Hung Yen requests basic completion of site clearance for Khoai Chau Golf Course project before April 30

Mai Hương |

Hung Yen - April 2nd, the Provincial People's Committee listened to a report on the progress of site clearance for the Khoai Chau eco-tourism urban complex and golf course project.

According to a report by the Department of Agriculture and Environment, as of April 1, the total area to be recovered in phase 1 of the project is 569.05ha; localities have issued notices of land recovery reaching 100%.

The work of preparing and approving compensation, support, and resettlement plans reached 254.78ha, equivalent to 44.77%, an increase of 5.62% compared to the 24th. 3. The area that has been paid for compensation and support reached 176.36ha, equivalent to 30.99%, an increase of 2.10% compared to before.

However, the implementation process still has some difficulties and obstacles, especially in land recovery and planning compensation and support for Dai Nam Co., Ltd. On March 31, the Department of Agriculture and Environment and the Department of Construction coordinated with the People's Committee of Chau Ninh commune, Land Fund Development Center No. 1 and the investor to hold a meeting and agree on a handling plan.

At the meeting, delegates focused on analyzing the causes of existing problems and obstacles, and at the same time proposed solutions to accelerate the progress of site clearance.

The Department of Agriculture and Environment requested the Provincial People's Committee to direct localities and relevant units to focus manpower, urgently complete and approve compensation, support, and resettlement plans; organize payments to people, soon hand over land to investors, and strive to complete before April 30 according to the direction of the Provincial Key Project Steering Committee.

Lãnh đạo tỉnh yêu cầu tập trung tháo gỡ khó khăn, đẩy nhanh tiến độ giải phóng mặt bằng dự án. Ảnh: Tất Đạt
Provincial leaders requested to focus on removing difficulties and accelerating the progress of project site clearance. Photo: Tat Dat

Concluding the meeting, Vice Chairman of the Provincial People's Committee Nguyen Hung Nam acknowledged the proactiveness of departments, branches, and localities, but also frankly pointed out that the progress of site clearance is still slow and has not met the set requirements.

The Vice Chairman of the Provincial People's Committee assigned the Department of Agriculture and Environment to preside over and coordinate with relevant units to focus on thoroughly removing difficulties and obstacles; organize flexible and drastic implementation, in accordance with legal regulations, ensuring progress. The goal is to basically complete site clearance by April 30, creating conditions to soon start construction of the Club House area of the project.

At the same time, departments, branches, and localities are required to strengthen propaganda, publicize, and make transparent mechanisms and policies for compensation, support, and resettlement in order to create consensus among the people; ensure the legitimate rights and interests of people and businesses, and promptly detect and prevent acts of policy profiteering and violations of the law.

In the process of implementation, if difficulties and obstacles arise, units continue to report to the Provincial People's Committee for timely direction to remove them.

Mai Hương
RELATED NEWS

Series of large projects in Hue are directed to accelerate

|

HUE - Hue City leaders inspect and request to accelerate the progress of a series of key transportation, industrial, and tourism projects.

Progress of energy projects in Khanh Hoa

|

Khanh Hoa - The locality has just announced the progress of energy projects, and pointed out many obstacles that cause many projects to be behind schedule.

Gia Lai welcomes 26 new projects, registered capital of more than 65,700 billion VND

|

Gia Lai - April 1st, Gia Lai Department of Finance said that in March 2026, the whole province attracted 26 new investment projects, with a total registered capital of more than 65,700 billion VND.

Government stipulates principles for management and use of trade union funds

|

Decree No. 105/2026/ND-CP of the Government has stipulated the subjects of application, principles for management and use of trade union funds and the deadline for paying trade union fees.

Gold prices reverse sharply after Trump's speech

|

Gold prices turned down after Donald Trump's statement, which did not clarify the prospect of cooling down the conflict, causing the market to become cautious again.

Iran declares to continue attacking the US and Israel

|

Iran affirmed that it would escalate the war, denied the assessment of weakening military capabilities and denied the current ceasefire negotiations.

Car crashes into barrier on Nhat Tan bridge, suspected to be due to driver drowsiness

|

Hanoi - A car moving on Nhat Tan bridge lost control and crashed into a barrier separating the lane.

Stock market unexpectedly adjusts

|

The stock market closed the second trading session of April emotionally, with continuous tug-of-war.

Series of large projects in Hue are directed to accelerate

PHÚC ĐẠT |

HUE - Hue City leaders inspect and request to accelerate the progress of a series of key transportation, industrial, and tourism projects.

Progress of energy projects in Khanh Hoa

Hữu Long |

Khanh Hoa - The locality has just announced the progress of energy projects, and pointed out many obstacles that cause many projects to be behind schedule.

Gia Lai welcomes 26 new projects, registered capital of more than 65,700 billion VND

Hoài Phương |

Gia Lai - April 1st, Gia Lai Department of Finance said that in March 2026, the whole province attracted 26 new investment projects, with a total registered capital of more than 65,700 billion VND.