Request for quality control of Nha Trang - Cam Lam expressway before opening day

Hữu Long |

Khanh Hoa – The joint venture of contractors proposed to allow the Nha Trang - Cam Lam expressway to operate, the Ministry of Transport requested the investor to closely monitor the quality of the project.

The Ministry of Transport (MOT) has just sent a document responding to Project Management Board 7 (PMU, investor) on the content of quality control and construction progress of the Van Phong - Nha Trang section component project of the North - South Eastern Expressway Construction Project in the 2021-2025 period.

This is the latest information on the Nha Trang - Cam Lam expressway project after the consortium of contractors including Son Hai Group Co., Ltd., Vietnam Construction and Import-Export Joint Stock Corporation - Vinaconex, and LIZEN Joint Stock Company proposed to put into operation 68.35km, connecting from Nha Trang - Cam Lam expressway before January 10, 2025.

According to initial progress, the project will be completed and put into operation by the end of 2025.

The Ministry of Transport requires Project Management Board 7 to review and thoroughly handle local items with some remaining problems and defects that have been pointed out by the State Inspection Council through field inspections, so as not to affect the quality of the project; control the origin of materials, supplies, and technical instructions of the project, especially in asphalt concrete paving work to ensure quality, flatness, and allowable errors...

For items with high technical and aesthetic requirements such as bridgehead roads, expansion joints, railings, median strips, etc., the investor needs to direct consultants to inspect, review and immediately handle locations that do not meet requirements.

Project Management Board 7 proactively coordinates with local authorities to complete all site clearance work, especially for the rest stop, and hand it over to the project before December 31, 2024, without affecting the construction progress.

Currently, the contractor consortium is ahead of schedule. The contractor consortium affirms that it will complete the entire project of the 68.35km long route.

To put the project into operation soon, promote investment efficiency and especially serve people's travel needs during the Lunar New Year, the contractor consortium has requested the Ministry of Transport and Project Management Board 7 to have a plan and direct relevant units to complete the necessary procedures.

Hữu Long
TIN LIÊN QUAN

5 completed expressways connecting Ho Chi Minh City - Nha Trang

|

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

|

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

PSG eliminates Messi and Inter Miami from FIFA Club World Cup

|

PSG easily won 4-0 against Inter Miami to advance to the quarter-finals of the FIFA Club World Cup 2025.

The Ministry of Public Security guides vehicle registration after July 1

|

Implementing the policy of arranging and reorganizing administrative units at all levels, the Ministry of Public Security has just issued instructions to local police on vehicle registration.

Russia launches nearly 540 UAVs and missiles, Ukraine suffers unprecedented attack

|

Russia launched a series of fierce airstrikes, simultaneously launching a total of nearly 540 missiles and unmanned aerial vehicles (UAVs) into Ukrainian territory.

Stock market waiting for liquidity boom

|

The stock market may have a few adjustment sessions in the context of still waiting for positive supporting information.

A series of important policies take effect from July 1, 2025

|

Chairmen of commune-level People's Committees with the authority to issue Red books; norms for cars serving general work at the commune level... are some important policies effective from July 1, 2025.

5 completed expressways connecting Ho Chi Minh City - Nha Trang

Hữu Long |

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

Hữu Long |

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.