On May 18, the Department of Finance of Ba Ria - Vung Tau province said that as of mid-May 2025, the locality has disbursed more than 5,370 billion VND in public investment capital as planned.
This amount corresponds to 19.91% of total public investment capital according to the 2025 allocation plan. Of which, the central budget disbursed more than 430 billion VND, the provincial budget disbursed about 3,510 billion VND and the district budget disbursed nearly 1,430 billion VND.
Some units have a high disbursement rate such as Chau Duc District People's Committee, reaching nearly 42%. However, many units such as Vung Tau City People's Committee, Department of Health, Specialized Project Management Board... have low disbursement rates, due to many reasons such as land clearance problems; investment adjustment procedures; land use conversion and bidding delays.
The Provincial People's Committee has requested departments, branches and units to promptly complete procedures for allocating capital for eligible projects; continue to review and handle problems to ensure disbursement progress for projects under implementation; handle cases of slow disbursement of public investment capital.