5 key projects in Ho Chi Minh City missed deadline in 2024

Anh Tú |

Five key transport projects in Ho Chi Minh City were expected to be completed by the end of 2024, but due to slow progress, they have now been forced to be postponed to 2025.

Tan Ky Tan Quy Bridge

One of the notable projects at the western gateway is Tan Ky Tan Quy Bridge (Binh Tan District). This project has a total investment of more than 668 billion VND, and was restarted in June 2024 after a long period of stagnation due to land acquisition problems. Initially, the main bridge was expected to be completed and opened to traffic in December 2024, but so far the progress is still delayed.

Cau
Tan Ky Tan Quy bridge construction site is speeding up progress after postponing the opening date to early 2025. Photo: Anh Tu

The main reason for the delay is the failure to agree on the method of relocating the medium and low voltage grid and transformer stations at both ends of the bridge. Therefore, the completion date has been postponed to January 2025.

Ba Hom Bridge

Similarly, the Ba Hom Bridge project (Binh Tan District) started in 2018 with a total investment of about 374 billion VND, is also facing problems related to the relocation of the power system, affecting the completion plan by the end of this year.

Hang loat tru dien an ngu giua duong tai khu vuc thi cong du an cau Ba Hom. Anh: Anh Tu
A series of electric poles block the road at the construction site of Ba Hom bridge project. Photo: Anh Tu

Tran Quoc Hoan - Cong Hoa connecting road

In Tan Binh District, the Tran Quoc Hoan - Cong Hoa connecting road project also met the same fate. This is a key project to reduce the load on the gateway area of ​​Tan Son Nhat Airport, where serious traffic jams often occur.

According to the original plan, the project would be completed by the end of 2024. However, problems with Package 13, which has 67 households and part of the area belonging to Textile Factory 7, have delayed the handover of the site.

According to the Ho Chi Minh City Traffic Construction Investment Management Board, if the site is handed over as soon as possible (at least two months before the opening date), the entire project can be completed before February 28, 2025.

ham chui
The Tran Quoc Hoan - Phan Thuc Duyen underpass was opened to traffic earlier. Photo: Anh Tu
Mot doan thuoc du an duong
A section of the Tran Quoc Hoan - Cong Hoa road project is stuck with residential land. Photo: Anh Tu

Expanding Duong Quang Ham Street

The Duong Quang Ham Street expansion project (Go Vap District) has also been delayed due to similar difficulties. The project has a total investment of more than VND2,000 billion, with the goal of upgrading the 2.5 km long, 32 m wide, 6-lane road.

However, the construction progress has encountered many difficulties because the handover of the site has been sporadic and unsynchronized. Up to now, Ho Chi Minh City Power Corporation has only received about 60% of the site and is facing difficulties in undergrounding the power cable lines. It is expected that the completion of undergrounding the power grid will last until April 2025 and will be completed in June 2025.

Hien hang tram cay cot dien van con ngon ngang ngay giua cong trinh va hai ben duong chua duoc di doi. Anh: Anh Tu
Currently, hundreds of electric poles are still lying in the middle of the construction site and on both sides of the road and have not been moved. Photo: Anh Tu
Thoi gian thi cong keo dai khien viec sinh hoat, di lai cua nhung ho dan song tren tuyen duong Duong Quang Ham tro nen bat tien vi khong co duong ra vao.
The long construction period makes the daily life and travel of local residents quite inconvenient. Photo: Anh Tu

An Phu Interchange

One of the key projects in the east of the city, the An Phu traffic intersection project (Thu Duc City), also recorded slow disbursement progress.

The An Phu intersection project has a total investment of more than 3,400 billion VND. This project, when completed, is expected to contribute to reducing traffic congestion in the East of Ho Chi Minh City, but due to land issues, the construction progress has been affected.

Toan canh du an nut giao An Phu van con ngon ngang. Anh: Anh Tu
Panoramic view of the An Phu intersection project still in disarray. Photo: Anh Tu
Do cham tien do, toan du an du kien hoan thanh toan bo cuoi 2025. Anh: Anh Tu
Due to delays, the entire project is expected to be completed by the end of 2025. Photo: Anh Tu

According to plan, a branch of the HC1 underpass was expected to open to traffic by the end of this year, but because the workload has only reached nearly 70%, the completion time has been forced to be postponed to 2025.

The main reason is the problem with the land area at the approach road and overpass towards Luong Dinh Cua street, with an area of ​​over 20,000m², belonging to the An Phu urban area project invested by Thu Thiem Investment Joint Stock Company.

Although the Ho Chi Minh City Department of Transport has repeatedly requested Thu Duc City to hand over the site soon, the exact time has not yet been determined.

Doan dau duong Luong Dinh Cua giao nut giao An Phu van con vuong mat bang. Anh: Anh Tu
The first section connecting Luong Dinh Cua Street to An Phu intersection still has land clearance problems. Photo: Anh Tu

Anh Tú
TIN LIÊN QUAN

Ho Chi Minh City - Tay Ninh breaks through connection with two key projects

|

The Ho Chi Minh City - Moc Bai Expressway and the National Highway 22 expansion project are about to be implemented, helping to reduce congestion and enhance connectivity between Ho Chi Minh City and Tay Ninh, contributing to completing the traffic network of the Southern Key Economic Zone and promoting international transport to Cambodia.

Reviving a national key project after 3 decades of being "suspended"

|

Although it is a key project, the project to build technical infrastructure and urgent works for Da Nang University in Hoa Quy (Da Nang City) - Dien Ngoc (Quang Nam Province) has been "suspended" for nearly 3 decades, causing much frustration among local people.

More than 100 children in Nghe An get seasonal flu every day

|

On average, every day, Nghe An Obstetrics and Pediatrics Hospital receives from 100 to 125 children with seasonal flu for examination and treatment.

Dam Vinh Hung's reaction to the news of losing almost his entire foot

|

Before the news about the photo of a foot missing 4 toes, believed to be Dam Vinh Hung's, the reporter contacted the male singer to find out the situation.

Huong Pagoda is deserted, tourists go to worship in the rain

|

Although it is still early in the year, the number of visitors to Huong Pagoda these days is quite sparse. Many visitors expressed surprise at the many changes in this year's festival.

Hanoi Police entered the semi-finals of the Southeast Asian Cup C1 with a perfect record

|

On the evening of February 6, Hanoi Police defeated Borneo Samarinda, thereby entering the semi-finals of the Southeast Asian Cup C1 with an all-win record.

Strong cold air mass, forecast to be very cold

|

According to a representative of the meteorological agency, due to the impact of continuously strengthening cold air, the Northern region, Thanh Hoa, Nghe An and Ha Tinh will experience severe cold from tomorrow, February 7.

Owner of "rip-off" restaurant in Nha Trang accused of owing 1.4 billion VND in rent

|

Khanh Hoa - The owner of a restaurant in Nha Trang was accused of "ripping off" Chinese tourists and currently owes the landlord more than 1.4 billion VND.

Ho Chi Minh City - Tay Ninh breaks through connection with two key projects

MINH QUÂN |

The Ho Chi Minh City - Moc Bai Expressway and the National Highway 22 expansion project are about to be implemented, helping to reduce congestion and enhance connectivity between Ho Chi Minh City and Tay Ninh, contributing to completing the traffic network of the Southern Key Economic Zone and promoting international transport to Cambodia.

Reviving a national key project after 3 decades of being "suspended"

Nguyễn Linh |

Although it is a key project, the project to build technical infrastructure and urgent works for Da Nang University in Hoa Quy (Da Nang City) - Dien Ngoc (Quang Nam Province) has been "suspended" for nearly 3 decades, causing much frustration among local people.