Long Thanh airport steel roof installation racing ahead of schedule by 1 month

HÀ ANH CHIẾN |

Dong Nai – Contractor Hanoi Construction Corporation (Hancorp) hopes to exceed the schedule by 1 month when constructing and installing the steel roof of Long Thanh airport passenger terminal .

Race ahead of schedule from 20 days to 1 month

On August 29, Lao Dong Newspaper reporters were present at the scene of Long Thanh airport in Binh Son commune, Long Thanh district, Dong Nai province.

After 1 year of construction, the shape of the airport has been revealed, the construction of the steel roof of the passenger terminal is being accelerated.

The steel roof of Long Thanh airport's passenger terminal in package 5.10 has a total investment of more than 36,000 billion VND. Photo: HAC
The steel roof of Long Thanh airport's passenger terminal in package 5.10 has a total investment of more than 36,000 billion VND. Photo: HAC

Mr. Nguyen Duc Thuan - Deputy Director in charge of the Executive Board of Hanoi Construction Corporation (Hancorp) said: "Package 5.10 - Long Thanh airport passenger terminal has completed the rough construction 20 days ahead of schedule. In the next phase, the joint venture of contractors, investors and supervision consultants are preparing for the finishing work, erection of steel structures and imported materials.

According to the schedule, the construction will be completed by the end of 2024, but we are trying to exceed the schedule by 20-30 days to ensure the fastest possible construction progress of the passenger terminal."

In addition, imported materials such as glass and corrugated iron roofs have been signed contracts and are being imported for installation.

Package 5.10 of Long Thanh airport passenger terminal. Photo: HAC
Package 5.10 of Long Thanh airport passenger terminal. Photo: HAC

According to Mr. Thuan, in this bid package, the two largest contractors in Vietnam are Dai Dung Steel Structure and ATAD Steel Structure to carry out the steel structure of the roof of Long Thanh airport's passenger terminal.

Steel structures are processed at the factory, applying the most advanced technology such as automatic welding, factory painting, quality control from the factory and installed for this project.

Regarding progress, Mr. Thuan said that with the help of the investor and supervising consultant, the construction went smoothly and any problems were resolved.

In the extreme weather of sometimes sunny and sometimes rainy, the contractor works 3 shifts, supports workers to travel by bus, provides resting camps, water bottles, raincoats for workers to work overtime to ensure health and progress...

On the upcoming September 2nd holiday, construction is taking place regularly, site progress is guaranteed as usual.

Package 5.10 passenger terminal is considered the "heart" of Long Thanh airport

A corner of Long Thanh airport terminal. Photo: HAC
A corner of Long Thanh airport terminal. Photo: HAC

Package 5.10 - Construction of Long Thanh airport passenger terminal is considered the "heart" and critical progress path of Long Thanh airport phase 1.

Package No. 5.10 for construction and equipment installation of Long Thanh airport passenger terminal started on August 31, 2023.

According to Vietnam Airports Corporation (ACV), package 5.10 includes construction items of the passenger terminal (central terminal and three wings), structure of 1 ground floor and 3 floors, total floor area of ​​about 376,451m2, with a contract value of more than 36,005 billion VND.

Part of the wing of Long Thanh airport passenger terminal, the far side is used as an air traffic control station. Photo: HAC
Part of the wing of Long Thanh airport passenger terminal, in the distance is the air traffic control station. Photo: HAC

Up to now, the passenger terminal has completed the entire reinforced concrete column and beam construction of the 1st floor (114,060/114,060 m2), 2nd floor (96,173/96,173 m2), 3rd floor (73,212/73,212 m2) and is implementing the reinforced concrete beam construction of the 4th floor, reaching 25,150/25,150 m2.

On August 22, the steel structure of wings 2 and 3 was installed according to the contract plan and schedule.

Workers constructing the Long Thanh airport passenger terminal ensure labor safety. Photo: HAC
Workers constructing the Long Thanh airport passenger terminal ensure labor safety. Photo: HAC

In parallel with the construction progress of the rough part, all the procurement and ordering of ME equipment, station equipment, HBS system, and facade glass walls have been implemented, signed contracts with suppliers and manufacturers, and are in the process of manufacturing and processing components according to the set schedule.

The expected progress is to complete the entire construction before December 2025, complete the facade installation before March 2026, in parallel with the completion and installation of test equipment from the beginning of 2026 and strive to complete all items before August 31, 2026.

Some actual images at Long Thanh airport recorded by reporters on August 29:

Mr. Lai Xuan Thanh, Chairman of the Board of Directors of Vietnam Airports Corporation (ACV), said that the Long Thanh airport project phase 1 is expected to be completed and test run before August 31, 2026. By September 2, 2026, Long Thanh airport will welcome its first commercial flight.

HÀ ANH CHIẾN
TIN LIÊN QUAN

643 tỉ xây đường nối sân bay Long Thành và cao tốc Bắc - Nam

HÀ ANH CHIẾN |

Đồng Nai cần đầu tư 643 tỉ đồng để xây dựng tuyến Quốc lộ 20B nối sân bay Long Thành với cao tốc Bắc - Nam (đoạn Phan Thiết - Dầu Giây).

Tuyến đường sắt 40.500 tỉ đồng nối TPHCM và sân bay Long Thành

HÀ ANH CHIẾN |

Đồng Nai kiến nghị sớm đầu tư 3 tuyến gồm đường sắt cao tốc Bắc - Nam, đường sắt nhẹ Thủ Thiêm - sân bay Long Thành và đường sắt Biên Hoà - Vũng Tàu.

Khả năng sân bay Long Thành khai thác trong tháng 6.2026?

Xuyên Đông |

Bộ Giao thông Vận tải vừa trả lời về kiến nghị đưa sân bay Long Thành vào hoạt động từ tháng 6.2026.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

Ngầm tràn ngập sâu, Quảng Bình cảnh báo dân không di chuyển

CÔNG SÁNG |

Do ảnh hưởng bão số 4, từ 7 giờ sáng 20.9, địa bàn tỉnh Quảng Bình vẫn còn nhiều ngầm tràn nước ngập sâu, chảy xiết và chia cắt cục bộ.

Bão số 4 Soulik suy yếu vẫn có thể tàn phá Thái Lan

Khánh Minh |

Bão số 4 Soulik dù đã suy yếu thành áp thấp nhưng dự kiến sẽ mang theo mưa lớn đến Thái Lan.

Ảnh hưởng thi công âu thuyền, nhà dân bị ngập sâu trong nước

YẾN PHƯƠNG - TẠ QUANG |

Việc thi công công trình Âu thuyền Cái Khế đã khiến nhiều nhà dân tại TP Cần Thơ bị lún, nứt nghiêm trọng và ngập sâu trong nước.