule, the team of officers and workers at the construction site are always enthusiastic about their work," Mr. Cuong shared.

Don vi thi cong tren doc nui cheo leo. Anh: Tran Bui
Construction unit on steep mountain slope. Photo: Tran Bui
Ha tang dang sap duoc don vi thi cong hoan thien.
The infrastructure is about to be completed by the construction unit.

According to research, the project to comprehensively develop dynamic urban areas has been implemented in Yen Bai City since 2019 with a total investment of 63.27 million USD, equivalent to more than 1,423 billion VND. Of which, the loan capital from the World Bank (WB) is 39.46 million USD, equivalent to 888 billion VND and domestic counterpart capital is 23.81 million USD, equivalent to 535 billion VND.

The road connecting Au Co Street and Nguyen Tat Thanh Street is a sub-project of Yen Bai City.

May moc hang nang duoc huy dong tren cong truong.
Heavy machinery was mobilized on the construction site.
,a
The route will start construction in December 2022.
v
And expected to be completed in December 2024.
Vi tri tuyen duong.
Route location.

Trần Bùi
RELATED NEWS

A ward in Hanoi resolves land procedures overdue for 134 days, must apologize to citizens

|

Hanoi - Long Bien Ward is assessed as still having shortcomings and limitations when resolving administrative procedures on land, including dossiers that are overdue for 134 days.

Prenn Pass road closed in Da Lat for 6 days to repair landslide site

|

Lam Dong - Functional agencies decided to close Prenn Pass road for 6 days to repair and fix damaged points caused by previous landslides.

Forecast of the time to end widespread severe cold in the North

|

According to a representative of the meteorological agency, it is forecast that widespread severe cold and frost in the North will last until about January 10, to prevent frost and frost in mountainous areas.

Ho Chi Minh City launches campaign to handle sidewalk and roadway encroachment throughout the area

|

Ho Chi Minh City is deploying a peak period of inspection and handling of sidewalk and roadway encroachment throughout the area to restore urban order.

A restaurant yacht catches fire on the Saigon River

|

Ho Chi Minh City - Restaurant yacht on Saigon River suddenly catches fire, functional forces are controlling the fire.

Construction of 223 billion VND commercial center in Yen Bai is about to start

Trần Bùi |

The Go! Yen Bai Commercial Center project with a total investment of 223 billion VND will start construction on October 5.

Two intersections connecting Yen Bai city with Noi Bai - Lao Cai highway

Trần Bùi |

The two IC 12 and IC 13 intersections that have been and will be completed soon play a particularly important role in connecting Yen Bai City with the Noi Bai - Lao Cai highway.

Image of Yen Bai mountain town escaping the risk of flooding for the second time

Trần Bùi |

Yen Bai - After moving their belongings all night, people in the mountain town breathed a sigh of relief when they did not have to witness "flood upon flood".