200 households in Hung Yen in the land clearance area of the DT. 382 upgrade project

Hà Vi |

Hung Yen - About 200 households in Dong Tao Dong village, Hoan Long commune, are within the land clearance area to serve the DT. 382 road renovation and upgrade project.

On August 28, the People's Committee of Hoan Long commune, Hung Yen province organized a conference to deploy the plan to clear violations of the traffic safety corridor and clear ground (GPMB) to serve the construction of the project to renovate and upgrade DT. 382 road through the commune. About 200 households in Dong Tao Dong village within the GPMB area attended the conference.

At the conference, Hoan Long Commune People's Committee informed about the policy, scope of site clearance, progress and roadmap for implementing the project to renovate and upgrade DT. 382 road. In addition, households were informed of the plan to inspect, identify and handle cases of encroachment on roadways, sidewalks, and traffic safety corridors on DT. 381 and DT. 382 routes.

According to the plan, the scope of inspection and handling of traffic safety corridor violations is determined from 3 - 5m from the road edge.

Hoan Long commune will focus on propaganda and mobilization of organizations and individuals with works and assets within the clearance area to voluntarily comply, ensure site clearance to serve traffic projects and safety for people and vehicles. From September 26 to 3, the locality will promote propaganda about the policy, clearance plan and relevant legal regulations, and mobilize people to voluntarily dismantle and relocate violating works and assets.

Hà Vi