Bac Ha district administrative headquarters construction project with investment capital of 200 billion VND, funded from the centralized budget source and Bac Ha district budget, of which the total investment of the construction package is 135 billion VND .
According to research, the project's scale includes: A 5-storey complex headquarters building, including 3 clusters of spaces arranged on 3 levels of the terrain connected by a system of roofed corridors, creating a continuous working space. Perfect, convenient.
The floor plans arrange working spaces for agencies and departments under the District Party Committee, People's Council, and People's Committee. The project also has a 2-storey kitchen and public service room along with exterior and auxiliary items.
This is a key project of Bac Ha district to welcome the 25th district Party Congress and party congresses at all levels for the 2025 - 2030 term; creating architectural highlights, urban landscape, perfecting infrastructure, striving to bring Bac Ha town to a class 4 urban area by 2025.
The project is constructed by a joint venture of Duc Tuan Construction Investment Company Limited - Termite Fumigation Company Limited - 19.8 Construction Company Limited.
According to a reporter from Lao Dong Newspaper in the middle of July, on the project construction site in the center of Bac Ha town, machines and human resources are operating at full capacity. Work on house foundations and pile pressing is being implemented.
Mr. Ly A Pao (resident of Bac Ha town) said: "The new administrative center, the face of the town and Bac Ha district, is being built, making us very excited and looking forward to it. This will be the most beautiful headquarters ever."
Through research, the project has an implementation period of 360 days, starting in early June and expected to be completed and put into use by May 24, 2025.
Talking to reporters from Lao Dong Newspaper, a representative of Bac Ha District Construction Investment Project Management Board said: "The new headquarters was built on the old headquarters, so site work is more or less convenient. Only There are a few households that have to clear and hand over land for the project.
Currently, the contractor has gathered hundreds of tons of materials for construction. At the same time, deploy pile pressing to build the foundation for the building."
According to the leaders of Bac Ha District People's Committee, after many years of use, the old headquarters is no longer suitable because it cannot meet all the working and reception needs of officials and employees in the district.
Therefore, once completed, the new administrative headquarters project will improve the efficiency of public service performance and meet the needs of the people.
It is known that in early July 2024, the People's Committee of Lao Cai province issued a Decision to recognize Bac Ha urban area after arranging the administrative unit (merging Ta Chai commune into Bac Ha town) to meet the criteria of class 5 urban area with a total of The rating is 88.1/100.