Request for quality control of Nha Trang - Cam Lam expressway before opening day

Hữu Long |

Khanh Hoa – The joint venture of contractors proposed to allow the Nha Trang - Cam Lam expressway to operate, the Ministry of Transport requested the investor to closely monitor the quality of the project.

The Ministry of Transport (MOT) has just sent a document responding to Project Management Board 7 (PMU, investor) on the content of quality control and construction progress of the Van Phong - Nha Trang section component project of the North - South Eastern Expressway Construction Project in the 2021-2025 period.

This is the latest information on the Nha Trang - Cam Lam expressway project after the consortium of contractors including Son Hai Group Co., Ltd., Vietnam Construction and Import-Export Joint Stock Corporation - Vinaconex, and LIZEN Joint Stock Company proposed to put into operation 68.35km, connecting from Nha Trang - Cam Lam expressway before January 10, 2025.

According to initial progress, the project will be completed and put into operation by the end of 2025.

The Ministry of Transport requires Project Management Board 7 to review and thoroughly handle local items with some remaining problems and defects that have been pointed out by the State Inspection Council through field inspections, so as not to affect the quality of the project; control the origin of materials, supplies, and technical instructions of the project, especially in asphalt concrete paving work to ensure quality, flatness, and allowable errors...

For items with high technical and aesthetic requirements such as bridgehead roads, expansion joints, railings, median strips, etc., the investor needs to direct consultants to inspect, review and immediately handle locations that do not meet requirements.

Project Management Board 7 proactively coordinates with local authorities to complete all site clearance work, especially for the rest stop, and hand it over to the project before December 31, 2024, without affecting the construction progress.

Currently, the contractor consortium is ahead of schedule. The contractor consortium affirms that it will complete the entire project of the 68.35km long route.

To put the project into operation soon, promote investment efficiency and especially serve people's travel needs during the Lunar New Year, the contractor consortium has requested the Ministry of Transport and Project Management Board 7 to have a plan and direct relevant units to complete the necessary procedures.

Hữu Long
RELATED NEWS

5 completed expressways connecting Ho Chi Minh City - Nha Trang

|

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

|

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Ho Chi Minh City seeks opinions on naming lines and metro stations to avoid confusion

|

Ho Chi Minh City is seeking public opinions on the naming of metro lines and stations to build a system of easy-to-remember and easy-to-recognize names, limiting inadequacies.

Ministry of Industry and Trade informs about goods not yet reduced according to gasoline prices

|

Representatives of the Ministry of Industry and Trade said that not all points of sale fully supply all types of gasoline and the price of each type of gasoline may be different.

Da Nang will organize a forum to gather opinions and rebuttals before choosing a logo

|

Da Nang - The city is listening to the contributions and criticisms of the people, and will carefully choose the symbol of the new city.

Lao Cai reviews after reflecting 41 scores of 10 in Math concentrated in one exam cluster

|

Lao Cai - Before the analysis spreading on social networks about the concentration of 10s in Math at an exam cluster, the Provincial Department of Education has intervened to review and clarify.

Ministry of Industry and Trade has not finalized peak hour electricity prices for households

|

The Ministry of Industry and Trade said that it has only proposed to study applying electricity prices during peak hours to households, and has not applied them immediately.

5 completed expressways connecting Ho Chi Minh City - Nha Trang

Hữu Long |

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

Hữu Long |

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.