On the construction site of a hundred billion embankment in Lao Cai

Đinh Đại |

The more than 200 billion Red River embankment project, completed at the end of this year, will help Lao Cai city synchronize its technical infrastructure, aiming for class I urban criteria.

The Red River embankment project (Urban Sub-area No. 15, Lao Cai City, Lao Cai Province) has a length of nearly 1km, with a total investment of more than 200 billion VND. This is an investment project that has been approved by the People's Committee of Lao Cai province since November 2017.
The Red River embankment project (Urban Sub-area No. 15, Lao Cai City, Lao Cai Province) has a length of nearly 1km, with a total investment of more than 200 billion VND. This is an investment project that has been approved by the People's Committee of Lao Cai province since November 2017.
The project will be implemented from the beginning of 2024, the project investor is the ODA and Construction Investment Project Management Board of Lao Cai province.
The project will be implemented from the beginning of 2024, the project investor is the ODA and Construction Investment Project Management Board of Lao Cai province.
The joint venture of Cao Minh Construction Company Limited - 299 Construction and Trading Joint Stock Company is responsible for the construction.
The joint venture of Cao Minh Construction Company Limited - 299 Construction and Trading Joint Stock Company is responsible for the construction.
According to research, this project helps synchronously develop technical infrastructure, thereby contributing to helping Lao Cai city fulfill the criteria of a class I urban area by 2025.
According to research, this project helps synchronously develop technical infrastructure, thereby contributing to helping Lao Cai city fulfill the criteria of a class I urban area by 2025.
Recorded by the reporter in the last days of July, at the embankment project site, workers and machinery were working enthusiastically, even though it was getting dark and it was starting to rain lightly.
Recorded by the reporter in the last days of July, at the embankment project site, workers and machinery were working enthusiastically, even though it was getting dark and it was starting to rain lightly.
According to observations, many concrete items and pillars of the embankment have been completed, and a large amount of iron and steel has been prepared for the next stages. Drainage items have been cast and are ready to be installed.
According to observations, many concrete items and pillars of the embankment have been completed, and a large amount of iron and steel has been prepared for the next stages. Drainage items have been cast and are ready to be installed.
The workers are working hard.
The workers are working hard.
To bring the project to its destination on schedule, both the Investor and the contractor made efforts to overcome difficulties in site clearance to proceed with construction.
To bring the project to its destination on schedule, both the investor and the contractor are making efforts to overcome difficulties in site clearance to proceed with construction.
Through research, the current construction progress of the project is about more than 30%, the construction unit is aiming to complete it by the end of 2024.
Through research, the current construction progress of the project is about more than 30%, the construction unit strives to complete it by the end of 2024.
When completed, this embankment will help prevent landslides on the banks of the Red River and complete the technical infrastructure for Lao Cai city.
When completed, this embankment will help prevent landslides on the banks of the Red River and complete the technical infrastructure for Lao Cai city.
On the afternoon of July 31, talking to a reporter from Lao Dong Newspaper, the leader of the ODA Project Management Board of Lao Cai province said: "We and the contractor are currently making efforts to bring the project to its destination on time. Recently, the unit also conducted enforcement on a number of households to clear the site for the construction unit. Strive to complete it by the end of this year."
Talking to reporters from Lao Dong Newspaper, the leader of the ODA Project Management Board of Lao Cai province said: "We and the contractor are currently making efforts to bring the project to its destination on time. Recently, the unit also conducted enforcement on a number of households to clear the site for the construction unit. Strive to complete it by the end of this year."
Recorded by reporters at the project construction site.
Đinh Đại
TIN LIÊN QUAN

Lào Cai sạt lở 17 điểm trên tỉnh lộ gây ách tắc giao thông

Đinh Đại |

Tỉnh lộ 158, đoạn qua địa phận huyện Bát Xát (Lào Cai) bị sạt lở 17 điểm khiến giao thông bị ách tắc.

Nhiều tuyến quốc lộ sạt lở chia cắt giao thông ở Lào Cai

Đinh Đại |

Hai tuyến Quốc lộ qua địa phận huyện Mường Khương, tỉnh Lào Cai cùng lúc xảy ra sạt lở đất đá khiến giao thông tạm thời bị chia cắt.

Xắn tay khắc phục hậu quả do mưa bão ở Lào Cai, Điện Biên

Việt Dũng |

Mưa bão ở các tỉnh miền núi phía Bắc khiến những tảng đá to, cây đổ ra đường và được lực lượng Cảnh sát giao thông cùng người dân khắc phục, đảm bảo lưu thông.

Dự báo thời điểm bão Trà Mi đạt cường độ cực đại giật cấp 15

AN AN |

Dự báo bão Trà Mi sẽ đạt cường độ cực đại khoảng cấp 12, giật cấp 15 khi tiến đến vùng biển quần đảo Hoàng Sa trong ngày 26.10.

Giờ thứ 9: Đứa con bất hạnh - Phần 1

Nhóm PV |

Giờ thứ 9 - Bé gái trong câu chuyện ngày hôm nay phải ở với bố dượng của mình sau khi mẹ đẻ ly hôn. Đứa bé sẽ lớn lên như thế nào và có cuộc sống ra sao?

Diễn biến mới vụ hóa đơn nước cao bất thường ở Thái Bình

TRUNG DU |

Thái Bình - Trước hàng loạt hành động khó hiểu từ phía Công ty CP Nước sạch Thái Bình, khách hàng cho biết sẽ tiếp tục kiến nghị đến các cơ quan chức năng.

Phụ huynh cho con đi học trở lại sau khi nhà trường nhận sai

NGUYỄN TRƯỜNG |

Ninh Bình - Sau 2 ngày cho con nghỉ học để làm rõ thông tin nhà trường dùng sữa hết hạn cho học sinh uống, ngày 23.10, các phụ huynh đã cho con đi học trở lại.

Biển Đông vẫn là điểm nóng với các tranh chấp lãnh thổ

Ngọc Vân |

Biển Đông vẫn là điểm nóng với các vấn đề tranh chấp lãnh thổ và khác biệt về yêu sách biển, cùng với tình hình quân sự hoá tại khu vực.

Lào Cai sạt lở 17 điểm trên tỉnh lộ gây ách tắc giao thông

Đinh Đại |

Tỉnh lộ 158, đoạn qua địa phận huyện Bát Xát (Lào Cai) bị sạt lở 17 điểm khiến giao thông bị ách tắc.

Nhiều tuyến quốc lộ sạt lở chia cắt giao thông ở Lào Cai

Đinh Đại |

Hai tuyến Quốc lộ qua địa phận huyện Mường Khương, tỉnh Lào Cai cùng lúc xảy ra sạt lở đất đá khiến giao thông tạm thời bị chia cắt.

Xắn tay khắc phục hậu quả do mưa bão ở Lào Cai, Điện Biên

Việt Dũng |

Mưa bão ở các tỉnh miền núi phía Bắc khiến những tảng đá to, cây đổ ra đường và được lực lượng Cảnh sát giao thông cùng người dân khắc phục, đảm bảo lưu thông.