The above project passes through many communes of Trieu Son and Nhu Thanh districts, approved by the Chairman of Thanh Hoa Provincial People's Committee in Decision No. 4521/QD-UBND dated October 31, 2019; The investor is the Department of Transport of Thanh Hoa province.
The project scale is to invest in upgrading and expanding 12,113km of existing roads to ensure the scale of level 3 delta roads with a total investment of nearly 972 billion VND; In which site clearance costs including provisions are nearly 390 billion VND, construction costs are more than 480 billion VND and other cost items are more than 102 billion VND. Project implementation period is no more than 5 years (2019 - 2023).
However, after many years of implementation, the above project is still unfinished, causing many difficulties for people's lives. Up to now, the People's Committee of Thanh Hoa province has only allocated funds to pay compensation for agricultural land and crops on the land. The remaining compensation funds for residential land and architectural objects of households do not have compensation funds. Many households live in a state of suspended planning, not knowing when they will be paid to move to a new place.
According to the People's Committee of Thanh Hoa province, the current capital plan allocated for the project's site clearance costs is 69 billion VND; The remaining land clearance capital according to the total initial approved investment is more than 320 billion VND.
However, through the process of organizing site clearance, the specific land price to calculate compensation when the State recovers land has increased by 2-3 times compared to the approved estimate, leading to the total land clearance cost of the project exceeding. to over 846 billion VND, an increase of more than 456 billion VND compared to the previously approved estimate.
Thus, the additional capital needed to complete site clearance is more than 777 billion VND.
The rising cost of site clearance has exceeded the province's ability to balance capital sources for the project because the province's medium-term public investment plan has fully allocated to tasks and projects in Resolution No. 123/NQ-HDND dated October 11. .2021 and Medium-term public investment plan with State budget capital for the period 2021 - 2025 in Thanh Hoa province.
Previously, on July 7, 2022, Mr. Do Trong Hung - Member of the Party Central Committee, Secretary of Thanh Hoa Provincial Party Committee, directed in Notice No. 153-TB/VPTU to focus on many solutions to soon stabilize people's lives in the future. areas affected by the project and create favorable conditions for continued investment to complete the route.
According to the People's Committee of Thanh Hoa province, following the direction of Provincial Party Secretary Do Trong Hung, in the coming time, the Provincial People's Committee will direct departments and branches to advise, propose and report to competent authorities to prioritize arrangements. capital to complete the entire site clearance work of the project.
Up to now, the approved implementation deadline has expired but it is unknown when the next capital allocation will be made and therefore, it is unknown when people will escape the misery caused by the suspended project.