Ceremony next to the giant steel pillars of the 500kV Lao Cai - Vinh Yen line

Bảo Nguyên |

To speed up the progress of the Lao Cai - Vinh Yen 500kV transmission line project, workers worked through the April 30 - May 1 holiday.

The 500kV Lao Cai - Vinh Yen Line project passes through Luc Yen and Yen Binh districts (Yen Bai province) with a total length of 90 km, 173 pole foundations.

According to the leader of Yen Bai Provincial People's Committee, the project has complex construction terrain, the Northwest region is about to enter the rainy season, so the local authorities have cooperated with the investor to accelerate the inventory and payment of funding for organizations, households and individuals whose land is recovered.

Up to now, the section passing through Luc Yen district has 82 pole foundation locations and Yen Binh district has 91 pole foundation locations that have completed site clearance and handed over the site to the investor to implement the project.

Cac nha thau huy dong nhan luc lam xuyen dip nghi le 30.4 - 1.5, phan dau hoan thanh cac vi tri mong cot trong thang 5. Anh: Bao Nguyen
The contractor mobilized human resources to work through the April 30 - May 1 holiday, striving to complete the pole foundation locations in May. Photo: Bao Nguyen

On April 30, according to the reporter of Lao Dong Newspaper, at the construction site of the project through Yen Bai province, dozens of workers are working enthusiastically.

Not only working day, the contractor also works overtime to take advantage of favorable weather, completing the foundation excavation of locations early in May, preparing for the erection of poles and pulling of ropes from June 2025.

At other foundation locations in Yen Bai province, the unit has simultaneously deployed the foundation location. To keep up with the overall progress of the project, the contractor has added human resources, increased shifts, and increased working hours.

Don vi thi cong vua hoan thanh dung cot vi tri 51
The construction unit has just completed the erection of the column at location 51. Photo: Bao Nguyen

Mr. Do Quang Khai - Deputy Director of Power Project Management Board 1 and Director of the 500 kV Lao Cai - Vinh Yen Power Line Project Management Board said: This is an important project in the national power transmission system, playing a key role in enhancing the power transmission capacity of hydropower plants in the Northwest region.

Therefore, the progress is being calculated daily for contractors. The foundation excavation will end on May 30. From June 1 to July 30, the contractor will complete the column installation and deploy the pulling of the rope from July to August 30. Units strive and are determined to energize on August 31, 2025.

Mr. Do Quang Khai also said that on April 30, leaders of Power Project Management Board 1 and Song Da 11 Joint Stock Company (the construction unit of package 4) visited and encouraged workers at the construction site.

Lanh dao Ban QLDA Dien 1 va Cty CP Song Da 11 tham, dong vien nguoi lao dong tren cong truong goi thau so 4, doan qua huyen Luc Yen, tinh Yen Bai.
Leaders of Power Project Management Board 1 and Song Da 11 Joint Stock Company visited and encouraged workers at the construction site of package No. 4, the section through Luc Yen district, Yen Bai province. Photo: Bao Nguyen

According to the workers, because it is located on rice fields, near streams, the soil is weak, so some locations are designed in the shape of a village foundation. The construction of the steel reinforcement was carried out overnight to ensure progress.

Normally, contractors arrange a team and a team for 2-3 foundation positions. However, due to the required progress, the unit arranged each team to take on 1 difficult position and 2 easy positions.

Although working through the holidays, the workers are very excited to receive encouragement and attention from the units leaders, said a worker named Nam who is working at the construction site.

Cot vi tri 33 dang duoc dung. Anh: Bao Nguyen
Location 33 is under construction. Photo: Bao Nguyen

On the side of the unit supplying steel poles for the 500kV Lao Cai - Vinh Yen transmission line project, through research - Dong Anh Steel Pipe Manufacturing Company Limited is supplying poles for 4/10 packages of the project with 65 steel poles and 99 steel pipes, with a total volume of more than 20,000 tons.

"Realizing that this is a national key project and is very urgent, with progress every day, nearly 600 officers and workers of the factory are participating in the production of 3 shifts, 4 teams, working through the April 30 - 1.5 holiday to meet the project's progress", Mr. Nguyen Minh De, General Director of Dong Anh Steel Pipe Manufacturing Company Limited informed.

Bảo Nguyên
RELATED NEWS

Phu Tho urgently clears land for 500kV power line project

|

Phu Tho - The province is focusing on speeding up the site clearance progress of the Lao Cai - Vinh Yen 500kV Line project through the area.

4 lessons learned from the construction of the 500kV transmission line project

|

The implementation of the 500kV line 3 in a record short time in terms of investment policy and project construction has brought about many positive results.

Husband goes to work far away, wife stays at home, has an affair and has a child with another person - Part 1

|

The 9th hour - Husband leaves home to work far away, sending money to support the family. But in loneliness, his wife had an affair and became pregnant with someone else. What will happen to this family?

Ho Chi Minh City Party Secretary Tran Luu Quang has more important tasks

|

HCMC - Secretary of the Ho Chi Minh City Party Committee Tran Luu Quang holds the position of Head of the Steering Committee for Anti-Corruption, Wastefulness and Negativity of Ho Chi Minh City.

The Press Law (amended) must create a breakthrough for the press in the new period

|

HCMC - The Press Law (amended) needs to be close to reality, creating a transition to help press agencies have the capacity to lead and orient public opinion in the new period.

Proposal to increase the level of asset and gemstone declaration from 50 million to 150 million VND

|

The draft Law amending and supplementing a number of articles of the Law on Anti-Corruption proposes that cadres must declare for gemstones and assets with a value of VND150 million or more.

Online lending trend in the digital age: Opportunities for Vietnamese commercial banks

|

If implemented safely, transparently and responsibly, online lending will not only improve the competitiveness of the banking system, but also contribute to shaping a more modern, comprehensive and efficient digital financial ecosystem for Vietnam.

Phu Tho urgently clears land for 500kV power line project

Tô Công |

Phu Tho - The province is focusing on speeding up the site clearance progress of the Lao Cai - Vinh Yen 500kV Line project through the area.

4 lessons learned from the construction of the 500kV transmission line project

Cường Ngô |

The implementation of the 500kV line 3 in a record short time in terms of investment policy and project construction has brought about many positive results.

Hoàn thành dự án đường dây 500kV mạch 3 dịp lễ 2.9 là mệnh lệnh

Lê Thanh Phong |

Tại cuộc họp về dự án đường dây 500kV mạch 3 ngày 13.8, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính nêu rõ, quyết tâm khánh thành vào dịp kỷ niệm Cách mạng Tháng Tám và Quốc khánh 2.9 năm nay.