Problems in 3 trillion-dollar industrial park projects in Bac Ninh

Vân Trường |

Three industrial park (IP) projects in Bac Ninh are facing difficulties in site clearance and procedures for granting investment certificates to secondary investors.

Gia Binh II Industrial Park Project is invested by Hanaka Group Joint Stock Company (Hanaka Group), with a total investment of VND 3,956.8 billion. The project has a total area according to the approved planning of 250 hectares. Up to now, 247.5 hectares have been compensated and cleared.

According to the reporter's records, the investor has leveled about 50% of the total area of ​​the industrial park; basically completed internal roads in the industrial park and wastewater treatment plant; and has attracted 3 secondary investors.

Speaking to reporters, a representative of Hanaka Group - the project investor, said that the project is having trouble with land acquisition for the remaining land area, because households have not received money according to the approved compensation decisions.

Similarly, the Gia Binh Industrial Park project is invested by Bac Ninh Industrial Park Infrastructure Construction and Investment Company Limited, with a total investment capital of more than VND 2,578 billion. Up to now, the technical infrastructure items have basically been completed.

Ben trong du an KCN Gia Binh (Bac Ninh). Anh: Van Truong
Inside Gia Binh Industrial Park project (Bac Ninh). Photo: Van Truong

However, the project is also facing problems with land acquisition for 64 households that have not received compensation for a total area of ​​about 0.88ha; specific instructions for the area within the external traffic boundary...

Or the investment project to build and operate the technical infrastructure of Thuan Thanh III Industrial Park - Sub-area B, invested by Trung Quy Investment Joint Stock Company with a scale of 300.04 hectares. The total investment capital for infrastructure after project adjustment is more than 3,100 billion VND.

Currently, the project still has 72.14 hectares of industrial park land that has not been compensated for site clearance.

At the same time, in the above 3 industrial park projects, in addition to the difficulties in site clearance, investors also said that the procedures for granting investment certificates for projects leasing land in industrial parks are facing difficulties due to changes in the Law on Real Estate Business 2023, effective from August 1, 2024, which stipulates that investment in the construction of technical infrastructure works must be completed and the project progress must be approved by competent State agencies.

Regarding the problems in the above industrial park projects, Chairman of Bac Ninh Provincial People's Committee Vuong Quoc Tuan requested localities with industrial park projects to urgently complete site clearance work, hand over clean land, so that industrial park infrastructure investors can complete the remaining infrastructure works.

Regarding the procedures for granting investment certificates for secondary projects, Mr. Vuong Quoc Tuan assigned the Bac Ninh Provincial Industrial Park Management Board to coordinate with relevant departments and branches to work with competent central agencies to have written responses, instructions and adjust regulations to suit reality.

Vân Trường
RELATED NEWS

Bac Ninh spends 565 billion VND to restore relics with national treasures

|

National treasures in Bac Ninh are places that attract tens of thousands of tourists to visit, research and learn.

Man City takes the top spot in Arsenal's Premier League table

|

On the night of December 27 (Vietnam time), Man City defeated Nottingham Forest 2-1, thereby temporarily taking the top spot in Arsenal's Premier League table.

ASEAN observer group in handling Cambodia-Thailand disagreements

|

Vietnam is ready to work with ASEAN to resolve Thailand-Cambodia disagreements, including strengthening the effectiveness of the ASEAN observer group.

U19 Vietnam futsal team loses Southeast Asian semi-final match

|

On the afternoon of December 27, in Thailand, U19 Vietnam futsal suffered a 3-7 defeat to U19 Indonesia futsal in the semi-finals of the 2025 Southeast Asian U19 Futsal Championship.

Identities of 18 casualties in the overturned truck carrying a charity delegation in Lao Cai

|

Lao Cai - Functional agencies have identified the identities and health status of the victims in the overturned truck carrying the charity delegation.

Female workers contribute to beautifying Da Lat to attend the Patriotic Emulation Congress

|

Lam Dong - Ms. Trinh Thi Phung - Da Lat Urban Services Joint Stock Company was honored to represent more than 92,000 workers at the National Patriotic Emulation Congress.

Estimated number of Ukrainian soldiers leaving the army in 2025

|

The number of Ukrainian soldiers defecting in 2025 is said to account for 1/4 of the country's total army.

Ba Ngan bridge opens to motorbikes, reconnecting the bridge to live on for Da Nang workers

|

Da Nang - Ba Ngan bridge (Duy Phuoc bridge) has officially allowed motorbike traffic after a period of lightning-fast construction of an emergency steel girder span.

Bắc Ninh sẽ sáp nhập 3 trường Cao đẳng, Trung cấp

Vân Trường |

Bắc Ninh dự kiến sẽ sáp nhập 3 trường: Cao đẳng Sư phạm, Cao đẳng Y tế và Trung cấp Văn hóa, Nghệ thuật và Du lịch.

Doanh nghiệp giấy ở Bắc Ninh đồng thuận dời khỏi khu dân cư

Vân Trường |

Bắc Ninh - Nhiều doanh nghiệp sản xuất giấy ở Phú Lâm, Phong Khê đã đồng thuận với phương án di dời khỏi khu dân cư, nhằm bảo vệ môi trường.

Bac Ninh spends 565 billion VND to restore relics with national treasures

Vân Trường |

National treasures in Bac Ninh are places that attract tens of thousands of tourists to visit, research and learn.