The government petitioned the investor to abandon the park

CÔNG HÒA |

On August 3, talking to Lao Dong, Mr. Dang Quoc Hung - Vice Chairman of the People's Committee of Trung Van ward (Nam Tu Liem district, Hanoi) said that the Phung Khoang lake park project with an area of ​​11.8 hectares was approved. Construction started in 2016, expected to be completed in 2017 but is still not operational.

Although many items have been completed, Phung Khoang Park cannot be put into use because there are still problems with site clearance. Dozens of households have not yet moved out of the project area, so many construction contents cannot be implemented, directly affecting the progress and completion time of this park.

"The Ward People's Committee has issued a written request to the investor to soon complete the site clearance work and restart the project so that the park can be completed soon to meet the entertainment and entertainment needs of the people," Mr. Hung adds.

Previously on August 2, Lao Dong reporters were present at the Phung Khoang air-conditioned park project and noted the fact that the four exterior sides of the park were still covered with corrugated iron and the doors were locked with iron chains. The road in the park was covered with moss because there were no passersby; Many trees have died, the lighting system is surrounded by trash and overgrown weeds cover the path.

Photo: Cong Hoa
A project entrance gate is always in a state of "closed door". Photo: Cong Hoa

Mr. Nguyen Van Minh, who lives in the apartment complex at 15 To Huu, (Nam Tu Liem, Hanoi), said that this park project has been surrounded by corrugated iron for a long time. Because it hasn't been used for a long time, many people have taken over the sidewalks as parking spaces.

"It hasn't been put into operation for too long, so many people often throw trash into the park, causing flies and mosquitoes to gather, which is extremely unhygienic, posing a potential risk of disease infection. Hopefully the project will operate soon to end this situation," Mr. Minh shared.

Every day, going to the gym on To Huu street, Ms. Nguyen Minh Anh (Nam Tu Liem, Hanoi) feels regretful when an air-conditioned park has completed many items but is not yet operational.

Ms. Minh Anh said that many types of plants and weeds have grown overgrown inside the park because they have not been pruned or cared for for a long time. Many trees have even grown outside the fence, making it difficult for people to walk.

"The area around To Huu street does not have any parks for people to play and entertain. While Phung Khoang lake park remains abandoned for so long, it is a waste. Looking forward to the project being completed to There is a clean and fresh place for exercise and entertainment," Ms. Minh Anh expressed.

Some images recorded at the Phung Khoang air-conditioned park project:

Photo: Cong Hoa
People carelessly throw waste into the park, potentially polluting the environment. Photo: Cong Hoa
Image:
The sign "Phung Khoang Lake Park construction project" in Trung Van ward, Nam Tu Liem district, Hanoi is obscured by green trees. Photo: Cong Hoa
Image:
Many people look forward to the project being completed soon to meet the needs of entertainment. Photo: Cong Hoa
Image:
Cars are carefree on the sidewalks around the park. Photo: Cong Hoa
Image:
The fountain is not working. Photo: Hoang Loc

Image:

The lake's water surface is pitch black, covered with green moss, and stinks. Photo: Hoang Loc
Photo: Cong Hoa
The park's paths and paths are overgrown with weeds. Photo: Cong Hoa
CÔNG HÒA
TIN LIÊN QUAN

Cận cảnh công viên vùng biên xuống cấp, được "bơm" 126 tỉ đồng để hồi sinh

Đinh Đại |

Lào Cai - Dự án cải tạo công viên Nhạc Sơn với số vốn đầu tư 126 tỉ đồng được kỳ vọng trở thành một tiêu chí đưa thành phố Lào Cai đạt đô thị loại I.

Quy mô công viên hơn 14ha lớn nhất quận Nam Từ Liêm

THIỆN NHÂN |

Sau thời gian chậm tiến độ, công viên Mễ Trì có quy mô lớn bậc nhất quận Nam Từ Liêm (Hà Nội) đã được đưa vào hoạt động.

Dự án công viên hơn 10 ha bỏ hoang giữa lòng Hà Nội

HỮU CHÁNH |

Dự án Công viên - hồ điều hòa thuộc khu đô thị Tây Nam Hà Nội rộng hơn 10 ha, mức đầu tư 1.600 tỉ đồng bỏ hoang suốt 15 năm, cỏ mọc um tùm gây lãng phí.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

VĐV bóng chuyền Nguyễn Thị Xuân và sự bền bỉ ở tuổi U40

NHÓM PV |

Góc nhìn thể thao số 181 có buổi trò chuyện với chủ công Nguyễn Thị Xuân về hành trình gắn bó với bóng chuyền cũng như dự định trong tương lai của tay đập 38 tuổi.

Close-up of the degraded border park, "pumped" with 126 billion VND to revive

Đinh Đại |

Lao Cai - Nhac Son Park renovation project with an investment capital of 126 billion VND is expected to become a criterion for Lao Cai city to reach a grade I urban area.

The park's scale is over 14 hectares, the largest in Nam Tu Liem district

THIỆN NHÂN |

After a period of slow progress , the largest scale Me Tri park in Nam Tu Liem district ( Hanoi ) has been put into operation.

Dự án công viên hơn 10 ha bỏ hoang giữa lòng Hà Nội

HỮU CHÁNH |

Dự án Công viên - hồ điều hòa thuộc khu đô thị Tây Nam Hà Nội rộng hơn 10 ha, mức đầu tư 1.600 tỉ đồng bỏ hoang suốt 15 năm, cỏ mọc um tùm gây lãng phí.