New direction on investment in the western section of the North-South Expressway

Xuyên Đông |

The Government has just issued new instructions on the North-South Expressway project, western section Gia Nghia - Chon Thanh.

Resolution No. 138/2024/QH15 of the National Assembly approved the investment project to build the North-South Expressway in the West, Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) section, with an investment scope of about 128.8 km, divided into 5 component projects. The preliminary total investment of the project is 25,540 billion VND, including: Central budget capital is 10,536.5 billion VND; local budget capital is 2,233.5 billion VND; capital arranged by investors is 12,770 billion VND.

The project will be implemented from 2024, basically completed in 2026, and put into operation in 2027.

Recently (September 20), the Government issued Resolution 147/NQ-CP implementing Resolution No. 138/2024/QH15.

Accordingly, the order, procedures, authority to appraise and decide on investment in component projects are as follows:

Component project 1 (investment in construction of expressway under public-private partnership method)

The People's Committee of Binh Phuoc province organizes the preparation of a Feasibility Study Report, submits it to the State Appraisal Council for appraisal, and submits it to the Prime Minister for approval according to the provisions of the Law on Investment under the public-private partnership method.

The management and use of state budget capital to support the construction of works and infrastructure systems arranged from public investment capital sources in component project 1 shall be implemented according to the provisions of Point b, Clause 5, Article 70 of the Law on Investment under the public-private partnership method.

The Ministry of Transport assigned the specialized construction agency to appraise the project's Feasibility Study Report.

Project group implementing investment in construction of service roads and overpasses (component project 2 and component project 3)

The Chairman of the People's Committee of Dak Nong and Binh Phuoc provinces exercises the authority of the investment decision maker, organizes the preparation and appraisal of the Feasibility Study Report and decides to approve the project.

The order, procedures, authority to appraise and decide on investment in component project 2 and component project 3 are implemented similarly to those for group B projects managed by localities according to the provisions of law on public investment.

Component project group implementing compensation, support, and resettlement (component project 4 and component project 5)

The Chairman of the People's Committee of Dak Nong and Binh Phuoc provinces exercises the authority of the investment decision maker, organizes the preparation and appraisal of the Feasibility Study Report and decides to approve the project.

The order, procedures, authority to appraise and decide on investment in component project 4 are implemented similarly to those for group B projects managed by localities according to the provisions of law on public investment.

The order, procedures, authority for appraisal and investment decision of component project 5 are implemented similarly to those for group A projects managed by localities according to the provisions of the law on public investment; assign the specialized construction agency under the People's Committee of Binh Phuoc province to organize project appraisal according to regulations.

The preparation, appraisal and decision to approve the appraisal results of environmental impact assessment reports are carried out for each component project, as follows:

The Ministry of Natural Resources and Environment organizes the appraisal and approval of the appraisal results of the environmental impact assessment report for component project 1 and component project 5.

The Provincial People's Committee organizes the appraisal and approval of the appraisal results of the environmental impact assessment report for component projects 2, 3 and 4.

Xuyên Đông
TIN LIÊN QUAN

Taking his child to do high school graduation exam procedures, father in Binh Dinh died, child seriously injured

|

Binh Dinh - Father drove a motorbike carrying his son to the high school graduation exam preparation point when he suddenly crashed into an electric pole, causing him to die on the spot and seriously injuring his son.

Mobilized with the message to 2k7 students before the graduation exam day of the principal in Nha Trang

|

Khanh Hoa - The principal of a high school in Nha Trang sent to 2k7 students with many emotions from the boat drivers before the special boat trip in 2025.

Hour 9: Unexpected meeting - Part 1

|

Hour 9 No. 160 - The wife waited for her missing husband for 10 years and then took another step. One day, if the husband returns, what will happen to this family?

Unbelievable confusion on the day of completing the procedures for taking the high school graduation exam in Hanoi

|

Hanoi - Some candidates confused the exam scores between My Dinh High School and My Dinh 1 Secondary School in the afternoon to complete the procedures for taking the high school graduation exam.

HCMC will auction land along 5 metro lines, expected to collect 152,000 billion VND

|

Ho Chi Minh City plans to collect about VND152,000 billion from the auction of land along 5 metro lines, including lines 1, 2, 3a, 4 and 5.

Bac Kan Secretary Hoang Duy Chinh becomes a member of the National Assembly Standing Committee

|

Mr. Hoang Duy Chinh - Secretary of the Bac Kan Provincial Party Committee was elected by the National Assembly to hold the position of Member of the National Assembly Standing Committee.

The Government finalizes the plan to merge 2 corporations into VNPT

|

Telecommunication Services Corporation, Communications Corporation officially merged into the Parent Company - Vietnam Post and Telecommunication Group (VNPT Group).

Camera of the accident between 2 passenger buses on the highway that killed 2 people

Duy Tuấn |

Binh Thuan - Camera recorded the scene of a passenger bus crashing into the back of a stopped passenger bus on the Vinh Hao - Phan Thiet highway, killing 2 people on September 19.

New information about the North-South Expressway west

Xuyên Đông |

The Ministry of Transport has just shared content related to the western section of the North-South Expressway.

Noi Bai - Lao Cai Expressway opens to traffic after 8 days of landslide

Đinh Đại |

A landslide has rendered the Noi Bai – Lao Cai expressway interchange (IC18) inoperable and will take many days to repair.