The shape of the Rach Mieu 2 bridge project after two years of construction

Thành Nhân |

To date, the Rach Mieu 2 bridge project has passed more than half the way. Currently, contractors are increasing construction efforts, striving to complete this project by 2025.

As of the end of July 2024, the Rach Mieu 2 bridge project was 55.9% completed, the overall basis basically met the plan, the main bridge part - Rach Mieu 2 bridge was more than 5% ahead of schedule.
As of the end of July 2024, the Rach Mieu 2 bridge project was 55.9% completed, the overall basis basically met the plan, the main bridge part - Rach Mieu 2 bridge was more than 5% ahead of schedule.
As noted by a reporter from Lao Dong Newspaper in recent days, on the construction site of the Rach Mieu 2 bridge project, there was sudden rain, at noon it was hot and muggy, but with the spirit of "overcoming the sun, overcoming the rain", the workers The construction unit has implemented many measures to speed up the construction volume.
As noted by a reporter from Lao Dong Newspaper, in recent days, on the construction site of the Rach Mieu 2 bridge project, there has been sudden rain, hot and muggy afternoons, but with the spirit of "overcoming the sun, overcoming the rain", the workers The construction unit has taken many measures to speed up the construction volume.
Despite the hot weather, workers worked in 3 shifts of 4 shifts both day and night to speed up the construction progress of the Rach Mieu 2 bridge project.
Rain or shine, the workers constructing Rach Mieu 2 bridge are still hard at work. Despite the hot weather, the workers worked in 3 shifts of 4 shifts both day and night to speed up progress.
Mr. Pham Anh Tuan - construction worker of package XL02 - Rach Mieu bridge project shared: "On the construction site, there are hot and sultry days, or sudden rains that cause everyone to stop work... However, with the spirit of construction efforts, the workers always take advantage of the nice weather, quickly eat a bowl of rice so they can work, and make up for the time they have to stop during hot weather, rain, and wind, to ensure progress. The construction level has been committed and the stage is completed.
Mr. Pham Anh Tuan - construction worker of package XL02 - Rach Mieu 2 bridge project - shared: "On the construction site, there are hot and muggy days, or sudden rains that cause everyone to stop work. .. However, with the spirit of construction efforts, the workers always take advantage of the nice weather, quickly eat a bowl of rice so they can work, and make up for the time they have to stop during hot weather, rain, and wind, to ensure Ensuring the committed construction progress, striving to complete the Rach Mieu 2 bridge project on the occasion of National Day 2025.
Older brother:
Mr. Nguyen Dinh Tuan - Technical Officer of Bac Trung Nam Infrastructure Construction Joint Stock Company - shared that this time is in the rainy season but with the spirit of "overcoming the sun, overcoming the rain", the construction unit has implemented many measures to accelerate the completion of the Rach Mieu 2 bridge project on the occasion of National Day 2025. "Currently, the team of workers is working hurriedly, the atmosphere on the construction site is very urgent and excited to completed on schedule according to the Prime Minister's direction," Mr. Tuan said.
Rach Mieu 2 bridge project connects Tien Giang province and Ben Tre province. This project has a total route length of about 17.6km, with a total investment of 6,810.11 billion VND from public investment capital.
Rach Mieu 2 bridge project connects Tien Giang province and Ben Tre province. This project has a total route length of about 17.6km, with a total investment of 6,810.11 billion VND from public investment capital.
Thành Nhân
TIN LIÊN QUAN

Căng cáp dây văng đầu tiên tại dự án cầu Rạch Miễu 2

Thành Nhân |

Sáng ngày 31.7, Ban Quản lý dự án Mỹ Thuận phối hợp với các đơn vị thi công tiến hành căng cáp dây văng đầu tiên tại trụ tháp P20 của dự án cầu Rạch Miễu 2.

Tiền Giang vận động người dân giải phóng mặt bằng dự án cầu Rạch Miễu 2

Thành Nhân |

Để thực hiện công tác giải phóng mặt bằng, Tiền Giang đã tiến hành vận động người dân bàn giao mặt bằng sạch để giao cho đơn vị thi công thực hiện dự án cầu Rạch Miễu 2.

Dự án Cầu Rạch Miễu 2 đã bổ sung vốn sau phản ánh của Báo Lao Động

Thành Nhân |

Sau phản ánh của Báo Lao Động, Ban Quản lý dự án Mỹ Thuận vừa phân bổ bàn giao hơn 212 tỉ đồng cho Tiền Giang để thực hiện công tác giải phóng mặt bằng đối với các hộ dân còn lại bị ảnh hưởng bởi dự án cầu Rạch Miễu 2 và Khu tái định cư của dự án cầu Rạch Miễu 2.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

VĐV bóng chuyền Nguyễn Thị Xuân và sự bền bỉ ở tuổi U40

NHÓM PV |

Góc nhìn thể thao số 181 có buổi trò chuyện với chủ công Nguyễn Thị Xuân về hành trình gắn bó với bóng chuyền cũng như dự định trong tương lai của tay đập 38 tuổi.