North-South high-speed railway expected to be completed in 2035

Xuyên Đông |

In a recent report by the Ministry of Transport, Vietnam strives to complete investment in the entire North-South high-speed railway route by 2035.

In the pre-feasibility study report of the North-South high-speed railway project, the Ministry of Transport (MOT) affirmed that it has actively studied experiences and consulted models from 22 countries and territories, and organized learning experiences in 6 countries that own and master high-speed railway technology.

The proposed investment for the North-South high-speed railway is 1,541km long, with a double track scale, 1,435mm gauge, electrification, infrastructure designed for a speed of 350km/h, 23 passenger stations with an average distance of about 67km, and 5 freight stations connected to freight hubs.

The route will start from Ngoc Hoi station (Hanoi), pass through 20 provinces and cities and end at Thu Thiem station (HCMC).

Regarding technology, the Ministry of Transport said that it recommends choosing rail technology.

Regarding the choice of design speed, the Ministry of Transport believes that a speed of 350km/h is suitable for routes of 800km or more, with many densely populated urban areas such as the North-South corridor of our country.

In addition, according to the consultant's calculation, on the Hanoi-HCMC route, a speed of 350km/h is likely to attract about 12.5% ​​more passengers than a speed of 250km/h; the investment cost for a speed of 350km/h is about 8-9% higher than a speed of 250km/h.

However, if investing at a speed of 250km/h, upgrading to a speed of 350km/h is difficult to implement and ineffective.

The Ministry of Transport aims to submit the investment policy to the National Assembly for approval at the October 2024 session; bid to select international consultants, conduct surveys, and prepare a pre-feasibility study report in 2025-2026; carry out site clearance, bid to select contractors, and start construction of component projects on the Hanoi-Vinh and Nha Trang-Ho Chi Minh City sections by the end of 2027; start construction of component projects on the Vinh-Nha Trang section in 2028-2029 and strive to complete investment in the entire route by 2035.

The Ministry of Transport also added that through reviewing the investment plan, the total project investment is initially determined to be about 67.34 billion USD.

The high-speed railway line on the North-South axis is expected to be invested with a structural length of 60% bridge, 10% tunnel and 30% ground, so the project investment rate is about 43.69 million USD/km.

During the feasibility study report preparation stage, after having survey data and detailed design, the Ministry of Transport will direct consultants to continue reviewing and calculating the total project investment to ensure accuracy, completeness, and suitability with the technology and scale of the project investment.

Regarding the plan to mobilize capital for project investment, the Ministry of Transport proposed mobilizing the central budget to arrange for medium-term periods, government bond capital, capital contributed by localities, mobilized capital with low costs, few constraints, increased revenue sources, and annual spending savings.

It is expected that the State budget capital will be allocated in the medium-term public investment plan periods to complete the project in 2035, with capital allocated for about 12 years. Each year, an average of about 5.6 billion USD will be needed to allocate for the project, equivalent to 24.5% of the annual medium-term public investment capital allocated in the 2021-2025 period and reduced to about 16.2% in the 2026-2030 period if the medium-term public investment ratio remains at 5.5-5.7% of GDP as it is now.

Xuyên Đông
RELATED NEWS

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Traffic ban on Prenn Pass to Da Lat from tomorrow afternoon, December 8

|

Lam Dong - The ban on traffic on Prenn Pass will take place from 11am to 5pm on December 8 to cut down trees at risk of falling, causing traffic insecurity.

Gia Bac Pass in Lam Dong opens to traffic after 5 days of paralysis due to serious landslides

|

Lam Dong - At 5:00 p.m. this afternoon, Gia Bac Pass officially opened the route, vehicles on National Highway 28 began traveling again after a period of paralysis due to landslides.

Updated gold price at the end of session 7.12: gloomy end of the week

|

Updated gold price at the end of the session on December 7: Gold prices last week decreased simultaneously in both domestic and international markets.

Long Thanh airport resettlement area is spacious with villas and townhouses after nearly 5 years

|

Dong Nai - The 280-hectare Long Thanh airport resettlement area has become a bustling urban area, bringing a better life than before to the people.

Bộ GTVT đã đi 5 nước để nghiên cứu đường sắt cao tốc Bắc - Nam

Xuyên Đông |

Ngày 18.3, Bộ Giao thông Vận tải (GTVT) cho biết, nhằm nghiên cứu, đánh giá kỹ lưỡng kinh nghiệm phát triển đường sắt cao tốc; Bộ GTVT đã tổ chức đoàn công tác liên ngành trực tiếp khảo sát tại 5 quốc gia.

Bộ GTVT thông tin về dự án đường sắt cao tốc hơn 7 tỉ USD

Xuyên Đông |

Dự án đường sắt cao tốc Thành phố Hồ Chí Minh - Cần Thơ với mức đầu tư hơn 7 tỉ USD được người dân rất quan tâm. Ngày 7.2, Bộ Giao thông Vận tải (GTVT) thông tin về dự án này.

Cân nhắc phát triển đường sắt cao tốc khu vực Đồng Bằng sông Cửu Long

Xuyên Đông |

Dự án đường sắt cao tốc đang rất được người dân quan tâm.