On July 19, at the Conference on briefings and providing press information in July, Mr. Nguyen Anh Tuan - Deputy Director of the Department of Construction of Lam Dong province said that currently, Lam Dong province is developing 800 social housing units of the first phase. period 2021-2025, 1,400 units in period 2026-2030. By 2030, develop 2,200 social housing units.
Recently, localities have directed departments and divisions to speed up the progress of land acquisition at social housing projects in the area. However, in general, the progress of land recovery is still slow compared to the roadmap agreed by the Provincial People's Committee.
Deputy Director of the Department of Construction of Lam Dong province said that site clearance is currently very difficult due to the sudden increase in land prices. This has caused difficulties in land price appraisal and increased compensation and site clearance costs. Therefore, the implementation time is long, delaying the implementation of compensation and land recovery.
In addition, the procedures for selecting investors are regulated in many laws, decrees, circulars... so localities encounter many difficulties when applying legal regulations for investor appraisal. Investment policy and investor selection according to regulations.
Social housing construction projects carry out the same procedures as residential and urban area projects. Therefore, the time to approve investment policies and select investors has not been shortened. Social housing projects must invite interested investors, then organize bidding.
"According to regulations, the process of completing all steps from preparing the profile of qualifications and experience to approving the bidding results for investor selection takes about 205 days.
The agency that selects investors and evaluates bids has no experience in implementation, leading to slow and prolonged implementation time at each step" - Mr. Nguyen Anh Tuan said.