Can Gio Bridge design change, HCMC saves nearly 2,000 billion VND

MINH QUÂN |

HCMC - Can Gio Bridge's design was adjusted from a 230m high single-tower cable-stayed bridge to a two-tower design, saving nearly 2,000 billion VND.

According to the Ho Chi Minh City Department of Transport, the architectural plan for Cau Gio Bridge approved by the Ho Chi Minh City People's Committee in 2019 is a single-tower cable-stayed bridge (230m high) with the idea of ​​sketching the image of a mangrove tree - a characteristic of Can Gio.

However, after a period of research, this option has revealed many economic and technical limitations. The design of a tower column is difficult to construct due to the large load of the beam segments and is not suitable for the capacity of domestic contractors, which has reduced the feasibility of the project.

In addition, the arrangement of a tower also does not ensure the stability of the bridge, especially in terms of dynamics when facing strong winds...

In terms of cost, the one-tower option is estimated to cost about VND1,962 billion more than the two-tower option and the construction time is also expected to be longer.

With the above limitations, the Ho Chi Minh City People's Committee has decided to approve the proposal to change the design from a single-tower cable-stayed bridge to a double-tower bridge. The new plan still retains the mangrove architecture and ensures a 55m clearance for navigation. This adjustment has received the consensus of the Standing Committee of the Ho Chi Minh City Party Committee, creating favorable conditions for the next steps of the project.

Phoi canh cau Can Gio khi doi sang 2 tru thap.  Anh: So GTVT TPHCM
Perspective of Can Gio Bridge when it changes to 2 towers. Photo: Ho Chi Minh City Department of Transport

Currently, the total investment of Can Gio bridge after design changes is 10,569 billion VND, implemented in the form of public-private partnership (PPP), BOT contract (build - operate - transfer).

Can Gio Bridge is 7.3km long, connecting from Road 15B (parallel to Huynh Tan Phat in Nha Be district) across Soai Rap River and continuing to Rung Sac Road in Can Gio.

However, the HCM City Department of Transport said that Can Gio Bridge has not yet been included in the adjusted master plan for Can Gio district and the zoning plans in Nha Be district. Therefore, up to now, Can Gio Bridge has not been approved by the competent authority.

The Ho Chi Minh City People's Committee has assigned the Department of Planning and Architecture to urgently complete the dossier and speed up the appraisal and approval of planning adjustments to 2040 and vision to 2060. The Department also needs to review and propose a list and detailed progress plan for relevant agencies in adjusting 1/2,000 scale zoning plans and technical infrastructure and urban traffic sectors to complete the legal basis for the Can Gio bridge project.

Currently, the HCM City Department of Transport has proposed that the HCM City People's Committee assign this department and localities to adjust related planning projects.

After the competent authorities approve the adjustment of the general construction planning of Ho Chi Minh City until 2040 and vision to 2060, the City Appraisal Council will submit to the competent authority to decide on the investment policy for the Can Gio bridge project.

Ho Chi Minh City aims to start construction on Can Gio Bridge on April 30, 2025 and complete it in 2028. When completed, the project will replace Binh Khanh ferry, connecting Ho Chi Minh City's only island district with the central area, while promoting the development of sea encroachment projects and Can Gio international port.

MINH QUÂN
RELATED NEWS

Athletes and coaches participate in elections

|

Coaches and athletes participating in the election affirmed that each ballot is a responsible choice for the development of the country.

32 voters aged 100 and over in Quang Ninh vote to elect National Assembly and People's Council deputies at all levels

|

Quang Ninh - On the morning of March 15, many voters, although elderly in the province, still tried to be present at the polling station to exercise their rights and obligations as citizens.

Ballot boxes in Con Co special zone overcome waves to help voters exercise their right to vote

|

Quang Tri - Con Co Special Zone has arranged ships to bring auxiliary ballot boxes across large waves to the sea, helping voters on ships to exercise their citizen rights.

From voters' votes, sending faith in the new term

|

On March 15, nearly 79 million voters nationwide excitedly went to vote for National Assembly and People's Council deputies for the 2026–2031 term, placing their trust in worthy deputies.

Miss Bao Ngoc, Quyen Linh and artists share their feelings when going to vote

|

Ho Chi Minh City - On the morning of March 15, artists such as Miss Bao Ngoc, Thanh Thuy, Quyen Linh came to polling stations in the city to participate in voting.

Important day at the westernmost point of the Fatherland

|

Dien Bien - From early morning, more than 3,500 voters who are ethnic minorities of Sin Thau commune - a border commune in the westernmost part of the Fatherland joyfully gathered at the polling stations.

Village elders in the Fatherland's fence are proud to exercise citizenship

|

Lam Dong - On election day, elder Dieu Sranh in Bon Bu Nung, Quang Truc border commune, wearing traditional costumes, radiantly went to vote in the border area of the Fatherland.

The night before the election and people staying up with their votes

|

Can Tho - Security teams at the polling station quietly guarded overnight, contributing to maintaining safety for the election day.

Phối cảnh 2 cây cầu hơn 17.000 tỉ đồng ở TPHCM sắp xây dựng

MINH QUÂN |

TPHCM – Cầu Thủ Thiêm 4 và cầu Cần Giờ có tổng mức đầu tư hơn 17.000 tỉ đồng chuẩn bị trình HĐND TPHCM thông qua chủ trương đầu tư, khởi công dịp 30.4.2025, hoàn thành năm 2028, giúp tạo diện mạo mới cho giao thông TPHCM.

TPHCM sắp xây cầu hơn 11.000 tỉ đồng, dài 7,3km nối 2 huyện phía Nam

MINH QUÂN |

TPHCM - Dự án cầu Cần Giờ có tổng chiều dài 7,3km, tổng vốn hơn 11.000 tỉ đồng nối huyện Nhà Bè và Cần Giờ sắp trình HĐND TPHCM thông qua chủ trương đầu tư, khởi công năm 2025.

Dự án cầu Cần Giờ hơn 11.000 tỉ đồng trễ hẹn trình HĐND TPHCM

MINH QUÂN |

TPHCM – Dự án cầu Cần Giờ (nối hai huyện Cần Giờ và Nhà Bè) tổng vốn hơn 11.000 tỉ đồng lẽ ra phải trình HĐND TPHCM thông qua chủ trương đầu tư tại kỳ họp cuối năm nay nhưng phải lùi lại sang năm sau.