Working through sun and rain
As noted by Labor in recent days, at many column foundation locations of the 500kV circuit 3 line (through Thanh Hoa), engineers and workers in the electricity industry are rushing, "racing against time" to Construction of project items.
While quickly constructing at the foundation position of column No. 173 (section passing Dong Hoang commune, Dong Son district, Thanh Hoa province), Mr. Hoang Xuan Sy (56 years old) - Thua Thien Hue Power Transmission officer - said, he is one of dozens of Electricity industry officials from Thua Thien Hue to Thanh Hoa supporting the construction of 500kV circuit 3 line.
“We have been going to Thanh Hoa to strengthen for more than 2 months now. The time we left was right during the period of unfavorable weather, some times the heat was extremely harsh, some times it rained continuously. Working in such weather made it quite difficult for us. However, because of the common progress, everyone tried to work hard, regardless of the weather" - Mr. Sy shared.
Also according to Mr. Sy, now is the sprint phase to complete the remaining column foundation items, so the team members are even more enthusiastic, working in 3 shifts of 4 teams to complete the workload as scheduled. go out.
Sharing the same sentiment as Mr. Sy, Mr. Van Ngoc Sang - Team Leader of Phu Loc Power Transmission Team, Thua Thien Hue Power Transmission - said that for about the past half month, the weather in Thanh Hoa has been raining continuously, even sometimes. It was pouring rain that day, so it had a significant impact on construction work at the construction site.
“In general, for us, work is hard whether it's rain or shine. When it's sunny, we're tired and dehydrated. When it rains heavily, we have to stop, and when the rain stops, we run out to work again. In addition, construction in terrain such as hills and fields makes it more difficult," said Mr. Sang.
Also according to many officials and workers in the electricity industry from the southern provinces who have come to Thanh Hoa, they have not been able to go home for many months, and they somewhat miss their wives, children, and families. Therefore, their late hope is to make efforts to quickly complete the project and return to their families, wives and children.
Remove difficulties
It is known that regarding the problems and difficulties in the process of constructing the 500kV circuit 3 line through Thanh Hoa province, recently, Vietnam Electricity Group and Thanh Hoa Provincial People's Committee had a working session on the project. project construction support.
At this meeting, the Central Power Project Management Board - representative of the investor proposed that Thanh Hoa province continue to support propaganda and urge households with remaining houses and projects to dismantle and relocate. exit the safety corridor and salvage and clear the remaining trees.
At the same time, pay attention to support the approval of compensation plans for the remaining foundation locations and corridors; support in resolving related problems and issues arising during the construction process, including related to the return of public service roads, inter-village and inter-commune roads and organizing to ensure security and order for construction for cases of intentionally obstructing construction.
In particular, the investor proposed that Thanh Hoa direct the People's Committee of Nhu Thanh district to complete a plan to ensure construction security for wire pulling work (at about columns 70-71 and 71-72 through Thanh Ky commune). because the households received compensation according to the approved plan but prevented the construction unit from pulling the rope; Nghi Son Town People's Committee resolved problems in some locations where people petitioned not to be compensated for site clearance due to overlapping areas.
In response to the investor's proposal, the representative of the People's Committee of Thanh Hoa province pledged that the locality will mobilize the maximum resources to accompany the investor and construction units, determined to complete the project. in accordance with the instructions of the Prime Minister.