Traffic through Hai Van tunnel suspended tomorrow afternoon

Mai Hương |

On the afternoon of September 25, vehicles will temporarily stop circulating through Hai Van tunnel for 30 minutes to ensure traffic safety during the blasting process.

On September 24, the Management Board of Priority Infrastructure Investment Projects in Da Nang announced the plan for blasting and breaking the roadbed rock at the final intersection of the route connecting to Hai Van - Tuy Loan tunnel, part of the coastal road project connecting Lien Chieu port (phase 1).

According to the plan, the blasting time is from 1:15 p.m.to 1:45 p.m.on September 25.The blasting location is at the final intersection of the coastal road project connecting Lien Chieu port in Hoa Hiep Bac ward (Lien Chieu district).

Ben trong ham Hai Van. Anh: Minh Long
Inside Hai Van tunnel. Photo: Minh Long

During this time, all traffic through the blasting site and related residential roads will be temporarily stopped for about 30 minutes.

Traffic Police, construction units and Hai Van Tunnel Traffic Control Center will coordinate to arrange 3 checkpoints to regulate and temporarily stop traffic, ensuring traffic safety during the blasting period.

Checkpoint No. 1 is located at the northern entrance of Hai Van Tunnel. Checkpoint No. 2 is located 30m north of Ta Quang Buu roundabout and Nam Hai Van - Tuy Loan road. Checkpoint No. 3 is located north of Bridge No. 4 of Nam Hai Van - Tuy Loan road.

It is known that this is the first blasting in the blasting plan for the construction of the coastal road connecting Lien Chieu port. There are expected to be a total of 40 blasts during the construction process.

The project to invest in the construction of the coastal road connecting Lien Chieu port has a total investment of 1,203 billion VND, invested by the Management Board of Priority Infrastructure Investment Projects of Da Nang. The road is nearly 3km long, 30m wide, and includes 6 lanes. The project started in September 2023 and is expected to be completed and put into use by the end of 2025.

Mai Hương
RELATED NEWS

Hanoi barricades many points at Co Linh - Dam Quang Trung intersection

|

Hanoi - From March 18, Hanoi Department of Construction will barricade the Co Linh - Dam Quang Trung intersection to serve the underpass construction project.

The stock market is still under great adjustment pressure

|

The stock market may still be volatile as cautious sentiment dominates cash flow.

Multiple traffic accidents on National Highway 29, 1 dead

|

Dak Lak - A series of traffic accidents on National Highway 29 has caused 1 death and many vehicles to be heavily damaged.

Iran sets conditions for ceasefire with US

|

Iranian Foreign Minister Abbas Araghchi affirmed that the country's armed forces will not stop firing until the US admits its mistakes.

Wood chip factory "stuck" due to planning issues on expressway compensation land

|

Quang Tri - The enterprise's chip factory has to be relocated to serve the expressway but cannot be rebuilt on compensated land due to planning problems, causing production to be disrupted.

Villagers of Pang wish to settle down in the flood center

|

Lao Cai - After the flash flood in September 2025, many new houses were built in Pang Village, Phong Du Ha commune to help people stabilize their lives.

Cuba nationwide power outage after weeks of US oil blockade

|

Cuba's power grid collapsed across the island on March 16, local time.

Đà Nẵng sẽ quản lý hòn Sơn Chà và khu vực Nam núi Hải Vân

Lê Trọng |

Văn phòng Chính phủ vừa có thông báo về xác định địa giới hành chính giữa tỉnh Thừa Thiên Huế và TP Đà Nẵng.

Đề xuất cải tạo đường sắt đèo Hải Vân và di dời ga Đà Nẵng

Mai Hương |

Cục Đường sắt Việt Nam vừa đề xuất lập dự án cải tạo đường sắt khu vực đèo Hải Vân và di dời ga Đà Nẵng.

Di tích Hải Vân Quan còn thiếu nhiều hạ tầng dịch vụ

Mai Hương - Nguyễn Linh |

Đà Nẵng - Do việc xây dựng phương án khai thác dịch vụ du lịch tại di tích Hải Vân Quan vẫn còn nằm trên giấy nên nơi đây vẫn còn ngổn ngang, chưa hoàn thiện.