Da Nang inspects the progress of the Truong Son Monument Project Phase 2

Thu Giang |

On September 30, Vice Chairwoman of the Da Nang People's Committee Nguyen Thi Anh Thi inspected the progress of the Infrastructure Project and the landscape of the Truong Son Monument campus (phase 2).

At the relief workshop, Vice Chairwoman of the Da Nang People's Committee Nguyen Thi Anh Thi acknowledged that the project had basically been completed according to plan, but she emphasized the requirement to ensure the right quality and progress, completing on the set time frame on July 27, 2026.

The Vice Chairman of the Da Nang People's Committee assigned the Department of Construction to coordinate with the Project Management Board to review and handle the remaining problems, while finding solutions to both comply with legal regulations and ensure progress.

Regarding the dumping site, Vice Chairman of the People's Committee of Da Nang City Nguyen Thi Anh Thi suggested that the People's Committee of Thanh My commune be responsible for advising, finding a suitable location and coordinating with the Department of Construction to guide and urgently complete before October 10, 2025.

The Department of Culture, Sports and Tourism of Da Nang City is responsible for coordinating with the Project Management Board to promptly complete the list of art councils to submit in accordance with regulations, the Project Management Board and the investor must ensure that the project dossier is approved on November 30, 2025.

Regarding the arrangement of residents in the Truong Son Dong road area, by September 30, 2025, the Nam Giang Regional Investment and Promotion Project Management Board had completed leveling the resettlement area and handing over the site to affected households.

The total compensated area reached 5.57 hectares, most households agreed with the plan, only 1 household has not agreed with the compensation and site clearance plan.

In this situation, Vice Chairwoman of the Da Nang People's Committee Nguyen Thi Anh Thi directly visited the family to listen, share the difficulties and encourage and persuade, in order to create consensus and ensure the project implementation process went smoothly.

Thu Giang