Rectifying a series of Cam Ranh contractors in construction acceptance

Hữu Long |

Khanh Hoa - The inspection agency discovered many violations in the acceptance and handover of construction works in Cam Ranh.

In January 2025, the Inspectorate of Khanh Hoa Department of Construction concluded the inspection on the implementation of legal regulations in the acceptance and handover of 13 construction works.

These projects are invested by Cam Ranh City Construction Project Management Board (Cam Ranh PMU).

Cam Ranh Project Management Board issued a document announcing the commencement of construction of 3 projects but did not send it to Cam Ranh City People's Committee as prescribed.

These are the dyke system works of Project 773 in Cam Lap commune; Upgrading and repairing the drainage system in Cam Ranh; Maintaining and repairing traffic works in 2023.

The Department of Construction Inspectorate also discovered that the contractor who signed the acceptance report did not have a chief supervisor for the three projects, which did not comply with regulations. This responsibility belongs to Thuan Hung Consulting and Construction Joint Stock Company; D68 Construction - Real Estate Company Limited and Cam Ranh Project Management Board.

The composition of the construction contractor signing the acceptance minutes without a commander for 5 projects is not in accordance with regulations. This responsibility belongs to 778 Investment and Construction Company Limited; T.A.L Construction Consulting Joint Stock Company; Dong Do Company Limited; Cam Ranh Urban Joint Stock Company and Cam Ranh Project Management Board.

There are 4 projects where the construction contractor stamped and signed the drawings to make the completed drawings and the supervising contractor confirmed the completed drawings, but did not fully show some information on the completed drawings stamp.

This responsibility belongs to T.A.L Construction Consulting Joint Stock Company; Thuan Hung Construction and Consulting Joint Stock Company; Nam Tien Construction and Installation Consulting Company Limited; Dong Do Company Limited; D68 Construction - Real Estate Company Limited; Cam Ranh Urban Joint Stock Company and Cam Ranh Project Management Board.

There are 2 projects where the contractor has created a construction diary but the content of the number of workers and construction equipment is not guaranteed. This responsibility belongs to 778 Investment and Construction Company Limited; Cam Ranh Urban Joint Stock Company and Cam Ranh Project Management Board.

For the 5 completed projects, handed over for exploitation and use, after completing the construction of the project, Cam Ranh Project Management Board sent a request for inspection of the acceptance work to the specialized construction agency.

However, the time when Cam Ranh Project Management Board sent the request for inspection of acceptance work was not 10 days before the date the investor organized the acceptance of the completion of the project according to regulations.

Based on the above content, the Construction Department Inspectorate decided not to impose administrative penalties on contractors and Cam Ranh Project Management Board, but only requested to rectify and learn from experience.

Hữu Long
RELATED NEWS

Building a unique tunnel connecting Nha Trang and Cam Ranh airport

|

Khanh Hoa - The locality is researching to build a long tunnel through Cu Hin mountain, forming an additional traffic route connecting Nha Trang with Cam Ranh airport.

Many houses in Quang Ngai shake violently due to earthquakes

|

Quang Ngai - On the evening of March 21, an earthquake occurred in Mang But commune, causing many people to panic when they felt their houses shake violently for a few seconds.

For the first time, National Assembly deputies have representatives of the O Du ethnic group, born in 2002

|

For the first time, National Assembly deputies have representatives of the O Du ethnic group, one of the smallest ethnic groups in Vietnam.

Japan women's team wins 2026 Women's Asian Cup

|

On the evening of March 21, the Japanese women's team won the 2026 Women's Asian Cup championship after defeating the Australian women's team in the final.

Entangled with 19 households, Hang Bang canal in Ho Chi Minh City missed the finish line

|

Ho Chi Minh City - Hang Bang canal cannot be completed due to 19 households, causing the unfinished renovation appearance, people regret and hope to soon reach the finish line synchronously.

Wage policy is more realistic thanks to surveying workers' living standards

|

Experts believe that investigating workers' living standards will create real data, helping wage policies to be closer to workers' lives.

Iran's largest nuclear facility attacked by the US and Israel

|

Iran's Natanz nuclear facility attacked by the US and Israel on March 21.

VGCL President Nguyen Anh Tuan elected as National Assembly Deputy of the XIV term

|

Comrade Nguyen Anh Tuan - Member of the Party Central Committee, Member of the Standing Committee of the Party Committee of the Fatherland Front, Central mass organizations, President of the Vietnam General Confederation of Labour was elected as a National Assembly Deputy of the 16th term.

Building a unique tunnel connecting Nha Trang and Cam Ranh airport

Hữu Long |

Khanh Hoa - The locality is researching to build a long tunnel through Cu Hin mountain, forming an additional traffic route connecting Nha Trang with Cam Ranh airport.

Xuất hiện thư nặc danh dọa đặt bom sân bay Cam Ranh

Hữu Long |

Khánh Hòa – Công an xác định có một thư điện tử nặc danh với nội dung đe dọa đặt bom gửi đến sân bay Cam Ranh.

Một người làm thuê múc đất đã thắng kiện TP Cam Ranh

Hữu Long |

Khánh Hòa - Chủ đất thuê người làm thuê đến múc và lấp đất thì bị chính quyền xử phạt hành chính. Người làm thuê sau đó khởi kiện ra tòa và thắng kiện.