The reason why many projects in Hai Duong are slow to disburse

Hoàng Khôi |

On July 18, Hai Duong Provincial People's Committee organized a meeting with the Provincial Construction Investment Project Management Board on the implementation of tasks and organizational structure of the unit.

According to the report of the Project Management Board of Hai Duong province, the total assigned public investment capital plan for 2024 is: 3,829,023 billion VND/55 projects. Of these, 24 projects are undergoing compensation and site clearance work.

Of the total 24 projects being prepared for investment in 2024 with this Board as the investor, the total planned capital is more than 2,299 billion VND, the capital disbursement plan in 2024 is more than 2,337 billion VND. 9 projects are organizing to select construction contractors, 15 projects are organizing to select contractors, survey, prepare and submit construction drawings and estimates for approval. In the third quarter of 2024 alone, 10 projects are expected to start construction, with the remaining 14 projects expected to start in the fourth quarter.

Currently, basic project site clearance work has been implemented by localities. However, due to difficulties, implementation progress is still slow for many projects, affecting disbursement progress. Funds for site clearance to date have only been disbursed 179.7/1,126.7 billion VND, equivalent to 15.95%.

The reason for disbursement results being slower than planned is mainly due to slow compensation and site clearance work. On the other hand, due to the lengthy procedures for carrying out investment preparation work; The allocation of capital plans for some projects is not consistent with the project implementation schedule, which also affects the disbursement schedule. The limited capacity of project implementation contractors has also significantly affected the implementation of projects...

At the meeting, Standing Vice Chairman of the Provincial People's Committee Luu Van Ban requested the Management Board to research and propose solutions to overcome the shortcomings and limitations of 2023. Among them, rebalancing the number of personnel suitable for current workload.

The Standing Vice Chairman of the Provincial People's Committee also requested districts, towns and cities to focus on speeding up site clearance progress. After approving the compensation and support plan, localities simultaneously carry out procedures for immediate disbursement and payment; Complete documents and documents to comply with regulations. The District Clearance Council synthesizes problems, proposes implementation plans and coordinates with Departments and branches to propose reporting to the Provincial People's Committee to agree on implementation plans throughout the province.

Districts complete settlement of cleared projects. During the process of site clearance, some works need to be dismantled. The Provincial People's Committee requested the Project Management Board to coordinate with the district-level Site Clearance Board to support, with the goal of accelerating the relocation of works for development. project implementation.

Hoàng Khôi
TIN LIÊN QUAN

18 nghị quyết vừa được HĐND tỉnh Hải Dương thông qua

Hoàng Khôi |

Tại Kỳ họp thứ 23 khóa XVII, nhiệm kỳ 2021 - 2026, HĐND tỉnh Hải Dương thông qua 18 nghị quyết quan trọng.

Hải Dương khai mạc kỳ họp HĐND, xem xét nhiều nội dung quan trọng

Mai Dung |

​​Sáng 11.7, HĐND tỉnh Hải Dương khoá XVII khai mạc kỳ họp thứ 23. Ông Trần Đức Thắng, Ủy viên Trung ương Đảng, Bí thư Tỉnh ủy Hải Dương dự và chỉ đạo kỳ họp.

Gần 200 dự án ở Hải Dương chậm tiến độ, ngừng hoạt động

Hoàng Khôi |

Ngày 24.6, ông Lưu Văn Bản, Ủy viên Ban Thường vụ Tỉnh ủy, Phó Chủ tịch Thường trực UBND tỉnh Hải Dương chủ trì phiên họp thường kỳ tháng 6 (lần 8) để nghe và cho ý kiến một số nội dung báo cáo của các sở, ngành.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

VĐV bóng chuyền Nguyễn Thị Xuân và sự bền bỉ ở tuổi U40

NHÓM PV |

Góc nhìn thể thao số 181 có buổi trò chuyện với chủ công Nguyễn Thị Xuân về hành trình gắn bó với bóng chuyền cũng như dự định trong tương lai của tay đập 38 tuổi.