Construction and installation of 80T scale equipment - Construction of foundation, crane column extension and connecting the rail to side 3HA started in February 2024 and was completed in June 2024.
The project was built on an area of 1,000 m2, with a total cost of 1,786 million VND. In which, the participating members contributed 100 working days.
After being put into use, the project will help reduce time and manpower in the work of weighing and measuring the load of vehicles transporting products of the company and customers; improve the efficiency of accurately measuring the load of vehicles transporting concrete products (ensuring traffic safety when moving on the road).