Repairing Phan Thiet - Dau Giay Expressway must commit to ending flooding

Lê Thanh Phong |

Phan Thiet - Dau Giay Expressway was once flooded and cars were swept away, but is being repaired very urgently.

In the early morning of July 29, 2023, heavy rain caused the section through Ham Tan district at Km25+419 of the Phan Thiet - Dau Giay highway to be deeply flooded. Cars passing through this section were submerged in water, a truck was swept to the side of the road and half of the vehicle was submerged. Many cars did not dare to drive, had to stop, causing a traffic jam of nearly 10km.

According to Mr. Dang Hung Thai - Executive Director of Phan Thiet - Dau Giay Expressway Project, there are 3 streams flowing from upstream to downstream. Along with the sudden heavy rainfall, water overflowed onto the expressway at the above location. This is an unexpected incident and will be thoroughly resolved.

There were arguments about the cause of the flooding and the Ministry of Transport has come to a conclusion. The cause was the Phan River dam upstream, 8.6km from the flooded area. In general, after dams are put into operation, the downstream flow often changes. Downstream of the Phan River bridge, the riverbed and stream have invasive vegetation, sedimentation, narrowing the flow, causing local water stagnation, leading to a rise in the water level in the culvert area, causing flooding of the road.

Recently, contractors have started building stone retaining walls, drainage culverts, reinforced concrete retaining walls, and surface drainage ditches. The reservoir project, with a capacity of 831 m3, is expected to no longer be subject to severe flooding as it once was.

We appreciate the efforts to implement the Phan Thiet - Dau Giay Expressway flood control project. However, the parties involved need to make a commitment that after the completion of the project, the expressway will no longer be flooded, causing danger to vehicles and hindering traffic.

Another thing that people are very interested in is the rest stops on the highway. According to information from the Phan Thiet - Dau Giay Expressway Management Board, this highway rest stop will be built at km 47+500 in Xuan Loc district, Dong Nai province and Ham Tan district, Binh Thuan province. The two winning bidders are the joint venture Phuong Trang Passenger Transport Joint Stock Company - Thanh Hiep Phat Company Limited, with a total project investment capital of nearly 300 billion VND.

However, the Phan Thiet - Dau Giay expressway rest stop project will take about 15 months to build, so it will not be in time to serve people traveling during this year's Tet holiday.

During Tet, the traffic on the highway is very heavy. Last year, passengers had to climb over fences to use the "free toilets" on both sides of the highway. This year, while the rest stops have not been completed, temporary rest stops should be built to serve the people.

Lê Thanh Phong
RELATED NEWS

Live football Arsenal vs Bournemouth in Premier League

|

The match between Arsenal and Bournemouth takes place at 6:30 p.m. on April 11 (Vietnam time).

Update on gasoline and oil prices on April 11: World oil prices reverse sharply

|

Update on gasoline and oil prices on April 11: In today's trading session, world oil prices reversed to decrease.

Live Nam Dinh vs Hoang Anh Gia Lai in round 18 of V.League 2025-2026

|

Live football match between Nam Dinh and Hoang Anh Gia Lai in round 18 of V.League 2025-2026 at 6:00 p.m. today (April 11).

Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to open to traffic in September

|

Hanoi - Ring Road 2.5, Dich Vong - Duong Dinh Nghe section is expected to be technically opened to traffic in early September if the site is handed over on schedule.

Explaining why the 72 billion VND irrigation project has not been handed over after many pipe bursts

|

Dak Lak - The Provincial Department of Agriculture and Environment has explained the reason for not being able to hand over the 72 billion VND irrigation project after many pipe bursts.

US declares Iran has no cards left at the negotiating table

|

US-Iran negotiations in Pakistan face many obstacles as disagreements on preconditions have not been resolved.

Proposal to include civil status services in VNeID to replace paper extracts

|

Delegate To Ai Vang (Delegation of Can Tho City) proposed to implement a one-stop shop integrating civil status services into VNeID, using VNeID to replace document extracts.

Bộ GTVT chỉ đích danh trách nhiệm vụ ngập cao tốc Phan Thiết - Dầu Giây

Xuyên Đông |

Ngày 26.4, trên cổng thông tin điện tử, Bộ Giao thông Vận tải trả lời cử tri về việc làm rõ trách nhiệm vụ ngập cao tốc Phan Thiết - Dầu Giây.

Nhiều xe mô tô vẫn chạy chui vào cao tốc Phan Thiết - Dầu Giây

Duy Tuấn |

Bình Thuận - Nhiều xe máy, xe mô tô phân khối lớn chui vào được cao tốc Phan Thiết - Dầu Giây, phóng bon bon trên cao tốc bất chấp nguy hiểm, dù tại các nút giao vào cao tốc đều có chốt gác và người trực để ngăn xe máy, người đi bộ vào cao tốc.

Chính thức kết luận nguyên nhân ngập cao tốc Phan Thiết - Dầu Giây

Hiếu Anh |

Trao đổi với Báo Lao Động tối 9.8, ông Uông Việt Dũng, Chánh văn phòng Bộ Giao thông Vận tải cho biết, đơn vị đã có kết luận nguyên nhân ngập cao tốc Phan Thiết - Dầu Giây.