Speeding up construction of the largest bridge on Ben Luc - Long Thanh highway

Anh Tú - Minh Tâm |

HCMC - After more than 1 year of restarting construction, Binh Khanh Bridge of the Ben Luc - Long Thanh Expressway project has reached 82% and is expected to be completed in September 2025.

Du an cau Binh Khanh (goi thau J1) thuoc Du an cao toc Ben Luc - Long Thanh bac qua song Soai Rap, noi huyen Can Gio voi Nha Be (TP. HCM).  Cau Binh Khanh la cay cau lon nhat tren tuyen cao toc nay voi tong von dau tu hon 2.800 ty dong, duoc khoi cong tu thang 8/2015 va du kien se hoan thanh sau 47 thang.
Binh Khanh Bridge Project (package J1) is part of the Ben Luc - Long Thanh Expressway Project spanning the Soai Rap River, connecting Can Gio District with Nha Be (HCMC). Binh Khanh Bridge is the largest bridge on this expressway with a total investment of over VND2,800 billion. Construction began in August 2015 and is expected to be completed in 47 months.
 Cuoi nam 2018 cau phai tam ngung thi cong do vuong mac ve von (thoi diem nay dat khoang 70% khoi luong). Thang 10.2023, cau Binh Khanh tai khoi dong tro lai, den nay da dat 82% ke hoach, cac cong nhan, ky su dang day nhanh tien do.
At the end of 2018, the bridge had to temporarily stop construction due to funding problems (at this time, it reached about 70% of the volume). In October 2023, Binh Khanh Bridge restarted, and has now reached 82% of the plan, and workers and engineers are speeding up the construction progress.
 Cau duoc thiet ke theo kieu day vang 2 mat phang ; do dai 2 nhip chinh giua long song la 375m, dat tren hai tru cau cao 155m voi mong tru thap co ket cau dang mong coc ong thep, tinh khong thong thuyen len den 55m, cao nhat Viet Nam o thoi diem hien tai.
The bridge is designed in a 2-plane cable-stayed style; the length of the 2 main spans in the middle of the river is 375m, placed on two 155m high bridge piers with a tower foundation of steel pipe piles, and a clearance of up to 55m.
 Chieu cao khoang khong giua gam cau voi mat nuoc duoc thiet ke de phuc vu cho nhung tau thuyen co trong tai lon, thuong xuyen luu thong tren song Soai Rap.
The height of the space between the bridge's undercarriage and the water surface is designed to accommodate large vessels that frequently travel on the Soai Rap River.
Theo ghi nhan, hien nay tren cong truong cong nhan dang tap trung duc hang, keo day vang, lam sat, do be tong cac dot… cac cong viec duoc trien khai dan trai.
According to records, currently at the construction site, workers are focusing on cantilever construction, cable-stayed construction, concrete pouring...
Giam doc Ban Quan ly cac duong cao toc phia Nam (Tong cong ty Dau tu phat trien duong cao toc Viet Nam) cho biet, den nay san luong cau Binh Khanh dat tren 82%. Cong nhan dang tap trung duc hang, lam day vang. “Voi tien do nay du kien khoang cuoi quy III, dau quy IV nam 2025 se hoan thanh cau Binh Khanh”, ong Vi thong tin.
According to the representative of the Southern Expressway Management Board (Vietnam Expressway Corporation), the output of Binh Khanh Bridge has reached over 82%. Workers are focusing on constructing cantilevers and cables. With this progress, it is expected that Binh Khanh Bridge will be completed by the end of the third quarter, early in the fourth quarter of 2025.
Doan duong dan len cau Binh Khanh bo phia Can Gio noi voi cau Phuoc Khanh ve phia Nhon Trach (Dong Nai) cung da co ban hoan thien.
The road leading to Binh Khanh bridge on Nha Be side connecting to Long An side is basically completed.
Con doan noi bo phia Can Gio cung da co ban hoan thien.
The section connecting the Can Gio shore has also been basically completed.
Khi cau Binh Khanh hoan thien, tuyen cao toc Ben Luc - Long Thanh se duoc thong suot tu cao toc TPHCM - Trung Luong den het dia ban TPHCM.
When Binh Khanh bridge is completed, Ben Luc - Long Thanh expressway will be open from Ho Chi Minh City - Trung Luong expressway to the end of Ho Chi Minh City.
Anh Tú - Minh Tâm
TIN LIÊN QUAN

Hình hài 3,5km cao tốc Bến Lức - Long Thành đi qua khu rừng ngập mặn xanh mát

HÀ ANH CHIẾN |

Đồng Nai - Tuyến đường cao tốc Bến Lức - Long Thành nhánh phía Đông kết nối miền Đông Nam bộ và miền Tây Nam bộ đi qua tỉnh Đồng Nai dài 27 km, trong đó có hơn 3,5 km đi xuyên qua rừng ngập mặn sắp đưa vào sử dụng sau 7 năm khởi công.

Hợp long cầu 720 tỉ đồng trên cao tốc Bến Lức - Long Thành đoạn Đồng Nai

HÀ ANH CHIẾN |

Đồng Nai – Ngày 9.7, hạng mục thi công cầu Thị Vải cùng các cầu cạn thuộc gói thầu A7 dự án đường cao tốc Bến Lức – Long Thành, đoạn qua địa phận tỉnh Đồng Nai đã hợp long.

Cận cảnh cầu dây văng lớn nhất cao tốc Bến Lức - Long Thành vừa thi công lại

Phương Ngân - Anh Tú |

TPHCM - Gói thầu J1 thi công cầu Bình Khánh thuộc dự án cao tốc Bến Lức - Long Thành đã được thi công trở lại sau nhiều năm tạm dừng. Dự kiến cây cầu này sẽ hoàn thành vào tháng 9.2024.

Bão số 3 ảnh hưởng thế nào đến đường dây 500kV

Anh Tuấn |

Tập đoàn Điện lực Việt Nam cho biết, bão số 3 (Yagi) đã gây ra một số sự cố lưới điện 500kV, tập trung chủ yếu ở Quảng Ninh, Hải Phòng.

Khánh thành trường vùng cao do Quỹ XHTT Tấm lòng Vàng Lao Động tài trợ

Nhóm PV |

Dãy phòng học 2 tầng do Quỹ Xã hội từ thiện Tấm lòng Vàng Lao Động xây tặng đem lại niềm vui cho cô và trò Trường Mầm non Hương Liên (Hương Khê, Hà Tĩnh).

Tin 20h: Bắt được kẻ đào trộm mộ tống tiền 5 tỉ đồng

Nhóm PV |

Tin 20h ngày 13.9: Bắt được đối tượng đào trộm mộ tống tiền 5 tỉ đồng; Giá rau xanh tại Hà Nội tăng chóng mặt sau ngập lụt...

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ

phóng viên |

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ.

Bảo hiểm bồi thường 945 triệu đồng vụ sạt lở vùi ôtô ở Cao Bằng

Lục Giang |

Nhiều doanh nghiệp bảo hiểm đã triển khai các biện pháp khẩn cấp để hỗ trợ khách hàng như khẩn trương giám định tổn thất, tạm ứng bồi thường cho khách hàng.