Demolishing the last construction to expand the central street of Hanoi

HỮU CHÁNH |

Hanoi - 2-story apartment building - the last project within the Nguyen Tuan road expansion project to be demolished to serve construction work.

Lao Dong's records in recent days show that the collective house at 35A Nguyen Tuan is being demolished to construct the Nguyen Tuan road expansion project (Thanh Xuan ward, Hanoi).

This is a 2-story apartment building, involving 6 households. The prolonged site clearance for this project has greatly affected the overall progress of the project.

Over the past time, Thanh Xuan ward authorities have actively participated in propaganda, mobilization, and dialogue to get households to agree to hand over land for the project.

s
s
s
2-story apartment building demolished to construct the Nguyen Tuan street expansion project (Thanh Xuan ward, Hanoi). Photo: Song Huu

According to records, the Nguyen Tuan road expansion project has basically completed the main items to date, helping people travel more conveniently.

For the starting section of the route (the apartment building area being demolished), the contractor is mobilizing machinery and personnel to accelerate the construction progress of the final items to complete the entire project.

The project to renovate and expand Nguyen Tuan street was approved by the Thanh Xuan District (old) People's Committee in 2018.

The project is 720m long, starting point is the intersection with Nguyen Trai street, ending point is alley 162 Nguyen Tuan, the cross-section is expanded to 21m, including a 15m wide road surface and 2 sidewalks, each side 3m wide.

s
Machinery is mobilized to construct the first section of the project. Photo: Song Huu
s
The Nguyen Tuan road expansion project when completed has a cross-section of 21m. Photo: Song Huu

To implement the Nguyen Tuan road expansion project, the government must recover and clear 14,334m2 of land from 11 organizations and 160 households and individuals.

The project encountered obstacles in the implementation process, when many households did not agree to hand over the land, and there were many complaints related to the project.

After many times of local propaganda, mobilization and dialogue, by November 2024, most households had handed over land for the project.

From July 1, 2025, after operating the 2-level government, the Nguyen Tuan road expansion project will be transferred to Thanh Xuan Ward People's Committee as the investor.

HỮU CHÁNH
RELATED NEWS

Pensions and salaries of veteran People's Artists and Artists

|

The acting profession has different characteristics compared to many professions. When retiring, many artists become busier, more sought-after and have better incomes than when they were still working.

Last body found in the case of 3 people missing on the Dong Nai River

|

Lam Dong - After nearly 2 days of searching, functional forces have found the body of the last victim in the case of 3 people missing on the Dong Nai River.

Hết tháng 3, dự án mở rộng đường Nguyễn Tuân vẫn chưa hoàn thành

SÓNG HỮU |

Hà Nội - Dự án mở rộng đường Nguyễn Tuân đến nay vẫn chưa hoàn thiện, trong đó còn vướng một nhà tập thể chưa được giải phóng mặt bằng.

Hiện trạng dự án đường Nguyễn Tuân sau dịp nghỉ Tết Nguyên đán

NHÓM PV |

Hà Nội - Dự án mở rộng đường Nguyễn Tuân vẫn dang dở, không có hoạt động thi công, chiều 22.2.

Dự án đường Nguyễn Tuân: Phường nói xong trước Tết, người dân hoài nghi

SÓNG HỮU |

Hà Nội - Trước Tết Nguyên đán 3 ngày, dự án mở rộng đường Nguyễn Tuân vẫn nhầy nhụa bùn đất, ảnh hưởng đến cuộc sống, việc đi lại của người dân.