Can Gio Bridge design change, HCMC saves nearly 2,000 billion VND

MINH QUÂN |

HCMC - Can Gio Bridge's design was adjusted from a 230m high single-tower cable-stayed bridge to a two-tower design, saving nearly 2,000 billion VND.

According to the Ho Chi Minh City Department of Transport, the architectural plan for Cau Gio Bridge approved by the Ho Chi Minh City People's Committee in 2019 is a single-tower cable-stayed bridge (230m high) with the idea of ​​sketching the image of a mangrove tree - a characteristic of Can Gio.

However, after a period of research, this option has revealed many economic and technical limitations. The design of a tower column is difficult to construct due to the large load of the beam segments and is not suitable for the capacity of domestic contractors, which has reduced the feasibility of the project.

In addition, the arrangement of a tower also does not ensure the stability of the bridge, especially in terms of dynamics when facing strong winds...

In terms of cost, the one-tower option is estimated to cost about VND1,962 billion more than the two-tower option and the construction time is also expected to be longer.

With the above limitations, the Ho Chi Minh City People's Committee has decided to approve the proposal to change the design from a single-tower cable-stayed bridge to a double-tower bridge. The new plan still retains the mangrove architecture and ensures a 55m clearance for navigation. This adjustment has received the consensus of the Standing Committee of the Ho Chi Minh City Party Committee, creating favorable conditions for the next steps of the project.

Phoi canh cau Can Gio khi doi sang 2 tru thap.  Anh: So GTVT TPHCM
Perspective of Can Gio Bridge when it changes to 2 towers. Photo: Ho Chi Minh City Department of Transport

Currently, the total investment of Can Gio bridge after design changes is 10,569 billion VND, implemented in the form of public-private partnership (PPP), BOT contract (build - operate - transfer).

Can Gio Bridge is 7.3km long, connecting from Road 15B (parallel to Huynh Tan Phat in Nha Be district) across Soai Rap River and continuing to Rung Sac Road in Can Gio.

However, the HCM City Department of Transport said that Can Gio Bridge has not yet been included in the adjusted master plan for Can Gio district and the zoning plans in Nha Be district. Therefore, up to now, Can Gio Bridge has not been approved by the competent authority.

The Ho Chi Minh City People's Committee has assigned the Department of Planning and Architecture to urgently complete the dossier and speed up the appraisal and approval of planning adjustments to 2040 and vision to 2060. The Department also needs to review and propose a list and detailed progress plan for relevant agencies in adjusting 1/2,000 scale zoning plans and technical infrastructure and urban traffic sectors to complete the legal basis for the Can Gio bridge project.

Currently, the HCM City Department of Transport has proposed that the HCM City People's Committee assign this department and localities to adjust related planning projects.

After the competent authorities approve the adjustment of the general construction planning of Ho Chi Minh City until 2040 and vision to 2060, the City Appraisal Council will submit to the competent authority to decide on the investment policy for the Can Gio bridge project.

Ho Chi Minh City aims to start construction on Can Gio Bridge on April 30, 2025 and complete it in 2028. When completed, the project will replace Binh Khanh ferry, connecting Ho Chi Minh City's only island district with the central area, while promoting the development of sea encroachment projects and Can Gio international port.

MINH QUÂN
TIN LIÊN QUAN

Phối cảnh 2 cây cầu hơn 17.000 tỉ đồng ở TPHCM sắp xây dựng

MINH QUÂN |

TPHCM – Cầu Thủ Thiêm 4 và cầu Cần Giờ có tổng mức đầu tư hơn 17.000 tỉ đồng chuẩn bị trình HĐND TPHCM thông qua chủ trương đầu tư, khởi công dịp 30.4.2025, hoàn thành năm 2028, giúp tạo diện mạo mới cho giao thông TPHCM.

TPHCM sắp xây cầu hơn 11.000 tỉ đồng, dài 7,3km nối 2 huyện phía Nam

MINH QUÂN |

TPHCM - Dự án cầu Cần Giờ có tổng chiều dài 7,3km, tổng vốn hơn 11.000 tỉ đồng nối huyện Nhà Bè và Cần Giờ sắp trình HĐND TPHCM thông qua chủ trương đầu tư, khởi công năm 2025.

Dự án cầu Cần Giờ hơn 11.000 tỉ đồng trễ hẹn trình HĐND TPHCM

MINH QUÂN |

TPHCM – Dự án cầu Cần Giờ (nối hai huyện Cần Giờ và Nhà Bè) tổng vốn hơn 11.000 tỉ đồng lẽ ra phải trình HĐND TPHCM thông qua chủ trương đầu tư tại kỳ họp cuối năm nay nhưng phải lùi lại sang năm sau.

Vụ phụ huynh “sợ” các khoản thu đầu năm: Kiểm điểm cô giáo

QUÁCH DU |

Thanh Hóa - Sau khi phụ huynh tại một trường tiểu học (ở thị xã Nghi Sơn) bức xúc, "thấy sợ" về các khoản thu đầu năm học, nhà trường đã kiểm điểm một cô giáo.

Hòa Bình di dời khẩn cấp người dân trong đêm, tránh sạt lở

Minh Nguyễn |

Hòa Bình - Tối 22.9, người dân ở tổ 1, phường Thống Nhất, TP Hòa Bình phải di dời khẩn cấp để đảm bảo an toàn, tránh sạt lở.

BRICS có khả năng trở thành khối lớn nhất hành tinh

Khánh Minh |

23 quốc gia chính thức nộp đơn xin gia nhập BRICS trước hội nghị thượng đỉnh BRICS năm 2024.

Người dân dỡ nhà, giao đất làm đường 57km qua Hà Nội

HỮU CHÁNH |

Hà Nội - Nhiều người dân huyện Mê Linh đồng loạt tháo dỡ nhà để bàn giao mặt bằng cho dự án Vành đai 4.

Nối nghiệp cha ông, cốm Mễ Trì đỏ lửa những ngày vào mùa

HOÀNG XUYẾN - VIỆT ANH |

Dù công việc vất vả, nhưng nhiều gia đình tại làng cốm Mễ Trì Thượng (Nam Từ Liêm, Hà Nội) vẫn cố gắng giữ lửa nghề, nối nghiệp cha ông.