Thuy Nguyen district has 25 communes recognized as advanced new rural communes, 15 communes recognized as model new rural areas. In 2024, Hai Phong City and the district will invest 1,141 billion VND to implement 226 model new rural infrastructure projects in 10 communes in the district.
Recently, 6 communes simultaneously implemented construction, expected to mobilize a total of over 2,788 households, donating 233,972 m2 of land to carry out construction items.
Specifically, the model new rural infrastructure investment project in Duong Quan commune has a total investment of more than 103 billion VND. In particular, there are 2 types of roads with a total length of about 4.56 km and civil works, items at: Duong Quan Kindergarten, Duong Quan Primary School, Duong Quan Secondary School; Build, upgrade and renovate village cultural houses.
In An Lu commune, the District People's Committee approved an investment of more than 82.8 billion VND to build 9 roads with a total length of about 3.55 km and civil works including construction investment items at the commune's primary school. An Lu; An Lu commune secondary school, village cultural house.
The project in Ngu Lao commune was approved with a total investment of more than 134.9 billion VND, including the construction of 18 roads with a total length of over 7.8 km and civil works including items at the Primary School. Ngu Lao School, Ngu Lao Secondary School, cultural works.
New rural projects in Luu Ky commune with a total investment of more than 129 billion VND include 19 traffic routes with a total length of about 8.93 km and civil works including construction investment items at the school. Luu Ky Primary School and Luu Ky Kindergarten.
The model new rural construction project in Trung Ha commune was approved in Decision No. 2342/QD-UBND with a total investment of over 126 billion VND including 17 roads and civil works including school items. studies, cultural works.
Thuy Trieu commune also invested nearly 122 billion VND to build 15 inter-commune roads, village trunk roads and alley roads with a total length of about 7.56 km. The civil works part includes items upgrading and renovating primary schools and secondary schools; Build, upgrade and renovate village cultural houses, thereby contributing to helping Thuy Trieu commune comprehensively implement the criteria for building a model new rural area.
Leaders of the People's Committee of Thuy Nguyen district asked the communes to do a good job of propaganda to create high consensus and consensus among the people to carry out the tasks of site clearance and relocation of architectural objects and crops. Along with that, support and create conditions for construction contractors; ensure the overall progress of the project (July 2025). The District Project Management Board coordinates closely with construction contractors and supervision consultants to urgently deploy implementation, ensuring technical and quality standards, traffic safety, environmental sanitation, completed on schedule.