Hanoi removes site clearance, accelerates construction of Ring Road 2.5 - Linh Nam

Minh Hạnh |

Hanoi accelerates site clearance for Ring Road 2.5 - Linh Nam project, but many obstacles put the progress at risk of slowing down.

Hanoi is accelerating the project to upgrade and expand Linh Nam road (belonging to Ring Road 2.5) to reduce congestion and complete infrastructure in the southern area. However, site clearance (GPMB) is still a major "bottleneck", with the risk of affecting progress.

For many years, Linh Nam road has always been narrow and overloaded, especially during rush hours. The route passes through crowded residential areas, interspersed with markets, schools and production facilities, so it is often congested and flooded when it rains heavily, posing a potential traffic unsafety.

Các đơn vị đang đẩy nhanh tiến độ thi công. Ảnh: Long Phi
Units are speeding up construction progress. Photo: Long Phi

The project is invested by Vinh Hung Ward People's Committee, about 3.4km long, connecting from Tam Trinh intersection to Nguyen Khoai dike. In which, the section from Vinh Hung intersection to Nguyen Khoai dike belongs to Ring Road 2.5, playing an important inter-regional connecting role.

According to the plan, the road will have a cross-section widened from 22.5m to 40m, with a scale of 4–6 lanes, synchronously investing in technical infrastructure. The total recovered area is about 98,345m2, involving nearly 800 households and 34 organizations in 5 wards: Linh Nam, Vinh Hung, Vinh Tuy, Hoang Mai and Tuong Mai.

The goal is to complete site clearance in the second quarter of 2026. Localities are focusing on removing obstacles, prioritizing resettlement arrangements, and ensuring people's rights to create a clean ground.

Currently, the contractor is constructing according to the motto "where there is land, do it thoroughly". Many households have moved assets and handed over land. People said that the project has been prolonged for many years, affecting their lives, but they expect that when completed, it will reduce congestion and improve the living environment. However, they hope that the compensation, support, and resettlement policies will be implemented satisfactorily.

Hà Nội thúc tiến độ đường Lĩnh Nam, vướng giải phóng mặt bằng. Ảnh: Long Phi
Hanoi urges progress on Linh Nam road, entangled in site clearance. Photo: Long Phi

Vice Chairman of Vinh Hung Ward People's Committee - Mr. Ngo Manh Cuong said that the total investment after adjustment is more than 2,860 billion VND, of which site clearance costs account for a large proportion. The project was approved in 2013 and has been adjusted many times.

Currently, site clearance work is being implemented synchronously: Vinh Tuy ward has achieved about 90%; Linh Nam ward has been completed; Vinh Hung ward basically meets the progress. Meanwhile, Hoang Mai and Tuong Mai wards still have many problems.

In Vinh Hung ward, land has been recovered from 253 households and 10 organizations; about 2/3 of the site has been handed over. 123 households have been approved for compensation plans, of which 76 households have received money and handed over the site; 49 households are publicly disclosing the draft plan. The main difficulty is the complex origin of the land, diverse legal documents, causing verification and planning to take a lot of time.

According to Mr. Cuong, officials must go directly to each household, often working until evening to dialogue and review dossiers. Thanks to that, most people have agreed, and there is currently only one case that has not been agreed upon.

According to the direction, the project must complete site clearance before March 31, 2026. However, with the current progress, some areas are at risk of delay.

In Tuong Mai ward, the route is 1,745m long, involving 225 households and 7 organizations, but only 96 households have their plans approved; many cases have not completed dossiers. Similarly, Hoang Mai ward has a route of about 1.53km long, involving 272 households and 11 organizations, but progress is still slow.

Representatives of Vinh Hung Ward People's Committee said that only Vinh Hung, Linh Nam and Vinh Tuy wards are likely to complete on schedule; Hoang Mai and Tuong Mai may be extended to April 2026, putting the entire project at risk of delay. The main reason is difficulties in verifying land origin and developing compensation and resettlement plans.

Currently, the contractor has deployed in many sections with land such as the Nguyen Khoai slope area, Long Thuyen market, No. 419 Linh Nam and in front of the textile factory. However, construction is difficult due to weak soil foundation, requiring complex technical treatment. Some sections longer than 50m must be deeply dug, pumped water, reinforced foundation and driven piles to ensure stability.

In addition, many areas in Hoang Mai and Tuong Mai have not completed site clearance, so synchronous construction is not possible.

According to the Project Management Board, site clearance is a decisive factor in the progress. The locality is implementing it according to the principles of publicity, transparency, legality and ensuring the rights of the people.

Đẩy nhanh tiến độ giải phóng mặt bằng, mở rộng đường Lĩnh Nam về đích trước hạn. Ảnh: Long Phi
Accelerate site clearance progress, expand Linh Nam road to reach the finish line ahead of schedule. Photo: Long Phi

With the determination of Hanoi City and the involvement of localities, the goal is to soon complete site clearance, creating conditions for the project to be completed in 2026. When completed, Linh Nam - Ring Road 2.5 will contribute to reducing congestion, improving traffic and opening up new development space for the southern area of the Capital.

Minh Hạnh
RELATED NEWS

Hanoi uses site clearance results as a measure to evaluate leaders

|

Hanoi - The city will take site clearance results as a direct measure to assess the level of task completion of the head.

Mobilizing people to agree on site clearance for National Highway 6 upgrade project

|

Hanoi - The Vietnam Fatherland Front Committee of Phu Nghia commune continues to mobilize people to agree on site clearance for the National Highway 6 renovation and upgrade project.

778 billion VND underpass project in Hanoi entangled in "super-thin houses", unable to complete site clearance

|

Hanoi - Ring Road 2.5 underpass project has some works that have not been cleared, the Traffic Management Board requests investors and authorities to handle them thoroughly.

The appearance of the 10-lane road in Dong Nai connecting Ho Chi Minh City is about to open to traffic

|

Dong Nai - Road 25B (Ton Duc Thang road) from National Highway 51 to the center of Nhon Trach commune is about to be opened to traffic with 10 lanes.

US declares Iran has no cards left at the negotiating table

|

US-Iran negotiations in Pakistan face many obstacles as disagreements on preconditions have not been resolved.

Exemption from Russian oil sanctions expires today, Asia puts pressure on the US

|

Some Asian countries are putting pressure on the US to extend the easing mechanism of sanctions against Russian oil, while Europe is showing disagreement.

Live football U20 Vietnam women vs U20 Japan women in the Asian quarter-finals

|

Live football match between Vietnam U20 women's team and Japan U20 women's team in the 2026 Asian quarter-finals, taking place at 4:00 PM today (April 11).

Proposal to relax regulations on holiday swaps so that workers can have continuous leave

|

Regulations on compensatory days are still "rigid", making it not feasible to swap working days to extend holidays; many opinions suggest that it should be relaxed in a more flexible direction.

Hanoi uses site clearance results as a measure to evaluate leaders

HOÀI ANH |

Hanoi - The city will take site clearance results as a direct measure to assess the level of task completion of the head.

Gần 500 hộ tự nguyện tháo dỡ công trình, nhà ở, bàn giao mặt bằng dự án nâng cấp Quốc lộ 6

Anh Tuấn |

Hà Nội - Theo UBND xã Phú Nghĩa, trong quý I/2026 đã có gần 500 hộ tự nguyện tháo dỡ công trình, nhà ở, giao mặt bằng dự án nâng cấp Quốc lộ 6.

Mobilizing people to agree on site clearance for National Highway 6 upgrade project

Anh Tuấn |

Hanoi - The Vietnam Fatherland Front Committee of Phu Nghia commune continues to mobilize people to agree on site clearance for the National Highway 6 renovation and upgrade project.

778 billion VND underpass project in Hanoi entangled in "super-thin houses", unable to complete site clearance

SÓNG HỮU |

Hanoi - Ring Road 2.5 underpass project has some works that have not been cleared, the Traffic Management Board requests investors and authorities to handle them thoroughly.