Quang Binh extended the scandalous suspended project

CÔNG SÁNG |

The Party Committee of Quang Binh Provincial People's Committee agreed to propose a 5th extension of the scandalous Dohwa hanging project in recent times, while before it was the opposite.

5th extension

According to information from the People's Committee of Quang Binh province, in the conclusion notice of the Party Committee of the Provincial People's Committee at the meeting on August 13, it has just agreed to extend the 5th time for the Quang Binh Energy Pellet Factory Project of Co., Ltd. Dohwa Resource Development (Dohwa Project).

Accordingly, after listening to the Economic Zone Management Board's report on the policy of adjusting the Quang Binh Energy Pellet Plant Project of Dohwa Resource Development Company Limited; Opinions of members of the Party Committee of the Provincial People's Committee; The Party Committee of the Provincial People's Committee agreed on the policy of adjusting the Dohwa Project.

Previously, as Lao Dong Newspaper reported , on February 22, 2024, Deputy Head of the Management Board of Quang Binh Economic Zone Hoang Dang Anh submitted a report to the Provincial People's Committee on the implementation of the Dohwa Project, clearly stating what the project needs to consider. Consider terminating operations.

The document clearly states that this project does not fall under the provisions of the Investment Law to adjust project implementation progress, therefore, the Economic Zone Management Board requests to terminate the project's operations.

However, on June 17, 2024, the Management Board of Quang Binh Economic Zone sent another document to the Provincial People's Committee about adjusting the extension for this company until December 2025.

Inconsistency of the Economic Zone Management Board

Regarding the extension of the above Project, Lawyer Doan Trong Bang, Black & White Law Firm - Hanoi Bar Association shared some information around this issue.

According to Lawyer Doan Trong Bang, in document No. 195 dated February 22, 2024 of the Economic Zone Management Board on reporting the implementation status of the Dohwa Project, it was identified and assessed that the Project is not under the permitted circumstances. Adjust project implementation progress according to the provisions of the Investment Law. On March 11, 2024, the Party Committee of the People's Committee of Quang Binh province reported to the Standing Committee of the Quang Binh Provincial Party Committee on the Energy Tablet Factory Project of Dohwa Resource Development Company Limited, which agreed with the proposal of the Management Board. economic zone manager on considering terminating the Project according to regulations, requesting the Standing Committee of the Provincial Party Committee to issue a policy on terminating the Project rather than adjusting the project implementation schedule.

However, in Document No. 780 dated June 17, 2024 of the Economic Zone Management Board on the adjustment of the Project, there is a different opinion: "The adjustment of the Project's progress is 24 months older than the Project implementation schedule. The investment project specified in the Decision document approving the initial investment policy and the reason for adjusting the implementation progress of the above project is in the case of overcoming consequences in case of force majeure according to the provisions of law. civil law and land law".

Thus, this shows the inconsistency in the opinions and judgments of the competent authorities, while previous documents have confirmed that the Project is not subject to regulations on adjustment of implementation progress. project under the Investment Law that had to terminate the Project, but the subsequent document changed it to allow the Project to adjust its implementation schedule.

On the other hand, the contents of the documents of the Economic Zone Management Board are recording inconsistent contents and opinions of investors. Sometimes the Investor explains that due to financial difficulties, the implementation has not been completed according to the committed schedule, other times the Investor explains that it is due to having to overcome the consequences in case of force majeure, for two reasons. This is because it is completely different and inconsistent.

Furthermore, in the opinion of Lawyer Doan Trong Bang, the problem of lack of capital, inability to mobilize capital leading to insufficient capacity to implement the Project is not considered a force majeure reason.

CÔNG SÁNG
TIN LIÊN QUAN

Quảng Bình yêu cầu báo cáo về gia hạn dự án treo của Dohwa

CÔNG SÁNG |

Xét thấy có nhiều ý kiến khác nhau liên quan đến dự án "treo" sản xuất viên nén năng lượng Dohwa, tỉnh Quảng Bình chỉ đạo làm rõ để có quyết định chính thức.

Làm rõ sự bất nhất của Khu kinh tế Quảng Bình khi xử lý dự án “treo”

CÔNG SÁNG |

Luật sư Đoàn Trọng Bằng, Công ty Luật Black & White - Đoàn Luật sư TP Hà Nội - đã có những giải thích cụ thể về sự bất nhất của Khu kinh tế Quảng Bình khi xử lý dự án "treo" Nhà máy sản xuất viên nén năng lượng.

Sự bất nhất của Ban Quản lý Khu kinh tế Quảng Bình trong việc xử lý dự án "treo"

CÔNG SÁNG |

Sau khi có văn bản báo cáo đề nghị UBND tỉnh cho chủ trương về việc chấm dứt dự án treo Nhà máy sản xuất viên nén năng lượng vì không đúng Luật Đầu tư, Ban Quản lý Khu kinh tế Quảng Bình sau đó lại có văn bản khác xin gia hạn dự án.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Quang Binh requested a report on extending Dohwa's suspended project

CÔNG SÁNG |

Considering that there are many different opinions related to the "suspended" Dohwa energy tablet production project , Quang Binh province directed clarification to make an official decision.

Làm rõ sự bất nhất của Khu kinh tế Quảng Bình khi xử lý dự án “treo”

CÔNG SÁNG |

Luật sư Đoàn Trọng Bằng, Công ty Luật Black & White - Đoàn Luật sư TP Hà Nội - đã có những giải thích cụ thể về sự bất nhất của Khu kinh tế Quảng Bình khi xử lý dự án "treo" Nhà máy sản xuất viên nén năng lượng.

Sự bất nhất của Ban Quản lý Khu kinh tế Quảng Bình trong việc xử lý dự án "treo"

CÔNG SÁNG |

Sau khi có văn bản báo cáo đề nghị UBND tỉnh cho chủ trương về việc chấm dứt dự án treo Nhà máy sản xuất viên nén năng lượng vì không đúng Luật Đầu tư, Ban Quản lý Khu kinh tế Quảng Bình sau đó lại có văn bản khác xin gia hạn dự án.