On the morning of July 31, information to reporters, representatives of Road Management Office 1.4 (Road Management Area 1) confirmed, the Thai Nguyen - Cho Moi route passing through Quang Chu commune had cracks appearing across the road surface.
At the scene, the collapsed and cracked area occupied 2/3 of the road surface and extended for nearly 50 meters. The crack is 3 - 5cm wide, and the road surface is showing signs of sinking to one side.
"This morning we went to check and discovered cracks. There has been heavy rain in the area in recent days, this may also be the cause of landslides and cracks. Currently there is still 1 lane for the Vehicles travel at limited speeds," said a representative of Road Management Office 1.4.
Also according to the Road Management Office 1.4, as soon as a crack is detected on the route, the unit stretches warning ropes and assigns officers to direct traffic to ensure safety. The repair will be carried out by BOT Thai Nguyen - Cho Moi Company.