National Highway 14B project through Da Nang is slow to construct as the rainy season approaches

Nguyễn Linh |

The project to upgrade National Highway 14B through Da Nang is behind schedule, the construction site is messy, causing dust and traffic unsafety when the rainy season is approaching.

Breakdown of progress

The project to renovate and upgrade National Highway 14B, more than 7.5km long, started at the end of 2023, aims to expand the cross-section, synchronize technical infrastructure and drainage systems. However, by the first half of 2026, the project is still stagnant. The section through Hoa Vang and Hoa Tien communes, Da Nang City is still messy with machinery, equipment, and barriers.

According to the Da Nang City Department of Construction, the three main reasons for the project's delay are site clearance problems, limited contractor capacity, and difficulties in filling soil sources.

Mr. Nguyen Ha Nam, Director of Da Nang City Department of Construction, explained: "The first reason is due to site clearance issues. The second reason is that the contractor's construction organization capacity is still limited. The third reason is that the project has a very high demand for embankment soil compared to both sides, so the search for material sources has encountered many difficulties in the past time." Mr. Nam added that the Department is focusing on removing obstacles to support contractors to have construction material sources and complete the project soon.

Regarding the project progress, in Official Dispatch No. 4105/UBND-STC on reporting and periodic review of contractor capacity in the first quarter of 2026, the City People's Committee emphasized the requirement to rectify construction work. In which, the project to renovate and upgrade National Highway 14B (Construction and installation package) undertaken by the Joint Venture of Dong Son Infrastructure Investment Joint Stock Company - CIENCO4 Group Joint Stock Company is being assessed as seriously violating the progress. Although the Ministry of Construction has extended the progress to September 2026, the construction output of this contractor has only reached nearly 43%, although the investor has had many urging documents.

Hoping to speed up progress

The slow construction situation not only causes dust and pollution but also poses a high risk of traffic accidents.

Ms. Tran Thi Dao - a resident of Hoa Tien commune - shared: "Construction is taking place very slowly. Meanwhile, the density of vehicles circulating on this route is very high, especially workers going to work every morning. This situation not only causes dust and environmental pollution but also poses many risks of traffic accidents.

Sharing the same frustration, Mr. Nguyen Thanh Cho, a resident of Hoa Tien commune, informed that the project has been prolonged through many stages but the progress is still very slow: "This road has been implemented since last year, but the progress is very slow, causing dust and frequent accidents. I hope the State will speed up the construction progress so that people can conveniently travel before the rainy season. Currently, the project is messy, causing many difficulties for people's travel.

Faced with the above situation, the City People's Committee has directed the Department of Construction and related units to urgently handle weak contractors, including the case at National Highway 14B project, and at the same time publicize the capacity of violating units on the City Electronic Information Portal. Investors and project management boards must also conduct periodic reviews and reports before the 25th of each month, and be responsible to the law and the Chairman of the City People's Committee if delays occur due to contractor capacity.

Nguyễn Linh
RELATED NEWS

National Highway 14B construction site is messy for many years, people worry about accidents

|

Da Nang - In the first half of 2026, National Highway 14B through Da Nang is still messy.

National Highway 14B raises capital, Da Nang commits to completing site clearance by the end of the year

|

Da Nang - After raising more than 173 billion VND in capital, Da Nang committed to completing site clearance for the National Highway 14B project by the end of the year.

The numbers show that Elon Musk is incredibly rich

|

Elon Musk became the first person in the world to own more than 1,000 billion USD, with asset scale far exceeding what most people can imagine.

Pretty girl" Ngo Lan Huong: I studied at Foreign Trade University and once thought I would work in import and export

|

Em xinh say hi Ngo Lan Huong shared about her professional views and the past of almost not pursuing art.

Ukraine lost more than 1,460 soldiers last week

|

The Russian Ministry of Defense said on June 12 that Ukrainian forces lost more than 1,460 soldiers in the operating area of the Western Combat Group in the past week.

The moon's words "Binh Xuan Truong" and the journey to find the martyr's grave for 50 years

|

Thanh Hoa - For more than 50 years, Mr. Do Dinh Ninh's family has been deeply concerned about the journey to find the martyr's grave. Taking DNA samples from relatives of martyrs has ignited hope.

National Highway 14B construction site is messy for many years, people worry about accidents

Nguyễn Linh - Trần Thi |

Da Nang - In the first half of 2026, National Highway 14B through Da Nang is still messy.

National Highway 14B raises capital, Da Nang commits to completing site clearance by the end of the year

Nguyễn Linh - Trần Thi |

Da Nang - After raising more than 173 billion VND in capital, Da Nang committed to completing site clearance for the National Highway 14B project by the end of the year.