Request for quality control of Nha Trang - Cam Lam expressway before opening day

Hữu Long |

Khanh Hoa – The joint venture of contractors proposed to allow the Nha Trang - Cam Lam expressway to operate, the Ministry of Transport requested the investor to closely monitor the quality of the project.

The Ministry of Transport (MOT) has just sent a document responding to Project Management Board 7 (PMU, investor) on the content of quality control and construction progress of the Van Phong - Nha Trang section component project of the North - South Eastern Expressway Construction Project in the 2021-2025 period.

This is the latest information on the Nha Trang - Cam Lam expressway project after the consortium of contractors including Son Hai Group Co., Ltd., Vietnam Construction and Import-Export Joint Stock Corporation - Vinaconex, and LIZEN Joint Stock Company proposed to put into operation 68.35km, connecting from Nha Trang - Cam Lam expressway before January 10, 2025.

According to initial progress, the project will be completed and put into operation by the end of 2025.

The Ministry of Transport requires Project Management Board 7 to review and thoroughly handle local items with some remaining problems and defects that have been pointed out by the State Inspection Council through field inspections, so as not to affect the quality of the project; control the origin of materials, supplies, and technical instructions of the project, especially in asphalt concrete paving work to ensure quality, flatness, and allowable errors...

For items with high technical and aesthetic requirements such as bridgehead roads, expansion joints, railings, median strips, etc., the investor needs to direct consultants to inspect, review and immediately handle locations that do not meet requirements.

Project Management Board 7 proactively coordinates with local authorities to complete all site clearance work, especially for the rest stop, and hand it over to the project before December 31, 2024, without affecting the construction progress.

Currently, the contractor consortium is ahead of schedule. The contractor consortium affirms that it will complete the entire project of the 68.35km long route.

To put the project into operation soon, promote investment efficiency and especially serve people's travel needs during the Lunar New Year, the contractor consortium has requested the Ministry of Transport and Project Management Board 7 to have a plan and direct relevant units to complete the necessary procedures.

Hữu Long
RELATED NEWS

5 completed expressways connecting Ho Chi Minh City - Nha Trang

|

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

|

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Veterans review history on April 30

|

In the atmosphere of celebrating April 30th, veterans review memories and heroic history through wartime stories.

Cultural houses in Hanoi are packed with people sitting and listening to information about the 5,601 billion VND road project

|

Hanoi - Cultural houses in Phu Dien and Ta Thanh Oai villages (Dai Thanh commune) are crowded with people coming to hear information about land acquisition and site clearance for the Ring Road 3.5 project.

30. 4 box office: movie "Heo Nam Mong" loses top 1 position, "Trum So" exhausted

|

The Vietnamese film market during the April 30th holiday recorded vibrant developments. Among the 5 Vietnamese films released in theaters, "Heo Nam Mong" unexpectedly dropped from the top 1 box office position.

More than 1,300 delegates will attend the 11th Congress of the Vietnam Fatherland Front

|

The 11th Congress of the Vietnam Fatherland Front, term 2026-2031, will be held from May 11-13 at the National Convention Center, Hanoi Capital.

5 completed expressways connecting Ho Chi Minh City - Nha Trang

Hữu Long |

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

Hữu Long |

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.