The 800 billion VND project stands alone in the middle of the "golden land" that has just been revived

Anh Tú |

HCMC - After 11 years of "standing still", the planned Exhibition Center project in Thu Thiem New Urban Area (HCMC) with a total investment of about 800 billion VND was officially revived. The project is expected to be completed by the end of 2025.

The Ho Chi Minh City Planning Exhibition Center project is built next to the Saigon River, in Thu Thiem New Urban Area, Thu Duc city. The project with an investment capital of about 800 billion VND, started construction in the first quarter of 2013.
The Ho Chi Minh City Planning Exhibition Center project was built with an investment of 800 billion VND, starting in 2013 at the land between the Saigon River road and main road R1 (Vong Cung Avenue) in the new urban area. Thu Thiem, Thu Duc City.
The exhibition center has an architecture of two blocks placed at an angle, bunched together, the steel blocks form a triangle. The project has an area of ​​more than 18,000 square meters with 5 floors, serving the function of displaying and exhibiting the city's architectural planning; organizing events, meeting places for professionals, residents, tourists... The project is considered an iconic project in Thu Thiem New Urban Area.
The exhibition center has an architecture of two blocks placed at an angle, bunched together, the steel blocks form a triangle. The project has an area of ​​more than 18,000 square meters with 5 floors, serving the function of displaying and exhibiting the city's architectural planning; organizing events, meeting places for professionals, residents, tourists... The project is considered an iconic project in Thu Thiem New Urban Area.
However, after completing the rough part, the project stalled for many years due to problems related to a construction contract package. The main reason is that the old contractor submitted samples of materials used for the project that did not meet the requirements; The material manufacturer's technical specifications also do not clarify the compatibility with the project design.
However, after completing the rough part, the project stalled for many years due to problems related to a construction contract package. The main reason is that the old contractor submitted samples of materials used for the project that did not meet the requirements; The material manufacturer's technical specifications also do not clarify the compatibility with the project design.
  According to PV, after many years of stagnation, the project still looks like a gray block of concrete. Many items of the building are degraded, outside the building, water stagnates in large puddles, and grass and trees grow overgrown.
According to reporters, after many years of stagnation, the project still looks like a gray block of concrete. Many items of the project are degraded.
Outside the building, water stagnates in large puddles, and grass and trees grow luxuriantly.
Outside the building, water stagnates in large puddles and grass and trees grow luxuriantly.
Inside the project, only the rough parts and the ceiling pipe system have been completed. Walls and pillars have not been plastered, floors have water stagnation.
Inside the project, only the rough parts and the ceiling pipe system have been completed. Walls and pillars have not been plastered, floors have water stagnation. There is still security on duty 24/24 to look after the project.
After many years of standing still, the Ho Chi Minh City Planning Exhibition Center project cannot help but cause regret for the people. "I have worked here for many years, and seeing this project still the same for many years, I am really sorry for a large project in the golden land of the city," Mr. Duong (63 years old) shared.
The "standing still" project for many years located close to Saigon Riverside Park cannot help but cause regret for the people. "I go here every day to exercise. I see this project still the same for many years. I really feel it is a waste. I hope the project will be completed soon to become a highlight for the City," Mr. Tuan (51 years old) ) share.
The Management Board of Construction Investment Projects for Civil and Industrial Works in Ho Chi Minh City has just opened a bidding package for the production and installation of glass walls, facades, support frames, partitions, railings, ceilings and metal decorative panels. type of Ho Chi Minh City Planning Exhibition Center project.
Recently, the Management Board of Construction Investment Projects for Civil and Industrial Works in Ho Chi Minh City announced the restart of the project and opening bids for the production and installation of glass walls, facades, support frames, partitions, railings, ceilings and metal decorative panels of the Ho Chi Minh City Planning Exhibition Center project. This package is widely bid, the estimated price of the package is more than 114 billion VND, and the implementation time of the package is 180 days. The entire project is expected to be completed by the end of 2025.
Perspective of Ho Chi Minh City Planning Exhibition Center.
Perspective of Ho Chi Minh City Planning Exhibition Center after completion.
Anh Tú
TIN LIÊN QUAN

Hiện trạng Trung tâm triển lãm 800 tỉ đồng trên "đất vàng" Thủ Thiêm sắp khởi động lại

HỮU CHÁNH |

Sau 10 năm khởi công, dự án Trung tâm triển lãm quy hoạch TP Hồ Chí Minh đạt hơn 80% tiến độ, song không thể hoàn thành, nằm trơ trọi giữa khu "đất vàng" Thủ Thiêm.

Sắp tái khởi công trung tâm triển lãm 800 tỉ sau nhiều năm chậm tiến độ

HỮU CHÁNH |

TP Hồ Chí Minh - Công trình trung tâm triển lãm có diện tích 18.000 m2 với tổng vốn đầu tư gần 800 tỉ đồng ở Khu đô thị Thủ Thiêm sẽ được tái khởi công vào đầu tháng 7.2023 sau nhiều năm "đắp chiếu".

Đìu hiu Trung tâm triển lãm "cánh diều" Hải Phòng sau 18 năm sử dụng

Băng Tâm |

Hải Phòng - Sau 18 năm chính thức khai thác, đưa vào sử dụng, Trung tâm Hội chợ Triển lãm quốc tế Hải Phòng không phát huy hiệu quả như kỳ vọng, ngày càng trở nên tiêu điều, có dấu hiệu xuống cấp.

Chính phủ có nhu cầu vay thêm 815.238 tỉ đồng

PHẠM ĐÔNG |

Tổng nhu cầu vay của Chính phủ năm 2025 dự kiến ở mức 815.238 tỉ đồng, tăng 20,6% so với kế hoạch vay của Chính phủ năm 2024.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

Xe bồn cháy dữ dội khi tiếp nhiên liệu ở cửa hàng xăng dầu, 1 người bị thương

NHẬT HỒ |

Bạc Liêu - Xe bồn cháy dữ dội, hư hỏng nặng, sau đó lửa lan sang khu vực gần nhà kho của cửa hàng xăng dầu.

Bắt 2 Phó Chủ tịch huyện ở Thanh Hóa

Trần Lâm |

Thanh Hóa - Mở rộng vụ án "Lợi dụng chức vụ, quyền hạn trong khi hành công vụ", cơ quan chức năng đã bắt tạm giam thêm 2 Phó Chủ tịch huyện Quảng Xương.

Vì sao NSND Trà Giang mang vẻ đẹp kinh điển?

Mi Lan |

Vẻ đẹp dung dị nhưng mạnh mẽ, kiên cường trong những vai diễn của NSND Trà Giang được ví như biểu tượng cho hình ảnh phụ nữ Việt Nam một thời.

Hiện trạng Trung tâm triển lãm 800 tỉ đồng trên "đất vàng" Thủ Thiêm sắp khởi động lại

HỮU CHÁNH |

Sau 10 năm khởi công, dự án Trung tâm triển lãm quy hoạch TP Hồ Chí Minh đạt hơn 80% tiến độ, song không thể hoàn thành, nằm trơ trọi giữa khu "đất vàng" Thủ Thiêm.

Sắp tái khởi công trung tâm triển lãm 800 tỉ sau nhiều năm chậm tiến độ

HỮU CHÁNH |

TP Hồ Chí Minh - Công trình trung tâm triển lãm có diện tích 18.000 m2 với tổng vốn đầu tư gần 800 tỉ đồng ở Khu đô thị Thủ Thiêm sẽ được tái khởi công vào đầu tháng 7.2023 sau nhiều năm "đắp chiếu".

Đìu hiu Trung tâm triển lãm "cánh diều" Hải Phòng sau 18 năm sử dụng

Băng Tâm |

Hải Phòng - Sau 18 năm chính thức khai thác, đưa vào sử dụng, Trung tâm Hội chợ Triển lãm quốc tế Hải Phòng không phát huy hiệu quả như kỳ vọng, ngày càng trở nên tiêu điều, có dấu hiệu xuống cấp.