On April 21, Chairman of Dong Nai Provincial People's Committee Nguyen Van Ut and the working delegation inspected the actual progress of site clearance and construction of provincial road projects 25B and 25C.
According to the Dong Nai Provincial Construction Investment Project Management Board, the Project to upgrade and expand Provincial Road 25B (section from the center of Nhon Trach commune to National Highway 51) has handed over 70% of the site, the construction output reached about 50%; the Provincial Road 25C construction project (section from National Highway 51 to Huong Lo 19) has handed over 95% of the site, committed to completion by the end of June 2026.
Chairman of the Provincial People's Committee Nguyen Van Ut emphasized: Provincial road projects 25B, 25C are key projects of the province to serve the connection of Long Thanh airport; Dong Nai has committed to the Government to complete these projects by the end of June 2026. Therefore, units must strive to implement to complete the commitment.