Efforts to hand over clean premises to the project
The Hoa Binh - Moc Chau expressway project was identified by Hoa Binh - Son La provinces as a key project that needs to be accelerated this year.
In the early days of August, present in Cao Son commune and Da Bac town, according to the reporter, the work of counting, compensation, and site clearance is being actively implemented by relevant units, making efforts to force to hand over clean site for the project to start construction before September 2.
On August 3, talking to reporters, Mr. Nguyen Thanh Tuan - Vice Chairman of Da Bac District People's Committee - said: "Currently, the counting of the 8km section through Da Bac town and Cao Son commune has been completed. As soon as the price is available. For specific land, the district will hold a meeting of the Valuation Council to set land prices and list compensation for people.
If people strongly agree, they will pay to hand over the clean site to the construction unit to conduct the groundbreaking ceremony."
According to Mr. Tuan, the Hoa Binh - Moc Chau expressway has 21/34km passing through Da Bac district with 4 communes and towns including Da Bac town, Cao Son commune, Tien Phong commune and Tu Ly commune. There are a total of 88 households whose houses and land are affected.
"The district is urgently implementing work related to compensation and site clearance to hand over a clean site for the project" - Mr. Tuan said.
Request to start construction of Hoa Binh - Moc Chau expressway before September 2
Information from the People's Committee of Hoa Binh province said that the Hoa Binh - Moc Chau expressway project (section from Km19+000 - Km53+000 in Hoa Binh province) has a construction scale of 34km long. Total investment is 9,997 billion VND.
The capital plan assigned to date is 4,523 billion VND. To date, the project has disbursed 39.2 billion VND.
According to the People's Committee of this province, regarding the project implementation progress, for consulting packages for technical design verification, Hoa Son bridge construction estimates and construction price appraisal consulting packages, currently has completed the contractor selection, contract signing and implementation.
For the section from Km19 - Km40+750 (before Hoa Son bridge), complete the design documents and submit to the specialized agency of the Ministry of Transport for appraisal.
The section from Km41+989 - Km53 (after Hoa Son bridge) has basically completed the technical design and construction estimates.
Particularly, the Hoa Son bridge project has basically completed the technical design and construction estimates (verification work is carried out in parallel with the design work).
"For Mai Chau district, prepare a public listing plan for affected organizations, individuals and households. Currently continuing to coordinate with the district People's Committee to carry out inventory and measurement work for affected individuals and households. Land recovery cases serve as a basis for preparing compensation estimates to be paid to affected households.
For Van Ho district, complete the land surveying and land clearance work to determine the land origin as a basis for preparing a site clearance plan" - informed the representative of the People's Committee of Hoa Binh province.
Recently, the People's Committee of Hoa Binh province also issued a document requesting the Management Board of investment projects for construction of traffic works in Hoa Binh province (investor) to coordinate with relevant units to speed up procedures according to the regulations. legal regulations to ensure the start of construction of the Hoa Binh - Moc Chau Expressway Project (section from Km19+000 - Km53+000 in Hoa Binh province) before September 2, 2024.