Digging mountains and filling fields to build roads costs more than 50 billion VND/km in Tuyen Quang

Việt Bắc |

After nearly 3 years of digging mountains and filling fields, the nearly 9km long road connecting Tuyen Quang - Phu Tho expressway with National Highway 2D is gradually taking shape.

The road project from My Lam Mineral Spring Tourist Area to National Highway 2D connecting to Tuyen Quang – Phu Tho Expressway is 8.9 km long with a total investment of over 487 billion VND. This is a newly opened road, designed to urban standards.

The project, invested by the Department of Transport of Tuyen Quang province, started construction at the end of 2021. It is expected to be completed and put into use in early 2025.

Recorded on October 18, after nearly 3 years of implementation, most of the entire length of the route has been formed. At locations where the roadbed has been handed over, construction is underway.

Along the entire route, about 4 km of roadbed construction and first layer of asphalt concrete have been completed. Lighting, sidewalks, drainage ditches and underground sewer systems through residential areas continue to be completed.

Due to the length of the newly opened route and the fact that it mainly passes through fields, hills and mountains with complex geological conditions, the construction has to be extended. Currently, some rocky mountain locations are still undergoing blasting and rock breaking to create a flat surface.

Mot doan tuyen dang trong giai doan hoan thien. Anh: Viet Bac.
A section of the route is under construction. Photo: Viet Bac.

Mr. La Van Khoa, Nhu Han commune (Yen Son district) is one of the first households to hand over the land for project construction. Up to now, the family is building a new house not far from the old place.

"The compensation policy is reasonable, so my family agreed immediately. With this route, traveling is more convenient. Hopefully, the economy will develop and people's lives will become better," said Mr. Khoa.

According to the investor, to implement the project, 209 households and individuals had their land reclaimed with a total reclaimed area of ​​20.1 hectares. Up to now, the inventory of land area and assets on land has been completed, there are currently 14 households in Tuyen Quang City with 0.6 hectares that have not been cleared.

Speaking to reporters, Mr. Nguyen Huu Phuong - Chairman of Yen Son District People's Committee said that the project passes through the area with a length of more than 3 km. The site clearance work was completed at the end of February 2024.

"The route is expected to promote economic development, especially the My Lam mineral spring tourist area, so it has received unanimous support from the people. Up to now, households whose land was recovered are gradually stabilizing their lives," Mr. Phuong informed.

Some recorded images:

Gan 4 km da duoc tham nhua lop 1, tuyen duong mo moi di qua dia hinh doi nui, dong ruong. Anh: Viet Bac.
Nearly 4 km has been paved with the first layer of asphalt, the newly opened road passes through mountainous terrain and rice fields. Photo: Viet Bac.
Tuyen duong thiet ke theo tieu chuan duong do thi mien nui, ha tang dong bo. Anh: Viet Bac.
The route is designed according to urban mountain road standards, with synchronous infrastructure. Photo: Viet Bac.
Mot so vi tri dang trong giai doan hoan thien cac hang muc phu tro. Anh: Viet Bac.
Auxiliary items are being completed. Photo: Viet Bac.
Nhung vi tri di qua dia hinh doi nui phuc tap don vi thi cong phai tien hanh no min, pha da tao mat bang. Anh: Viet Bac.
In locations that pass through complex mountainous terrain, construction units must use blasting and rock breaking to create a flat surface. Photo: Viet Bac.
Khi hoan thanh dua vao su dung tuyen duong nang cao hieu qua ket noi cao toc Tuyen Quang - Phu Tho, thuc day phat trien kinh te, du lich. Anh: Viet Bac.
When completed and put into use, the route will improve the efficiency of the Tuyen Quang - Phu Tho expressway connection, promoting economic and tourism development. Photo: Viet Bac.
Việt Bắc
RELATED NEWS

Lao Cai's 100 billion dong road misses finish line due to iron ore discovery

|

Lao Cai - After 1 year of implementation, the road connecting Provincial Road 151 with Noi Bai - Lao Cai Expressway with a total investment of 115 billion VND could not be completed on time due to the discovery of iron ore.

$60 million diamonds and valuable items just stolen from the Louvre Museum

|

Le Parisien newspaper cited an initial investigation revealing 9 valuable items that the group of thieves broke into the Louvre Museum in Paris and stole.

The case of a stepfather brutally beating a 10-year-old girl: Information from a boarding house

|

Ha Tinh - A 10-year-old girl in Co Dam commune was brutally abused by her stepfather, using a hammer to hit her head and had to be hospitalized, but the neighbors did not hear her crying.

The career of the musician "Red Flower Time" before passing away

|

The name of musician Nguyen Dinh Bang is associated with many songs such as "Thoi Hoa Thuong", "Con mua em bat ngo"...

Requirement for effective management of the gold market for socio-economic development

|

Faced with the complicated developments of the gold market, the National Assembly's Economic and Financial Committee requires effective management to develop the socio-economy in 2026.

Japanese policy reverses, paving the way for the first female prime minister

|

Ms. Sanae Takaichi is about to become Japan's first female prime minister thanks to a political alliance agreement formed at the last minute.

The US tightens taxes, Chinese companies sell more

|

President Trump's new tariff has prompted major US technology companies to rush to order robot components from China for storage.

The Prime Minister requested an assessment of staff streamlining and salary reform

|

The Prime Minister requested an assessment of administrative reform, staff streamlining associated with improving the quality of the staff and salary reform.

Lao Cai's 100 billion dong road misses finish line due to iron ore discovery

Đinh Đại |

Lao Cai - After 1 year of implementation, the road connecting Provincial Road 151 with Noi Bai - Lao Cai Expressway with a total investment of 115 billion VND could not be completed on time due to the discovery of iron ore.

Kỷ luật loạt cán bộ ở Thái Nguyên liên quan đường trăm tỉ

Nhóm PV |

Loạt cán bộ và nguyên lãnh đạo của TP Sông Công, Thái Nguyên bị xem xét, xử lý kỷ luật.

Xẻ núi lấp ruộng làm tuyến đường nghìn tỉ ở Thái Nguyên

Nguyễn Tùng |

Sau gần 2 năm xẻ núi, lấp ruộng thi công đêm ngày, tuyến đường 3.800 tỉ đồng kết nối các tỉnh Thái Nguyên - Bắc Giang - Vĩnh Phúc đã hình thành.