The construction investment project of the City Political - Administrative Center, transportation system and synchronous technical infrastructure system in North Cam River Urban Area was started on January 7, 2023. By May 6, 2023, the city will continue to start construction on the City Convention and Performance Center next to the Political - Administrative Center project. Both projects were invested and built by the city according to the orientation of Resolution No. 45 of the Politburo on the construction and development of Hai Phong City to 2030, with a vision to 2045 and the Resolution of the 16th Congress of the Party Committee. Hai Phong City, striving to complete the move of the city's administrative center to the North of Cam River by 2025.
Recently, the People's Council of Hai Phong City passed a resolution to adjust the investment policy of the City Political-Administrative Center Construction Investment Project, traffic system and synchronous technical infrastructure system in the area. North Cam River urban area. In particular, both investment levels and implementation progress are adjusted.
Regarding total investment, the city increased the project investment from more than 2,513 billion VND to more than 2,831 billion VND (an increase of nearly 318 billion VND). In particular, the adjustment of construction and equipment costs to 745.525 billion VND; Reduce project management costs, construction investment consulting and other costs by 109,391 billion VND; Reduced provision costs by more than 318 billion VND.
Regarding implementation progress, the project implementation period and completion of construction and handover to use from the third quarter of 2022 to the fourth quarter of 2024 are adjusted to from the third quarter of 2022 to the first quarter of 2025.
In addition to this project, the city also adjusted its investment policy with an investment project to build a city convention and performance center and a synchronous technical infrastructure system in the North Cam River Urban Area. In particular, increased project investment from nearly 2,337 billion VND to nearly 2,571 billion VND (an increase of 234 billion VND). The period of project implementation and completion of construction and handover into use from the third quarter of 2022 to the fourth quarter of 2024 is adjusted to from the third quarter of 2022 to the second quarter of 2025.
The reason for this adjustment is because both projects need additional trees for landscape infrastructure, additional furniture and equipment. Particularly for the Political-Administrative Center project, it is necessary to adjust foreign traffic routes and adjust the arrangement of working rooms of agencies and units (in terms of architecture, electricity, water and air conditioning systems, fire prevention). fire fighting, building interior equipment, sound system). The Convention - Performance Center project adds construction of medium voltage lines, new investment in all interior, sound and lighting equipment.
By 2025, when completed, the two projects will contribute to perfecting the architectural landscape of the new urban area North of Cam River towards synchronization and modernity, of international stature.