Project to overcome consequences of natural disasters worth tens of billions of dong in Ha Tinh is behind schedule

TRẦN TUẤN |

Ha Tinh - Although the Provincial People's Committee has repeatedly urged, up to now, some projects to overcome the consequences of natural disasters are still behind schedule.

65 billion dong project not completed

On February 11, a reporter from Lao Dong Newspaper noted that a group of workers were working on the Ngan Sau River Bank Erosion Repair Project, through Village 5 and Village 2, Ha Linh Commune, Huong Khe District. Through observation, up to now, the Project still has a long section of about a few dozen meters that has not been embanked.

This is a project with a total investment of 65 billion VND, invested by the People's Committee of Huong Khe district. Of which, 60 billion VND comes from the central budget, 5 billion VND is counterpart capital of the People's Committee of Huong Khe district.

The project was won by the Hoang Long and Hoang Lai Joint Venture, and construction began on November 1, 2024. According to schedule, the project must be completed by January 31, 2025.

Mr. Nguyen Anh Tuan - Director of the Project Management Board of Construction Investment of Huong Khe district - informed that up to now, the project to overcome landslides on the banks of Ngan Sau river through village 5 and village 2, Ha Linh commune has completed about 97% of the construction volume, basically about to be completed.

Nhom cong nhan dang thi cong phan con lai cua Du an ke chong sat lo bo song Ngan Sau qua xa Ha Linh. Anh: Tran Tuan.
A group of workers are constructing the remaining part of the Ngan Sau River embankment project through Ha Linh commune. Photo: Tran Tuan.

According to Mr. Tuan, it is expected that in about 10 days the project will be 100% completed for handover.

Mr. Tuan shared that due to the long bidding procedure, it affects the progress.

However, since the construction started, the investor has continuously urged the contractor to focus on overtime and increase shifts, so the project has now been basically completed.

Construction will resume after the full moon.

Also according to the reporter of Lao Dong Newspaper, the urgent project to repair the embankment to prevent landslides on the left bank downstream of Cho Vuc Bridge, Cam Due Commune (total investment capital of 10 billion VND) invested by Cam Xuyen District People's Committee has not been completed yet.

Du an ke chong sat lo bo song Ngan Mo qua xa Cam Due da duoc gia han den 30.4.2025. Chu dau tu cho biet, se don doc thi cong hoan thanh dap ung duoc tien do da gia han. Anh: Tran Tuan.
The embankment project to prevent landslides on the Ngan Mo riverbank through Cam Due commune has not been completed, but the contractor is expected to resume construction after the full moon of January. Photo: Tran Tuan.

On February 11, when the reporter was present, the project was not under construction.

An official from the Cam Xuyen District Construction Investment Project Management Board said that up to now, the urgent project to repair the embankment to prevent landslides on the left bank of the downstream Cho Vuc bridge, Cam Due commune, has completed about 85% of the project. The project has also requested an extension until April 30, 2025.

An official from the Cam Xuyen District Construction Investment Project Management Board informed that after the 15th of the first lunar month, the contractor will resume construction. With the remaining volume, the project will soon be completed before the requested extension.

As Lao Dong reported, from the central budget reserve in 2023 with a total support fund of 150 billion VND, Ha Tinh approved 7 projects to overcome the consequences of natural disasters in the area.

The project with the largest capital source is the project to overcome landslides on the banks of the Ngan Sau River, through village 5 and village 2, Ha Linh commune, Huong Khe district, with a total capital of 60 billion VND.

To date, many projects with small investment capital have been completed.

Recently, the People's Committee of Ha Tinh province has continuously urged investors on the progress of projects, requiring them to speed up construction to promptly disburse public investment capital in 2024.

The People's Committee of Ha Tinh province also assigned: "In all cases, the Chairmen of the People's Committees of the districts: Huong Khe, Vu Quang, Duc Tho, Cam Xuyen and Hong Linh town must take full responsibility before the law, the Provincial People's Committee, the Chairman of the Provincial People's Committee for the progress and quality of the project and must disburse the central support capital before December 31, 2024.

TRẦN TUẤN
TIN LIÊN QUAN

Dong Nai checks the progress of key transport projects

|

Vice Chairman of Dong Nai People's Committee Ho Van Ha checked the progress of key projects of Bien Hoa - Vung Tau highway, belt 3 of Ho Chi Minh City, Huong Lo 2, Road 25C ...

Bac Ninh checked the projects of social housing slowly implemented and handed over

|

Bac Ninh province checked and urged social housing projects to slow down, slowly handed over and after the Lao Dong newspaper.

Urgently clearing the project more than 79 billion dong in Hai Phong

|

On October 10, the People's Committee of Kien An District (Hai Phong) checked the progress of a number of projects being implemented in the area.

Cold air rushes in, forecast for rain in the North

|

According to the meteorological agency, the North is about to be affected by a cold front combined with a strong current in the upper westerly wind zone causing rain.

Can Tho Oncology Hospital project stops construction, damage piles up

|

Can Tho City Oncology Hospital (500 beds), located on Nguyen Van Cu Street, has had to temporarily stop construction for the past 3 years, causing the place to fall into a state of disrepair.

Ukrainian President says ready to swap land with Russia during peace talks

|

Ukraine is ready to swap land with Russia in peace talks.

Man City lost to Real Madrid in extra time

|

Man City lost 2-3 to Real Madrid after conceding two goals in the final 10 minutes of the match.

Moc Chau is also congested on normal days, visitors flock to hunt for plum blossoms

|

Right after the Lunar New Year holiday, Tu Anh called to book a motel or hotel near Moc Chau plum garden to visit for the weekend but all were fully booked.

Dong Nai checks the progress of key transport projects

HÀ ANH CHIẾN |

Vice Chairman of Dong Nai People's Committee Ho Van Ha checked the progress of key projects of Bien Hoa - Vung Tau highway, belt 3 of Ho Chi Minh City, Huong Lo 2, Road 25C ...

Bac Ninh checked the projects of social housing slowly implemented and handed over

Vân Trường |

Bac Ninh province checked and urged social housing projects to slow down, slowly handed over and after the Lao Dong newspaper.

Urgently clearing the project more than 79 billion dong in Hai Phong

Hoàng Khôi |

On October 10, the People's Committee of Kien An District (Hai Phong) checked the progress of a number of projects being implemented in the area.