Xuyen Tam canal renovation
Ho Chi Minh City misses the land handover deadline for the Xuyen Tam canal renovation project
|
Ho Chi Minh City cannot hand over the entire site of the Xuyen Tam canal renovation project in November 2025 according to the direction of Ho Chi Minh City Party Secretary Tran Luu Quang.
Ho Chi Minh City leaders request maximum mobilization of human resources and equipment to speed up Xuyen Tam canal
|
On the morning of November 18, Ho Chi Minh City started construction of two packages XL-01 and XL-02 of the Xuyen Tam canal project, completing the entire implementation of nearly 9 km and setting a goal of shortening the progress.
More than 2,200 households were cleared, Xuyen Tam canal must complete compensation in November
|
HCMC The Xuyen Tam canal renovation project needs to reclaim land from more than 2,200 households. The Ho Chi Minh City People's Committee requested to complete site clearance in November 2025.
HCMC reclaims land from 2,077 households in Binh Thanh District, only 510 households agree to receive compensation
|
HCMC - The Xuyen Tam canal renovation project needs to reclaim land from 2,077 households in Binh Thanh district, but so far only 510 households have agreed to receive compensation.
People expect the government to be determined to renovate Xuyen Tam canal in Ho Chi Minh City
|
HCMC - People expect the Xuyen Tam canal renovation project to be implemented on schedule, soon returning a clean living environment to the area.
Relocating a series of houses along the canal in Ho Chi Minh City to do more than 17,200 billion VND project
|
Ho Chi Minh City - Many households have houses along the canal, Xuyen Tam canal, in Go Vap district, have dismantled houses, handing over the ground, preparing to start the project to renovate the canal.
Starting construction of the most polluted canal in Ho Chi Minh City before April 30
|
HCMC - Go Vap and Binh Thanh districts are speeding up site clearance to start the first package of the Xuyen Tam canal renovation project before April 30, 2025.
The most polluted canal in Ho Chi Minh City is about to be renovated with 17,000 billion VND
|
HCMC - After many years of waiting, the Xuyen Tam canal renovation project, the most polluted canal in the city, with a total capital of more than VND17,000 billion, will start construction in April 2025.
Binh Thanh reclaims 53.7 hectares of land, clears 1,230 households
|
HCMC - Binh Thanh District reclaimed 53.7 hectares of land, affecting 2,077 cases, including 1,230 households that were completely cleared to implement the Xuyen Tam canal renovation project.
The 17,000 billion VND project to renovate the most polluted canal in Ho Chi Minh City is delayed
|
HCMC - The project to renovate Xuyen Tam Canal - the most polluted canal in the city, is expected to start construction in November 2024 but is delayed because the site has not been handed over yet.
Ho Chi Minh City launches project to relocate 46,500 houses along canals
|
Ho Chi Minh City will build a large-scale project to relocate all of the more than 46,500 houses located on and along canals.
Ho Chi Minh City clears 1,230 households in Binh Thanh, when will compensation be paid?
|
HCMC – The Xuyen Tam canal renovation project through Binh Thanh district will reclaim land from 2,077 cases (clearing 1,230 households), and pay compensation from December.
Ho Chi Minh City is about to reclaim land from more than 6,100 households to build 4 large projects
|
Ho Chi Minh City will reclaim land from more than 6,100 households to serve 4 projects: Ho Chi Minh City - Moc Bai Expressway, Ring Road 2, Xuyen Tam Canal renovation and Doi Canal North bank renovation.