In 2020, Phu Xuyen district (Hanoi) implemented the construction of the Project to renovate and embellish National Highway 1A (section from Km207 + 250 - Km208) and district administrative center infrastructure.
The project has a length of 743.6 m, after completion will have a cross section of 30m, including 4 motor vehicle lanes and 1 rudimentary vehicle lane on the west side (right side, 3 m wide), 1 lane East side (left, 5.5 m wide).
Recorded by Labor on July 14, it is shown that the section passing through the administrative center of Phu Xuyen district with 6 lanes has been completed, meeting the travel needs of people.
The remaining section of the route with a length of about 325 m is still unfinished, the land allocated is not consistent, alternating with the unfinished part.
The fact that the project cannot be completed creates a "bottleneck", often causing congestion.
"The road is narrow, there are many cars, just a careless accident can easily happen, especially for those who go through this area for the first time" - Mr. Nguyen Manh Hung (34 years old, Phu Xuyen) said and hopes the project will be implemented soon. completed to make people's travel convenient and safe.
Representative of Phu Xuyen District Land Fund Development Center explained that the reason why 325 m of National Highway 1A cannot be expanded is due to problems in site clearance .
Up to this point, there are 5 households whose land is being recovered and still have not agreed with the government's compensation plan.
Recently, the People's Committee of Phu Xuyen district and the District Land Fund Development Center have many times coordinated with the People's Committee of Phu Minh town to organize direct dialogues with households, as well as respond in writing; Mobilize 5 families to inventory and measure construction works on land.
However, all 5 households above have not yet coordinated with the working group to carry out the implementation, and have not yet inventoried the land and construction works on the land.
Previously, in February 2024, Phu Xuyen District People's Committee issued decisions on enforcing mandatory counting decisions for 5 families.
During the mandatory counting session held in March 2024, only 2 households coordinated with the working group to measure and count land and construction works on the land.
Leaders of Phu Xuyen District People's Committee said that the families did not receive compensation funds, site clearance support and moved and dismantled assets and structures out of the site clearance scope of the project. not only slows down project implementation progress, but also affects traffic safety in the area.
In order to complete the project as soon as possible, Phu Xuyen District People's Committee assigned the District Department of Natural Resources and Environment to review, review, verify and synthesize documents, and advise the District People's Committee to issue decisions on enforcement of revenue collection. Land recovery along with assets on land for households within the scope of site clearance.
The project to expand National Highway 1A through the center of Phu Xuyen district, when completed, will help people conveniently travel and trade goods to craft villages in the area, contributing to promoting socio-economic development. local association.