On August 29, the Office of the People's Committee of Ca Mau province said that the meeting of the People's Committee of Ca Mau province on August 27 was not a meeting resolved by the authority of the People's Committee of Ca Mau city.
At this meeting, Vice Chairman of Ca Mau Provincial People's Committee Le Van Su only requested that Ca Mau city review some contents and then report to the province as soon as possible. When the People's Committee of Ca Mau City has a report, the Provincial People's Committee will consider and give direction for the city to handle, because the case is under the jurisdiction of the People's Committee of Ca Mau City and specific information will be sent to the press later.
Previously, on August 20, 2024, the Chairman of the People's Committee of Ca Mau city (Ca Mau province) decided to enforce and force the implementation of remedial measures against Mr. Ho An Tap (41 years old, living in Tan Thanh commune). .
According to the enforcement decision, Mr. Ho An Tap must take remedial measures due to administrative violations specified in Clause 2, Article 11 of Decree No. 91/2019/ND-CP dated November 19, 2019. of the Government regulating penalties for administrative violations in the field of land.
Accordingly, converting aquaculture land to non-agricultural land in rural areas is not permitted by the competent authority, the violation area is 3,564.8 m2, the violation location is in Tan Thanh commune.
Remedial measures, for the area of 2,261.58m2, apply point a, clause 4, article 11 of Decree No. 91/2019/ND-CP, forcing the restoration of the original condition of the land before the violation. . For the area of 1,303.22m2, apply point a, clause 4, article 11 of Decree No. 91/2019/ND-CP, forcing the restoration of the original condition of the land before the violation (according to the drawing of the current state of the plot land established by Tan Thanh Commune People's Committee).
As Lao Dong informed, at the end of 2022, the Ho Tap Facebook account continuously posted images and livestreamed the construction process of what is considered the most beautiful building in Ca Mau.
However, through inspection, this project was in violation because it was built on aquaculture land.
After a series of changes in handling decisions, on August 23, Ca Mau City People's Committee officially implemented the decision to enforce Mr. Xi's villa. After the enforcement decision, the People's Committee of Ca Mau province convened a quick meeting on the afternoon of August 27 to request that Ca Mau city and relevant sectors review the report.