In 2025, the new Dak Lak province was allocated nearly VND14,830 billion, including VND7,628 billion from the central budget, the rest from the local budget. Of which, Dak Lak province (old) was allocated VND9,590 billion, Phu Yen province (old) VND5,239 billion.
By June 30, 2025, more than VND 12,190 billion had been allocated in detail to each project category, reaching 93.89%. Regarding the disbursement of the public investment plan, by June 30, 2025, the 2025 plan had assigned 12,190 billion VND in detail, of which 3,707 billion VND had been disbursed, reaching 30.4% of the plan.
The Khanh Hoa - Buon Ma Thuot Expressway Project (Component Project 3 invested by the province) has a total investment of VND 6,165 billion, with a route length of 48.09km. To date, the site clearance work has reached 100%.
The relocation of basic technical infrastructure has been completed (the 500kV power line alone has not been completed), the total construction volume has reached 55%. It is expected that in 2025, some sections of the route with large traffic volume will be completed, basically the entire route will be completed in 2026 and put into synchronous operation in 2027.
The project to renovate and upgrade provincial road 1 from Buon Ky bridge, Buon Ma Thuot city (old) to Km 49+00, with a total investment of 1,053 billion VND. The project has started construction in 2022, with the accumulated capital allocated by the end of the 2024 plan being 1,015 billion VND.
The project is under construction, the construction volume has reached about 82%. There are still some locations on the route that cannot be constructed because about 1.45km of site has not been cleared. It is expected to be completed in 2025.
The Phu Yen Province Coastal Road Project (old), the section connecting Tuy An District (old) - Tuy Hoa City (old) Phase 1, with a total investment of VND 2,228 billion. The project is 14.7km long, and has just started construction in 2025, with the accumulated capital allocated to the 2025 plan of VND 824 billion, reaching 37% of the total investment.
The volume of implementation to date has reached 2.8%, the plan for 2025 is 450 billion VND, 20.492 billion VND has been disbursed, reaching 4.6% of the plan. The project has a total reclaimed area of large scale, and has currently handed over 4.57 km of the site (36.8%).
Up to now, the section of the route handing over the construction site has encountered problems because some graves and 22KV power lines have not been relocated. Some other sections have not yet completed the determination and approval of specific land prices, as well as the conditions for land allocation for resettlement and land price determination.
The coastal road section north of An Hai bridge has a total investment of 659 billion VND, 7.482km long. The project will start construction in 2025, with the accumulated capital allocated by the end of the annual plan being VND 599.240 billion.
The project started in January 2024, and has so far handed over about 4.48 km (reaching 60%), the implementation volume has reached 23%. The 2025 plan is 417 billion VND, 71.8 billion VND has been disbursed.