Van Phong - Nha Trang Expressway cannot be opened to traffic during Tet

Hữu Long |

Contractors are completing the final stages to put the Van Phong - Nha Trang expressway into operation.

Cao toc Van Phong - Nha Trang dai hon 83km, di qua thi xa Ninh Hoa va 3 huyen Van Ninh, Dien Khanh, Khanh Vinh cua tinh Khanh Hoa. Cong trinh co quy mo 4 lan xe, rong 17m, van toc toi da 90km/h, duoc khoi cong hoi dau nam 2023, voi tong muc dau tu hon 11.800 ty dong.
The Van Phong - Nha Trang Expressway is 83km long, has 4 lanes, is 17m wide, and has a maximum speed of 90km/h. Construction will start in early 2023, with a total investment of more than 11,800 billion VND.
cuoi thang 12/2024, mot so nha thau da co van ban gui Bo Giao thong Van tai va Ban quan ly du an 7 (chu dau tu du an cao toc Van Phong - Nha Trang) de nghi dua vao khai thac su dung 68,35km noi tu cao toc Nha Trang - Cam Lam den nut giao Van Gia, thuoc du an Van Phong - Nha Trang truoc ngay 10/1/2025, tuc truoc Tet At Ty.
At the end of 2024, some contractors proposed to put the 68.35km expressway connecting Nha Trang - Cam Lam to Van Gia intersection into operation before January 10, 2025, before Tet At Ty.
Ong Dang Van Dung - Giam doc du an cao toc Van Phong - Nha Trang cho biet, qua kiem tra hien truong thi tren toan tuyen van con nhieu hang muc chua thi cong, dac biet la he thong an toan giao thong va gia co mai ta luy.
Although some contractors have proposed to exploit the route, the investor has not yet agreed. Mr. Dang Van Dung - Director of the Van Phong - Nha Trang Expressway Project explained that through on-site inspection, there are still many items that have not been constructed along the entire route, especially the traffic safety system and embankment reinforcement.
Doan tuyen duoc cac nha thau de xuat moi chi thi cong xong mat duong, khi ban giao con rat nhieu thu tuc, phai hoan thanh he thong an toan giao thong, bien bao, nut giao de xe nhap, tach lan.
The section proposed by the contractors has only completed the road surface. To hand over, the traffic safety system, signs, and intersections for vehicles to merge and separate lanes need to be completed.

Cong trinh dai hon 83 km, di qua thi xa Ninh Hoa va ba huyen Van Ninh, Dien Khanh, Khanh Vinh. Du kien cong trinh giao thong nay se hoan thanh vao ngay 30.4.2025, truoc 8 thang so voi ke hoach.
Currently, contractors on the Van Phong - Nha Trang Expressway are rushing to complete the final items to put the expressway into operation, nearly 4 months ahead of schedule.
Trong tuong lai, Cao toc Van Phong - Nha Trang khi dua vao hoat dong giup ket noi voi cac cao toc khac tren hanh trinh va se rut ngan khoang cach, thoi gian di chuyen.
In the future, when put into operation, Van Phong - Nha Trang Expressway will help connect with other expressways on the route and shorten the distance and travel time.

Hữu Long
RELATED NEWS

On the highway from Ho Chi Minh City to Nha Trang, are there any rest stops?

|

On the highway from Ho Chi Minh City to Nha Trang, there are many rest stops, basically meeting the drivers' resting needs.

Camera records the scene of a series of collisions between 2 passenger vans and a car on the highway

|

Binh Thuan - Camera recorded a series of collisions between 2 passenger vans and a car on the Vinh Hao - Phan Thiet highway, causing traffic jams for hours.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

|

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

Enrollment 2026: List of schools considering exam scores for competency and thinking assessment

|

Many universities have begun to announce their expected enrollment plans for 2026. In which, many schools use competency and thinking assessment exam scores for admission consideration.

The night before the election and people staying up with their votes

|

Can Tho - Security teams at the polling station quietly guarded overnight, contributing to maintaining safety for the election day.

Ho Chi Minh City builds 6 metro lines by 2030, inviting 7 ministries and sectors to support

|

Ho Chi Minh City sets a target to complete 6 metro lines before 2030, and at the same time invites 7 central ministries and sectors to participate in the appraisal team for bidding packages.

The joy of the first time going to the polls of young soldiers in Dak Lak

|

Dak Lak - Young soldiers express joy and pride when for the first time in their lives holding a ballot to fulfill the rights and responsibilities of citizens.

Ho Chi Minh City center is about to have an underground parking lot and a multi-story parking lot

|

Ho Chi Minh City - Ho Chi Minh City Center will build underground parking lots and multi-story parking lots to meet parking needs, limiting the situation of occupying roads and sidewalks.

On the highway from Ho Chi Minh City to Nha Trang, are there any rest stops?

Duy Tuấn |

On the highway from Ho Chi Minh City to Nha Trang, there are many rest stops, basically meeting the drivers' resting needs.

Camera records the scene of a series of collisions between 2 passenger vans and a car on the highway

Duy Tuấn |

Binh Thuan - Camera recorded a series of collisions between 2 passenger vans and a car on the Vinh Hao - Phan Thiet highway, causing traffic jams for hours.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.