2 bidding packages worth VND 42,000 billion at Long Thanh airport are ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - Package 4.6 runways and package 5.10 passenger terminals are the two largest packages of Long Thanh airport phase 1 project ahead of schedule.

Long Thanh airport passenger terminal is 20 days ahead of schedule

Airports Corporation of Vietnam (ACV) and joint venture contractors are implementing the construction of the two largest packages at the Long Thanh airport project (Binh Son commune, Long Thanh district) including: Package 5.10 - Construction construction of Long Thanh airport passenger terminal (total investment of 35,000 billion VND) and package 4.6 - Construction and installation of equipment for runways, taxiways, and aircraft aprons (with a total cost of investment of more than 8,100 billion VND).

These two bidding packages will start construction on August 31, 2023.

Workers construct package 5.10 of Long Thanh airport passenger terminal. Photo: Thu Phuong
Workers construct package 5.10 of Long Thanh airport passenger terminal. Photo: Thu Phuong

In particular, package 5.10 - Construction of Long Thanh airport passenger terminal, constructed by the VIETUR joint venture, is considered the "heart" and progress critical path of Long Thanh airport phase 1. As for package 4.6 - Construction of the runway is an important part of the project, directly related to safe flight operations.

According to ACV, package 5.10 includes construction items for the passenger terminal (central terminal and three wings), structure of 1 ground floor and 3 floors, roof peak height of 45.55m, the station is designed with Two separate departure and arrival elevations, total floor area is about 376,451 m2. Arrange 40 close parking positions for Code C, E and F aircraft.

This is a large-scale item with high technical nature, the construction progress determines the overall progress critical path of the entire project.

To date, the contractor has mobilized nearly 2,400 personnel and more than 1,500 pieces of machinery and equipment. The passenger terminal construction volume has so far completed all reinforced concrete columns and floor beams on the 1st and 2nd floors and is continuing to carry out reinforced concrete construction of floor beams on the 3rd and 4th floors.

Construction of the entire reinforced concrete structure is expected to be completed in August-September 2024, to begin erecting the roof steel structure. The estimated construction progress is 20 days ahead of the rough progress and 10 days ahead of the overall package progress compared to the contract schedule.

The takeoff and landing runway at Long Thanh airport is 2 months ahead of schedule

For package 4.6, including runway items measuring 4000 x 45 m; taxiway, connecting taxiway, quick exit taxiway (total area about 69.3 hectares); aircraft apron (total area about 47.9 hectares); Parking area for ground service vehicles (about 12.4 hectares) with contract value of 7,244 billion VND.

Package 4.6 constructs the runway at Long Thanh airport. Photo: Thu Phuong
Package 4.6 constructs the runway at Long Thanh airport. Photo: Thu Phuong

To date, ACV has completed a 3,800/4,000m (about 171,000 m2) cement concrete layer on the runway.

The runway project has exceeded the contract schedule by 2 months.

The precision landing support equipment produced at the factory at the end of January 2024 will be shipped to Vietnam in October 2024 and expected to be installed in December 2024.

With this progress, ACV is determined to direct construction units to complete the runway before April 30, 2025, 3 months ahead of the contract schedule.

Mr. Lai Xuan Thanh, Chairman of the Board of Directors of Airports Corporation of Vietnam (ACV), said: Long Thanh airport project phase 1 is expected to be completed and test run completed before August 31, 2026.

On September 2, 2026, Long Thanh airport will welcome the first commercial flight.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Không để xảy ra tiêu cực tại dự án sân bay Long Thành

HÀ ANH CHIẾN |

Chủ tịch Quốc hội Trần Thanh Mẫn đề nghị chủ đầu tư đảm bảo chất lượng công trình, không để xảy ra thất thoát, lãng phí, tiêu cực tại dự án sân bay Long Thành.

Chủ tịch Quốc hội Trần Thanh Mẫn kiểm tra sân bay Long Thành

HÀ ANH CHIẾN |

Ngày 8.8, Chủ tịch Quốc hội Trần Thanh Mẫn cùng đoàn công tác Trung ương đã kiểm tra tiến độ dự án sân bay Long Thành (Đồng Nai).

Khi nào xây cầu Cát Lái nối TPHCM với sân bay Long Thành?

HÀ ANH CHIẾN |

Dự án đầu tư xây dựng cầu Cát Lái thay phà Cát Lái kết nối TP Thủ Đức với huyện Nhơn Trạch (Đồng Nai) đã dự thảo, chờ TPHCM góp ý, thống nhất.

Trực tiếp bóng đá Man City vs Inter Milan tại Champions League

Nhóm PV |

Trực tiếp trận đấu giữa Man City vs Inter Milan tại vòng mở màn Champions League 2024-2025 diễn ra vào lúc 2h ngày 19.9.

Chồng chéo rừng phòng hộ, dân gặp khó khi thu hoạch rừng keo

TRẦN TUẤN |

Hàng trăm hecta keo của người dân xã Kỳ Tây (huyện Kỳ Anh, Hà Tĩnh) đang gặp khó trong việc thu hoạch do bị xác định chồng lấn đất rừng phòng hộ.

Sắp trình Chủ tịch nước danh sách phạm nhân được đặc xá

PHẠM ĐÔNG |

Hội đồng tư vấn đặc xá sẽ tổng hợp, trình Chủ tịch nước danh sách phạm nhân đủ điều kiện được đặc xá để xem xét, quyết định.

Công nhân Nhà máy xử lý rác Bảo Lộc mòn mỏi đợi chờ lương

HOÀI THANH |

Nhà máy xử lý rác ở Lâm Đồng hứa sẽ giải quyết một phần tiền lương trước ngày 15.9, nhưng đến nay, người lao động vẫn mòn mỏi đợi chờ.

Giờ thứ 9: Giao kèo hôn nhân - Phần 1

Nhóm PV |

Giờ thứ 9 - Hai nhân vật trong câu chuyện là bạn thân. Vì gia đình thúc ép, họ đã đến với nhau bằng một bản hợp đồng hôn nhân. Họ sẽ sống với nhau như thế nào?

No Negative Impacts at Long Thành Airport Project

HÀ ANH CHIẾN |

The President of the National Assembly, Trần Thanh Mẫn, requested the investor to ensure the quality of the project, prevent any loss, waste, or negative phenomena from occurring at the Long Thành Airport project.

Chairman of the National Assembly Trần Thanh Mẫn Inspects Long Thành Airport

HÀ ANH CHIẾN |

On August 8, Chairman of the National Assembly Trần Thanh Mẫn accompanied a delegation from the Central Committee to inspect the progress of the Long Thành Airport project (Đồng Nai Province).

When will the Cat Lai bridge connecting Ho Chi Minh City and Long Thanh airport be built?

HÀ ANH CHIẾN |

The investment project to build Cat Lai bridge to replace Cat Lai ferry connecting Thu Duc city with Nhon Trach district ( Dong Nai ) has been drafted, waiting for comments and approval from Ho Chi Minh City.