The Ministry of Construction has just answered citizens' questions about applications for individual house construction permits from organizations.

On the Government Portal, a citizen in Ho Chi Minh City wondered:

According to Article 58 of the dossier requesting a construction permit for individual houses, it includes:

1. Application for a construction permit according to the provisions of Form No. 01 Appendix II of this Decree.

2. One of the legal land documents for issuing a construction permit as prescribed in Article 53 of this Decree.

3. Construction design documents:

... b) For individual houses of organizations: 2 sets of construction design drawings in the construction design dossier deployed after the basic design (construction drawing design for projects only requires preparing an economic - technical report) approved according to the provisions of the law on construction accompanied by the results of administrative procedures according to the provisions of the law on fire prevention and fighting; report on the results of construction design appraisal in cases where the law on construction requires, including: project ground plan drawings on land plots accompanied by project location diagrams; floor plan drawings of floors, vertical and main sections of the project; foundation ground plan drawings and foundation sections accompanied by connection diagrams of technical infrastructure systems outside the project including water supply, drainage, power supply; commitment to ensure safety for adjacent works (for construction works with adjacent works)".

Ms. N.T. D asked, is it true that her company only needs to submit the above application to be granted a permit to build a detached house? Why did the Ward People's Committee report that it could not issue a detached house and request the company to carry out a 1/500 master plan?

The Ministry of Construction answers this question as follows:

The content of her petition does not have complete information about the dossier, so the Ministry of Construction does not have a sufficient basis to guide citizens according to regulations.

According to the content of the legal citation in the question related to the procedure for issuing construction permits for individual houses of organizations.

Accordingly, the dossier requesting a construction permit for individual houses of organizations is currently specified in point b, clause 3, Article 60 of Decree No. 217/2026/ND-CP dated June 19, 2026 of the Government detailing a number of articles of the Construction Law on management of construction activities (effective from July 1, 2026).

It is proposed that you study the contents of regulations on conditions for approving designs to be implemented after the approved basic design to complete the construction permit dossier according to regulations.

Theo Cổng thông tin Chính phủ
RELATED NEWS

Ministry of Construction answers land documents to issue construction permits

|

The Ministry of Construction has just answered the regulations on legal land documents for issuing construction permits.

Basis for issuing construction permits when competing for private house balconies

|

The Ministry of Construction has just answered the issue of competing for private house balconies in cases where localities do not have architectural management regulations and 1/500 detailed planning.

Ministry of Construction clarifies that schools are exempt from construction permits when building level 4 houses

|

The Ministry of Construction has just answered people's questions about building level 4 houses and the conditions for being exempt from construction permits.

Kieu Thanh "Phia truoc la bau troi" and the noises before being prosecuted

|

From a famous face on screen, being awarded the title of Meritorious Artist when she was young, Kieu Thanh gradually disappeared from Vietnamese films after the private life scandal.

Bonuses exceeding regulations and a series of violations, a multi-level marketing company fined 710 million VND

|

Total Swiss Vietnam has just been fined 710 million VND, including violations of not delivering contracts to multi-level marketing participants according to the provisions of law.

Lao Dong Newspaper acts as a bridge for readers to send "Words from the Heart" to parents during Vu Lan season

|

Write loving words from your heart during the Vu Lan season, Lao Dong Newspaper will help you convey messages to your parents on live television...

Ministry of Construction answers land documents to issue construction permits

Theo Cổng thông tin Chính phủ |

The Ministry of Construction has just answered the regulations on legal land documents for issuing construction permits.

Basis for issuing construction permits when competing for private house balconies

Như Hạ |

The Ministry of Construction has just answered the issue of competing for private house balconies in cases where localities do not have architectural management regulations and 1/500 detailed planning.

Ministry of Construction clarifies that schools are exempt from construction permits when building level 4 houses

Theo Cổng thông tin Chính Phủ |

The Ministry of Construction has just answered people's questions about building level 4 houses and the conditions for being exempt from construction permits.