At the end of 2022, Hanoi started the Project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section.
The project has a length of 21.7 km. The starting point is at km14 in Ba La, Ha Dong district (now Yen Nghia ward); the ending point is at km38, Xuan Mai town, Chuong My district (now Xuan Mai commune).
The total investment of the project is over 9,590 billion VND, implemented in the 2022-2027 period. When completed, the road will have a cross-section of 50-60m.
In Phu Nghia commune, the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section passing through the commune has a length of 7.8 km for site clearance.
As of March 22, Phu Nghia commune has issued 1,346 land acquisition notices for households and individuals within the land clearance area.
In which, the origin of land has been investigated for 1,338 land plots; the origin of land has been determined for 1,114 land plots, and the remaining 292 plots have not been identified for origin; 550 decisions have been issued approving compensation, support, and resettlement plans; 502 decisions have been issued to recover land with an area of nearly 22 hectares...

Regarding tasks in the coming time, Secretary of the Party Committee, Chairman of the People's Council of Phu Nghia commune Trinh Tien Tuong requested the Hanoi Traffic Construction Investment Project Management Board and functional sectors of the commune to coordinate in completing the inventory of the remaining land plots.
The Economic Department focuses more drastically on determining the origin of land for the remaining 292 land plots. The Project Management Board strengthens its forces to accelerate the progress of developing compensation and support plans,...
For the area of Nghia Hao, Nhat Tien villages, Dong Tau area (Doi 3 village) to Doi 2, Doi Che villages... wherever people hand over the site, functional forces dismantle it immediately to create conditions for simultaneous deployment throughout the route.
Following that, focus on implementing site clearance from Doi Che village to Dong Son commune (old) area.
Focus on immediately dismantling all historical relic identification signs, headquarters, and village gates within the land clearance area.
Phu Nghia Commune People's Committee develops a schedule to organize dialogues with households related to Dong Phuong Yen market area. Regarding resettlement, urgently build resettlement land prices, and develop a comprehensive resettlement plan.
It is necessary to soon invite the Hanoi City Inspectorate to work to clarify the origin of land in Thanh Binh and Dong Son communes (old)...
It is proposed that the Hanoi Traffic Construction Investment Project Management Board assign forces to immediately dismantle the households that have agreed to hand over; organize field trips to each household in Nghia Hao, Khe Than villages, Dong Sen, Dong Tau areas (Doi 3 village), Doi 2 to grasp the specifics.
Secretary of the Party Committee of Phu Nghia commune hopes that the Project Management Board will coordinate with the locality to focus on implementing the contents of work, trying to complete the site clearance of the Project to renovate and upgrade National Highway 6 section passing through Phu Nghia commune to ensure progress.