The cause of the 2.1 million cubic meter lake collapse has not been announced

THANH QUỲNH |

Dak Nong - For more than a year, authorities have yet to announce the cause of the collapse of a reservoir containing 2.1 million cubic meters of water.

On January 6, Mr. Pham Tuan Anh, Director of the Department of Agriculture and Rural Development of Dak Nong province, informed about the investigation into the cause of the collapse of Dak N'Ting reservoir, which contains 2.1 million m3 of water. This reservoir is located in Quang Son commune (Dak Glong district).

According to Mr. Pham Tuan Anh, up to now, the authorities have completed sampling, analysis and completed the inspection report related to the landslide incident at the above project.

Based on the inspection report, the consulting unit and relevant parties complete the incident cause assessment report as well as determine the causes of the parties.

"This is very complicated, we have to get feedback from the council members in the appraisal team, especially the consultants, to ensure accuracy and objectivity" - Mr. Pham Tuan Anh said.

According to Mr. Pham Tuan Anh, on November 30, 2025, the unit will complete the report on the cause of the collapse, as well as determine the responsibilities of the relevant parties.

The Dak N’Ting reservoir project has a capacity of over 2.1 million m3. The project’s goal is to provide irrigation water for 680 hectares of crops and for the daily life of about 1,000 surrounding households.

The project has a total investment of more than 137 billion VND, invested by the Dak Nong Provincial Construction Investment Project Management Board.

In late July and early August 2023, due to the impact of prolonged heavy rain, a large, prolonged slide appeared on the dam surface of the Dak N'Ting reservoir.

Due to the complicated landslide situation, the People's Committee of Dak Nong province has declared a natural disaster emergency at the Dak N'Ting reservoir project.

By November 2023, the People's Committee of Dak Nong province established an investigation team (chaired by the Department of Agriculture and Rural Development) for the Dak N'Ting reservoir incident (Expertise Team 522).

Then, Dak Nong Provincial People's Committee assigned Appraisal Team 522 to conduct an appraisal of the cause of the construction incident.

Along with defining the responsibilities of relevant units and individuals, Team 522 also has the task of advising the Provincial People's Committee on solutions.

However, it was not until mid-July 2024 that the Department of Agriculture and Rural Development of Dak Nong province found a unit that agreed to participate in the inspection consultancy.

THANH QUỲNH
TIN LIÊN QUAN

Dak Pokei Reservoir worth 553 billion VND is behind schedule and over budget

|

Kon Tum – Due to many reasons, the key Dak Pokei reservoir project with an investment capital of 553.3 billion VND is behind schedule and over budget.

Reservoir reaches peak, Binh Dinh releases flood for many days

|

According to the leader of the Department of Agriculture and Rural Development of Binh Dinh province, in the next 3-4 days, the province's reservoirs will continue to discharge flood water downstream to ensure reservoir safety.

Cities instead of using fists after traffic collisions

|

Recently, many cases of violence have occurred after traffic collisions, even causing serious injuries, causing public outrage.

A series of hundred-billion-dong stadiums in mountainous areas are set to be completed in 2025

|

The stadiums with a total investment of hundreds of billions of VND are being urgently constructed, expected to be completed and put into use in 2025.

Mr. Trump sets conditions for resuming negotiations with Mr. Zelensky

|

US President Donald Trump has said he will only talk to a leader with the same vision, who "wards to stop the blood flow".

On the first day the police issued a new driving license, people did not have to wait long

|

HCMC - From the morning of March 1, the police began to receive the issuance and exchange of driving licenses, many people came to do surprise procedures because the process was quick and did not have to jostle.

Many drivers are surprised at the first day of banning cars with more than 16 seats from entering the old town

|

Many drivers were confused on the first day of Hanoi's pilot ban on cars with more than 16 seats during rush hour on some streets in the Old Quarter.

Temporarily suspending the organization of party congresses at the commune and district levels, studying and amending the Constitution

|

Conclusion 127-KL/TW of the Politburo and the Secretariat clearly stated the requirement to temporarily suspend the organization of party congresses at the commune and district levels and study the amendment of the Constitution.

Dak Pokei Reservoir worth 553 billion VND is behind schedule and over budget

THANH TUẤN |

Kon Tum – Due to many reasons, the key Dak Pokei reservoir project with an investment capital of 553.3 billion VND is behind schedule and over budget.

Reservoir reaches peak, Binh Dinh releases flood for many days

Hoài Phương |

According to the leader of the Department of Agriculture and Rural Development of Binh Dinh province, in the next 3-4 days, the province's reservoirs will continue to discharge flood water downstream to ensure reservoir safety.

Né tránh giám định hồ chứa 2,1 triệu m3 nước bị sụt lún

PHAN TUẤN |

Đắk Nông - Nhiều đơn vị có chuyên môn nhưng lại né tránh tham gia giám định nguyên nhân hồ thủy lợi Đắk N'ting có sức chứa hơn 2,1 triệu m3 nước bị sụt lún.

Kon Tum: Sụt trượt trên tuyến đường tránh 1.000 tỉ đồng

THANH TUẤN |

Kon TumĐường tránh TP.Kon Tum có vốn đầu tư 1.000 tỉ đồng chưa được nghiệm thu xuất hiện các vết nứt, sạt trượt tại cầu Đăk Wet. Sự việc được báo cáo lên Tổng cục Đường bộ Việt Nam.