Digging mountains and filling fields to build roads costs more than 50 billion VND/km in Tuyen Quang

Việt Bắc |

After nearly 3 years of digging mountains and filling fields, the nearly 9km long road connecting Tuyen Quang - Phu Tho expressway with National Highway 2D is gradually taking shape.

The road project from My Lam Mineral Spring Tourist Area to National Highway 2D connecting to Tuyen Quang – Phu Tho Expressway is 8.9 km long with a total investment of over 487 billion VND. This is a newly opened road, designed to urban standards.

The project, invested by the Department of Transport of Tuyen Quang province, started construction at the end of 2021. It is expected to be completed and put into use in early 2025.

Recorded on October 18, after nearly 3 years of implementation, most of the entire length of the route has been formed. At locations where the roadbed has been handed over, construction is underway.

Along the entire route, about 4 km of roadbed construction and first layer of asphalt concrete have been completed. Lighting, sidewalks, drainage ditches and underground sewer systems through residential areas continue to be completed.

Due to the length of the newly opened route and the fact that it mainly passes through fields, hills and mountains with complex geological conditions, the construction has to be extended. Currently, some rocky mountain locations are still undergoing blasting and rock breaking to create a flat surface.

Mot doan tuyen dang trong giai doan hoan thien. Anh: Viet Bac.
A section of the route is under construction. Photo: Viet Bac.

Mr. La Van Khoa, Nhu Han commune (Yen Son district) is one of the first households to hand over the land for project construction. Up to now, the family is building a new house not far from the old place.

"The compensation policy is reasonable, so my family agreed immediately. With this route, traveling is more convenient. Hopefully, the economy will develop and people's lives will become better," said Mr. Khoa.

According to the investor, to implement the project, 209 households and individuals had their land reclaimed with a total reclaimed area of ​​20.1 hectares. Up to now, the inventory of land area and assets on land has been completed, there are currently 14 households in Tuyen Quang City with 0.6 hectares that have not been cleared.

Speaking to reporters, Mr. Nguyen Huu Phuong - Chairman of Yen Son District People's Committee said that the project passes through the area with a length of more than 3 km. The site clearance work was completed at the end of February 2024.

"The route is expected to promote economic development, especially the My Lam mineral spring tourist area, so it has received unanimous support from the people. Up to now, households whose land was recovered are gradually stabilizing their lives," Mr. Phuong informed.

Some recorded images:

Gan 4 km da duoc tham nhua lop 1, tuyen duong mo moi di qua dia hinh doi nui, dong ruong. Anh: Viet Bac.
Nearly 4 km has been paved with the first layer of asphalt, the newly opened road passes through mountainous terrain and rice fields. Photo: Viet Bac.
Tuyen duong thiet ke theo tieu chuan duong do thi mien nui, ha tang dong bo. Anh: Viet Bac.
The route is designed according to urban mountain road standards, with synchronous infrastructure. Photo: Viet Bac.
Mot so vi tri dang trong giai doan hoan thien cac hang muc phu tro. Anh: Viet Bac.
Auxiliary items are being completed. Photo: Viet Bac.
Nhung vi tri di qua dia hinh doi nui phuc tap don vi thi cong phai tien hanh no min, pha da tao mat bang. Anh: Viet Bac.
In locations that pass through complex mountainous terrain, construction units must use blasting and rock breaking to create a flat surface. Photo: Viet Bac.
Khi hoan thanh dua vao su dung tuyen duong nang cao hieu qua ket noi cao toc Tuyen Quang - Phu Tho, thuc day phat trien kinh te, du lich. Anh: Viet Bac.
When completed and put into use, the route will improve the efficiency of the Tuyen Quang - Phu Tho expressway connection, promoting economic and tourism development. Photo: Viet Bac.
Việt Bắc
TIN LIÊN QUAN

Lao Cai's 100 billion dong road misses finish line due to iron ore discovery

|

Lao Cai - After 1 year of implementation, the road connecting Provincial Road 151 with Noi Bai - Lao Cai Expressway with a total investment of 115 billion VND could not be completed on time due to the discovery of iron ore.

Hour 9: Playing wildly with Love - Part 1

|

The 9th hour, issue 159 - A beautiful 26-year-old girl, talented, mistakenly fell in love with a dating guy. Can they be happy together?

Supreme leader on TV, declares Iran will not surrender

|

Iran's Supreme Leader Ayatollah Ali Khamenei affirmed on June 18 that "the Iranian people are not a subject nation".

The Minister of Construction talks about private investment in railway development

|

The Minister of Construction said that there should be no need to worry about the possibility of private investors being sold to foreign countries when allowing them to participate in railway development.

Live Vietnam men's volleyball 2-0 New Zealand: Set 3

|

Live Vietnam men's volleyball against New Zealand in the opening match of AVC Nations Cup 2025, taking place at 20:30 on June 18 (Vietnam time).

16 Vietnamese citizens return home from Iran

|

On June 18, 2025, 16 Vietnamese citizens in Iran returned home, the remaining 11 citizens were still kept in touch regularly.

Thailand U19 Women's Team Wins 2025 Southeast Asian U19 Women's Championship

|

On the evening of June 18, the Thai U19 women's team won 3-1 against the Vietnam U19 women's team to win the 2025 Southeast Asian U19 Women's Championship.

TMV Aurora has not been licensed, but the clinic still provides weight loss consultation with RF waves and enzyme culture

|

Although not licensed by the authorities as a medical examination and treatment facility, TMV Aurora still advises on weight loss with RF waves and enzyme culture.

Lao Cai's 100 billion dong road misses finish line due to iron ore discovery

Đinh Đại |

Lao Cai - After 1 year of implementation, the road connecting Provincial Road 151 with Noi Bai - Lao Cai Expressway with a total investment of 115 billion VND could not be completed on time due to the discovery of iron ore.

Kỷ luật loạt cán bộ ở Thái Nguyên liên quan đường trăm tỉ

Nhóm PV |

Loạt cán bộ và nguyên lãnh đạo của TP Sông Công, Thái Nguyên bị xem xét, xử lý kỷ luật.

Xẻ núi lấp ruộng làm tuyến đường nghìn tỉ ở Thái Nguyên

Nguyễn Tùng |

Sau gần 2 năm xẻ núi, lấp ruộng thi công đêm ngày, tuyến đường 3.800 tỉ đồng kết nối các tỉnh Thái Nguyên - Bắc Giang - Vĩnh Phúc đã hình thành.