These days, taking advantage of favorable weather, Minh Ngoc Construction Investment Company Limited mobilizes human resources and machinery to construct asphalt concrete for the Ngo Quyen - Provincial Road 550 section through Luu Vinh Son commune, Thach Ha district.
Ngo Quyen Street - Provincial Road 550 is 5km long, connecting from the north of Ha Tinh City to the North - South Expressway in Luu Vinh Son Commune in the East - West direction.
The starting point of the route intersects with National Highway 1 (near the Traditional Medicine Hospital) in Thach Trung Ward (Ha Tinh City), the end point is at the expressway intersection with Provincial Road 550 (Luu Vinh Son Commune).
This route has been under construction since the beginning of 2023, and the volume has reached more than 85%.
At this time, Corporation 319 (Ministry of National Defense) is also focusing on the parallel road project connecting the extended Ham Nghi road with Provincial Road 550 at the North-South expressway intersection.
The starting point of this route intersects with Ham Nghi extended road (Thach Dai commune, Ha Tinh city), the end point is at the expressway intersection with Provincial Road 550 (Luu Vinh Son commune, Thach Ha district).
To date, this parallel route has completed more than 70% of the volume. The contractor is making efforts to put the project into operation by the end of June.

When put into operation, the two connecting and parallel routes will help people in Ha Tinh City move conveniently to the expressway as well as from the expressway to Ha Tinh City and surrounding areas.